Rotherham Metropolitan Borough Council

Approval of tender for upgrading & refurbishment works to 21 Reema Hollow Panel & 63 Reema Conclad Properties

Approved Committee 1 paper

Safe and Attractive Neighbourhoods (August 2010-February 2015) approved this item on Monday 31 October 2011. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

- That the tender submitted by Bramall Construction Ltd., dated 19 th September, 2011, in the sum of £695,106.00, be approved.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Safe and Attractive Neighbourhoods (August 2010-February 2015), 3 pages

Summary

To seek authority to accept a tender for the upgrading works to the external envelope of 21 no. Reema Hollow Panel properties and 63 Reema Conclad properties, at various locations in Aston, Whiston and Maltby.

Recommendations

That the tender submitted by Bramall Construction Ltd, dated 19th September 2011 in the sum of £695,106.00 is accepted. 7.0 Proposals and Details The project is for upgrading works to the external envelope of 21 no. Reema Hollow Panel properties and 63 Reema Conclad properties, at various locations in Aston, Whiston and Maltby.

This report covers approval of a contract for the above works.

A formal request to seek tenders for the works was received from Ian Smith, Technical Client Officer, Neighbourhood Investment Service. RMBC.

Five contractors were invited to tender at the request of Ian Smith following discussions with the Building Surveyor. Tender prices were as follows:

1) £695,106.00 – Bramall Construction Ltd 2) £714,573.19 – Mansells 3) £748,348.32 – George Hursts & Sons Ltd 4) £797,074.00 – Hobson & Porter 5) Geo Houlton – (Declined)

The lowest valid tender was received from Bramall Construction Ltd. This tender has been checked and found to be arithmetically correct.

The estimated costs for the proposed refurbishment works are as follows:

Tender cost £695,106.00 Contingency Sums £100,000.00 (inc in the above figure) Planning fees £885.00 Building Control Fees £1,700.00 Ecology Survey Fees £700.00 Pre Contract Professional Fees £12,910.00 Post Contract Professional Fees £38,411.50

Total £749,712.50 8.0 Finance Sufficient uncommitted capital resources to meet the costs of conversion have been identified within the Non-Traditional Investment Programme budget within the approved Housing Investment Programme 2011-12.

9.0Risks and Uncertainties A contingency sum for risk of 14% has been included within the estimate which is considered adequate for a scheme of this nature.

A delay in the time scale for the approval could have an impact on project delivery.

Building Regulations & Planning approval has already been granted for the scheme. 10.0 Policy and Performance Agenda Implications The delivery of investment works will further enhance the efforts being made to create and maintain a sustainable affordable housing offer within an area that is in demand and in supporting the long term availability of quality, well maintained homes.

NAS Service Plan Objectives

Tackling heating and insulation problems by thermally cladding non-traditional homes with poor insulation.

Corporate Plan

Helping to create safe and healthy communities where people are able to live in decent affordable homes of their choice, through targeted investment programmes in our homes.

Outcomes framework

The investment programme supports the outcomes framework as follows: Improved quality of life - in providing affordable accommodation with improved thermal efficiency Improved Health and Well being Reduced heating costs – assisting to maximise household income

11.0Background Papers and Consultation • Structural stock condition assessment of non decent homes volume one and two- August 2006 • Housing Market Assessment 2007 • Cabinet Member for Neighbourhoods Report- 30/04/07- Option appraisal of RMBC non traditional houses, flats and bungalows. • Site option appraisal of high investment non traditional built properties- July 2007 • Cabinet Member for Neighbourhoods Report- 19/05/08- Non Traditional Properties Update • Cabinet Member for Neighbourhoods report- 30/11/09 • Cabinet – 11th February 2009, Minute No:177

All correspondence is on project file: 081-000-031F

Contact Names:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval of tender for upgrading & refurbishment works to 21 Reema Hollow Panel & 63 Reema Conclad PropertiesReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Approval of tender for upgrading & refurbishment works to 21 Reema Hollow Panel & 63 Reema Conclad PropertiesThis decision
  2. Approval of tender for external works to The Lanes, Herringthorpe, RotherhamApproved
  3. Approval of Tender for the Construction of a Two Classroom Block and Alterations to the Main School Building at Laughton Junior and Infant SchoolApproved
  4. Approval of Tender for upgrading external fabric to 37 properties in Rawmarsh , RotherhamDecided
  5. Approval of Tender for upgrading external fabric to 80 properties in Swallownest, Brinsworth,Thrybergh areas of, RotherhamDecided
  6. Approval of Tender for upgrading external insulation works to 121 Properties at Thrybergh.Decided

More from Rotherham Safe and Attractive Neighbourhoods (August 2010-February 2015)

All decisions
MeetingDecisionOutcome
13 Feb 2015 Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... Noted Open
2 Feb 2015 Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. Agreed Open
2 Feb 2015 Housing Investment Programme 2014/15 update- That the report be received and its content noted. Noted Open
2 Feb 2015 Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... Noted Open
2 Feb 2015 Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... Noted Open