Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 12 December 2011. Below is the council's own wording, with the papers it was decided on.
- (1) That the revised budget position and the latest financial forecast be noted. (2) That the forecast savings and slippage on schemes within Capital Works to properties be utilised to offset forecast increased spend on other schemes within the same category.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Safe and Attractive Neighbourhoods (August 2010-February 2015), 9 pages
Summary
This report presents progress to date on the 2011/12 Capital Programme, together with a forecast outturn position to the end of the financial year based upon activity as at the end of October 2011.
Slippage from 2010/11 is incorporated into the forecast outturn position for 2011/12 and the Budget has been revised to reflect an increase in resources available as the funds not drawn down in 2010/11 have been carried forward into 2011/12.
Based upon activity to date there is a forecast under spend of £577k against the revised budget of £23.700m. The under spend will be carried forward into 2012/13 to meet the costs of schemes slipping into next year.
Recommendations
• That Cabinet Member receives and notes the revised budget position and the latest financial forecast.
• That forecast savings and slippage on schemes within Capital Works to Properties are utilised to offset forecast increased spend on other schemes within the same category. 7. Proposals and Details
Background
7.1.1 This budget report is based upon actual expenditure and commitments at the end of October 2011 (P07) which has been forecast to the end of the financial year to give a projected outturn position compared to budget.
7.1.2 The report will demonstrate two key points:
- Resources not drawn down in 2010/11 have now been carried forward as additional resources to meet increased spend in year which has arisen due to slippage in 2010/11.
- There is a forecast under spend of £577k against the revised budget position.
7.1.3 Carry Forward of Resources
The P04 (July) monitoring report which was presented to Cabinet Member on the 19th September 2011 identified that at the end of 2010/11 there had been substantial slippage on the HCA New Build and Private Sector Regeneration schemes expenditure due to the severely inclement weather during November and December 2010.
This led to 2010/11 planned spend slipping into the 2011/12 financial year, which resulted in a forecast over spend against the base budget in that year.
However, the report also identified that the resources not drawn down in 2010/11 would still be available to be carried forward into 2011/12.
This budget monitoring report incorporates the carried forward resources to present a revised budget position of £23.700m which can be seen at Appendix A.
7.1.4 The P07 monitoring position is forecasting total outturn of £23.123m against the revised budget of £23.700m as demonstrated within the table below.
Revised P07 Variance Budget Forecast £000’s £000’s £000’s Refurbishments 4,786 4,264 -522 Other capital works 4,862 4,807 -55 Total capital works to properties 9,648 9,071 -577 Fair access to all 3,339 3,339 0 Regeneration / Neighbourhood Renewal 4,012 4,012 0 Other public sector 6,701 6,701 0 Total revised capital programme 23,700 23,123 -577 The balance of this report will provide an overview of progress to date on the main spending heads of the HIP Programme.
7.2Details
7.2.1 Total Capital Works to Properties
It can be seen from Appendix A and the table above that the total forecast spend on capital works to properties is £9.071m compared to a budget of £9.648m, an under spend of £577k. This can be analysed as follows:-
Refurbishments
A total of £4.786m has been budgeted in 2011/12 to undertake refurbishment works on properties, and based upon activity to date, the forecast outturn is £4.264m, an under spend of £522k.
This is a substantial change to the P04 forecast which was projecting an overspend of £67k. The change in forecast is due to:
A high level of refusals on internal refurbishments Savings on specification as not all work required (e.g. full rewires) Slippage on external works
This has resulted in total saving of £252k on refurbishments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.