Housing Improvement Programme (HIP) 2011/12

Noted Committee 2 papers

Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 12 December 2011. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

- (1) That the revised budget position and the latest financial forecast be noted. (2) That the forecast savings and slippage on schemes within Capital Works to properties be utilised to offset forecast increased spend on other schemes within the same category.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Safe and Attractive Neighbourhoods (August 2010-February 2015), 9 pages

Summary

This report presents progress to date on the 2011/12 Capital Programme, together with a forecast outturn position to the end of the financial year based upon activity as at the end of October 2011.

Slippage from 2010/11 is incorporated into the forecast outturn position for 2011/12 and the Budget has been revised to reflect an increase in resources available as the funds not drawn down in 2010/11 have been carried forward into 2011/12.

Based upon activity to date there is a forecast under spend of £577k against the revised budget of £23.700m. The under spend will be carried forward into 2012/13 to meet the costs of schemes slipping into next year.

Recommendations

• That Cabinet Member receives and notes the revised budget position and the latest financial forecast.

• That forecast savings and slippage on schemes within Capital Works to Properties are utilised to offset forecast increased spend on other schemes within the same category. 7. Proposals and Details

Background

7.1.1 This budget report is based upon actual expenditure and commitments at the end of October 2011 (P07) which has been forecast to the end of the financial year to give a projected outturn position compared to budget.

7.1.2 The report will demonstrate two key points:

- Resources not drawn down in 2010/11 have now been carried forward as additional resources to meet increased spend in year which has arisen due to slippage in 2010/11.

- There is a forecast under spend of £577k against the revised budget position.

7.1.3 Carry Forward of Resources

The P04 (July) monitoring report which was presented to Cabinet Member on the 19th September 2011 identified that at the end of 2010/11 there had been substantial slippage on the HCA New Build and Private Sector Regeneration schemes expenditure due to the severely inclement weather during November and December 2010.

This led to 2010/11 planned spend slipping into the 2011/12 financial year, which resulted in a forecast over spend against the base budget in that year.

However, the report also identified that the resources not drawn down in 2010/11 would still be available to be carried forward into 2011/12.

This budget monitoring report incorporates the carried forward resources to present a revised budget position of £23.700m which can be seen at Appendix A.

7.1.4 The P07 monitoring position is forecasting total outturn of £23.123m against the revised budget of £23.700m as demonstrated within the table below.

Revised P07 Variance Budget Forecast £000’s £000’s £000’s Refurbishments 4,786 4,264 -522 Other capital works 4,862 4,807 -55 Total capital works to properties 9,648 9,071 -577 Fair access to all 3,339 3,339 0 Regeneration / Neighbourhood Renewal 4,012 4,012 0 Other public sector 6,701 6,701 0 Total revised capital programme 23,700 23,123 -577 The balance of this report will provide an overview of progress to date on the main spending heads of the HIP Programme.

7.2Details

7.2.1 Total Capital Works to Properties

It can be seen from Appendix A and the table above that the total forecast spend on capital works to properties is £9.071m compared to a budget of £9.648m, an under spend of £577k. This can be analysed as follows:-

Refurbishments

A total of £4.786m has been budgeted in 2011/12 to undertake refurbishment works on properties, and based upon activity to date, the forecast outturn is £4.264m, an under spend of £522k.

This is a substantial change to the P04 forecast which was projecting an overspend of £67k. The change in forecast is due to:

 A high level of refusals on internal refurbishments  Savings on specification as not all work required (e.g. full rewires)  Slippage on external works

This has resulted in total saving of £252k on refurbishments.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HIP AppendixAppendix 1 pages Download
PDF
Housing Improvement Programme (HIP) 2011/12Report 9 pages DownloadRead as text

At this meeting

Whole meeting
42Housing Improvement Programme (HIP) 2011/12This decision

On this subject at Rotherham

Search all
  1. Housing Improvement Programme (HIP) 2011/12This decision
  2. Housing Investment Programme 2012/13 - 2014/15:Garage Sites, Environmental Works, Non-Traditional Housing, Community Centre Improvements (5 Year Programme) and One-Off Property InvestmentApproved
  3. Mahon Avenue, Rawmarsh - Housing Market Renewal Pathfinder Improvement WorksDecided
  4. Thomas Street, Swinton - Housing Market Renewal Pathfinder Improvement WorksDecided
  5. St. Mary's Road - Housing Market Renewal 'Pathfinder' Improvement WorksDecided
  6. Manor Farm Estate Area - Housing Market Renewal Pathfinder Improvement WorksDecided

More from Rotherham Safe and Attractive Neighbourhoods (August 2010-February 2015)

All decisions
MeetingDecisionOutcome
13 Feb 2015 Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... Noted Open
2 Feb 2015 Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. Agreed Open
2 Feb 2015 Housing Investment Programme 2014/15 update- That the report be received and its content noted. Noted Open
2 Feb 2015 Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... Noted Open
2 Feb 2015 Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies