Resolved
- That the report be received and the indicative 2011/12 out-turn position be noted.
Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 2 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the report be received and the indicative 2011/12 out-turn position be noted.
This report represents the indicative out-turn position for the 2011/12 Capital Programme.
As at the end of 2011/12, the final indicative spend on the HIP was £36.408m compared to a budget provision of £38.052m, an underspend of £1.644m.
The report will provide details of savings and slippage on the individual schemes of work with the overall programme, and highlights the fact that the resources not drawn down in 2011/12 will be carried forward into next year.
That Cabinet Member receives and notes the indicative 2011/12 out-turn position 7.0 Proposals and Details
7.1.1 This budget report is based upon the indicative out-turn position for the Housing Investment Programme (HIP) 2011/12.
7.1.2 The indicative out-turn position, which is subject to external audit, is total spend of £36.408m against the revised budget of £38.052m which has resulted in an underspend of £1.644m as demonstrated within the table below.
Revised Out-turn Variance Budget 2011/12 £,000s £,000s £,000s Refurbishments 4,786 4,210 -576 Other Capital Works 4,862 4,708 -154 Total Capital Works to properties 9,648 8,918 -730 Fair Access to All 3,339 3,102 -237 Regeneration/Neighbourhood Renewal 3,257 2,583 -674 Other Public Sector 6,620 6,617 -3 Total Revised Capital Programme 22,864 21,220 1,644 HRA Self-Financing Settlement 15,188 15,188 0 Total Overall Spend 38,052 36,408 -1,644
The balance of this report will provide an overview on the out-turn position on the main spending heads of the HIP Programme.
7.2Details
7.2.1 Total Capital Works to Properties
It can be seen from Appendix A and the table above that the total out-turn position on capital works to properties is £8.918m compared to the budget of £9.648m, an underspend of £730k.
This is a substantial change to the P10 forecast which was projecting an underspend of £315k. The change, at out-turn can be analysed as follows:-
Refurbishments
A total of £4.786m was budgeted in 2011/12 to undertake refurbishment works on properties and the indicative out-turn position is spend of £4.210m, an underspend of £576k. This is a change to the forecast out-turn position at P10, which was projecting an underspend of £253k.
The underspend from the P10 forecast is due to:
• An accounting adjustment of £81k which represents performance profit on capital works delivered through the external contracts. This element has been charged to the revenue element of the repairs and maintenance contract, thus resulting in savings within capital.
• The previous report identified that there has been a high level of refusals by tenants for internal refurbishment works. During the year any savings arising through refusals has been utilised to bring forward works scheduled to be undertaken during 2012/13. Whilst this has allowed us to carry out some works for our tenants, the accelerated works also experienced a high level of refusals thus generating additional savings. These savings, together with minor savings on window replacements total £242k.
The actual refurbishment works completed during 2011/12 was as follows:
• Internal refurbishments completed to 401 properties. • Roofing works to 30 properties. • External refurbishment work completed on 297 properties. • Replacement/improvement works to windows in 167 properties.
Other Capital Works
Appendix A of the report identifies that a total of £4.862m was budgeted in 2011/12 to deliver other capital works to properties and that the indicative out-turn position is spend of £4.708m and underspend of £154k.
When this is compared to the forecast out-turn position at P10, there is a minimal change of £92k. However, as can be seen within the table below there has been substantial movement within individual schemes of work.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Investment Programme 2011-12 Indicative OutturnReport | 9 pages | DownloadRead as text |
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Feb 2015 | Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... | Noted | Open |
| 2 Feb 2015 | Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. | Agreed | Open |
| 2 Feb 2015 | Housing Investment Programme 2014/15 update- That the report be received and its content noted. | Noted | Open |
| 2 Feb 2015 | Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... | Noted | Open |
| 2 Feb 2015 | Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.