Housing Investment Programme 2012/13 - 2014/15:Garage Sites, Environmental Works, Non-Traditional Housing, Community Centre Improvements (5 Year Programme) and One-Off Property Investment
ApprovedCommittee1 paper
Safe and Attractive Neighbourhoods (August 2010-February 2015) approved this item on Monday 28 May 2012. Below is the council's own wording, with the papers it was decided on.
- (1) That the approach to identifying and initiating investment works described in the report be approved. (2) That the one-off property investment threshold delegated to the Director of Housing and Neighbourhood Services be increased from £20,000 to £45,000. (3) That one-off properties requiring major works in excess of £45,000 be subject to the approval of the Cabinet Member for Safe and Attractive Neighbourhoods.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Safe and Attractive Neighbourhoods (August 2010-February 2015), 10 pages
Summary
Further to the report to DLT 28.02.12 which set out the draft Three Year Housing Investment Programme 2012/13 to 2014/15; this report informs of the nature and scope of works to be undertaken in regards to:
• Garage Site Investment • Environmental Works • Non-Traditional Housing Investment • Community Centre Improvements (5 Year Programme) • One-Off Property Investment Threshold
These planned and capital works are not wholly informed by the Council’s stock condition database (Apex) and so the route to identifying the work is explained in the report along with the method of programme delivery.
Recommendations
That Cabinet member agrees:
6.1The approach to identifying and initiating investment works described in this report.
6.2To increase the one off property investment threshold that can be agreed by the Director of Housing and Neighbourhood Services from £20,000 to £45,000.
6.2To receive separate reports for consideration concerning one off properties which require major projects or works in excess of £45,000 per property are identified. 7.0 PROPOSAL AND DETAILS
Background
7.1.1 The purpose of this report is to present to Cabinet Member the proposed Three Year Housing Investment Programme (HIP) for the period 2012/13 to 2014/15 in respect of:
Garage Site Investment Environmental Works Non-Traditional Housing Investment Community Centre Improvements (5 Year Programme) One-Off Property Investment Threshold
7.1.2 The report details how the programme has been compiled and identifies how various individual schemes of work included within the programme have been drawn up using information, where applicable, from the Council’s Stock Condition database, APEX, Ward Members, Council Officers such as Housing Champions, Safer Neighbourhood Teams, Repairs Technical Officers, Building and Programme Surveyors as well as being informed by tenants, leaseholders and residents.
7.1.3 In addition to the above, the report identifies that works are being delivered via four main project activities:
1 Strategy 2 Procurement 3 Consultation and scheme development 4 Delivery
Each has been progressed in parallel; this approach ensures that the works are procured, that contractors are in place and consultation is undertaken to inform schemes of work, prior to works commencing on site.
7.1.4 Whilst the Programme presented is for a three year period, the main focus of this report will be year one, 2012/13, as subsequent years’ planned works will be reviewed on an annual basis. Total Spend in 2012/13 is anticipated to be:
Garage Site Investment - £200k Environmental Works - £500k Non-Traditional Housing Investment - £1.289m Community Centre Improvements (5 Year Programme) - £250k
7.1.5 The current investment threshold per property is £20,000. This investment threshold has been in place for several years without revision. Increasing this threshold to £45,000 will allow for decent homes, external and structural works to be carried out to miscellaneous properties, such as those appropriated from General Fund Assets, in a more efficient manner. It is not a given that all properties will be invested in; an option appraisal approach will be taken to the asset which takes into account, housing demand, property value and location. Where disposal is identified as the preferred option, Ward Member consultation and Cabinet Member approval will still be required.
7.2Details
7.2.1 The table below summarises the four programmes as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Investment Programme 2012/13: 2014/15:Garage Sites, Environmental Works, Non-Traditional Housing, Community Centre Improvements (5 Year Programme) and One-Off Property InvestmentReport
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.