Minded to Grant - That the tender submitted by Hall Construction Group Ltd. dated 18th June, 2015 be accepted. Reason:- To give authority to accept a tender for upgrading works to the external envelope of 80 non- traditional properties of various construction types in Swallownest, Brinsworth and Thrybergh. The work includes the installation of external wall insulation to improve the thermal comfort of these ‘hard to heat’ properties, facia and gutter replacement and approximately 60 of the properties are to be re roofed. In doing this the investment will help also alleviate fuel poverty for the tenants. Date of Publication of the Minded to Grant - Monday, 13 th July, 2015. Representations upon the decision are invited from Councillors, members of the public, partner agencies and any interested body or individual within five working days from the date of publication and must be received by Debbie Pons [email protected] no later than 5.00 p.m. on Friday, 17 th July, 2015. Date Representations Received:- None. Representations Received:- None. Date of Commissioner Manzie’s Final - 21 st July, 2015.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
5.1The report seeks authority to accept a tender for the upgrading works to the external envelope of 80 non- traditional properties of various construction types in Swallownest, Brinsworth and Thrybergh. The work includes the installation of external wall insulation to improve the thermal comfort of these ‘hard to heat’ properties, facia and gutter replacement and approximately 60 of the properties are to be re roofed. In doing this the investment will help also alleviate fuel poverty for the tenants.
5.2The cost of the work is higher than the delegated authority of the Director of Housing Asset and Neighbourhood Services to approve and therefore requires a Commissioner decision. The work will be funded through the 2015/16 HRA capital works budget already approved as part of the HRA Business Plan. Subject to approval works will commence in July 2015, and complete in November 2015.
Recommendations
6.1That the tender submitted by Hall Construction Group Ltd dated 18th June 2015 is accepted. 7. Proposals and Details
7.1A programme of external works and insulation to improve fuel poverty has been identified through the Asset Management Strategy, for 80 non-traditional properties of various concrete panel constructions which have a some inherent structural issues. The works will include external wall insulation as cavities are minimal and hard to treat, concrete and brick repairs, new fascia, soffits and barge boards. These will be structurally repaired as part of the works prior to being over clad and insulated with a brick effect render. A number of the properties are also to be re roofed as the concrete tiles have become porous with age.
Tender Process 7.2 A tender has been offered to the market via an established EU compliant construction framework agreement’ YORBuild. Under the YORbuild Framework, the contractors on the list are all independently verified. Four contractors were invited to tender from the YORTender Portal. All tenderers returned a valid tender within the agreed timeframe.
7.3Price submissions, evaluated by the Economic Development Services (EDS), returned the following tender prices:
7.4The most competitive tender is Hall Construction Ltd. The tender sum has been checked and found to be arithmetically correct. The difference between lowest and second lowest is also seen to be very competitive, given the type of work being undertaken. Appendix 1 is a closed item as it contains the tender submission sums and total scheme costs.
7.5Having won several previous tenders for External wall insulation schemes on housing work the contractor has performed well and is also conversant with local authority requirements and those of the client. The workforce are appointed to suit the works required with use of local labour where possible.
7.6In addition to the tender sum, the Council identifies a contingency sum to safeguard against any matters arising that the Council has not disclosed in the priced specification; if no cost implication matters arise, the contingency is not spent. The scheme is being managed by an EDS Project Management Team and their fees plus specialist survey costs and contingency gives the
7.7On the basis of the above it is recommended that the contract be awarded to Hall Construction Ltd against the fixed price submission tendered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.