Firsby Reservoir - Urgent Repair Works

Noted Committee 1 paper

Regeneration and Development noted this item on Monday 15 October 2012. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

Resolved :- (1) That the report be received and its contents noted. (2) That an exemption be granted from standing order 47.6.2 (requirement to invite two oral or written quotations for a contract with an estimated value of between £5,000 and £20,000) and the contracts be awarded in five disciplines, namely (i) dam design/safety, (ii) pumping, (iii) geotechnical engineering, (iv) diving and valve refurbishment and (v) general civil engineering, as necessary for the repair works to be undertaken at Firsby Reservoir and to ensure the safety of the reservoir. (3) That the sanction of The Mayor be sought to exempt this decision from the call-in procedure, in order to allow immediate action at Firsby Reservoir and to ensure that reservoir safety is maintained. ( nb : subsequent to this meeting, The Mayor gave the necessary authorisation to exempt this decision from the Council’s call-in procedure)
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Regeneration and Development, 2 pages

Summary

To report on subsidence at Firsby Reservoir and to seek an exemption from standing order 47.6.2 (requirement to invite two oral or written quotations for a contract with an estimated value of between £5000 and £20,000) in order that appropriate contractors and consultants be appointed to ensure reservoir safety at Firsby.

Recommendations

It is recommended that:

(i) An exemption from standing order 47.6.2 ((requirement to invite two oral or written quotations for a contract with an estimated value of between £5000 and £20,000) be granted and that contracts be awarded in five disciplines namely dam design/safety, pumping, geotechnical engineering, diving and valve refurbishment and general civil engineering as necessary for works at Firsby to ensure reservoir safety. (ii) The sanction of the Mayor be sought to exempt this recommendation from the usual call in procedure in order to allow immediate action at Firsby Reservoir to ensure reservoir safety is maintained. 7. Proposals and Details

Firsby Reservoir has been under special observation since concerns over the dam’s integrity were raised earlier this year in the section 10 inspection. On Monday 8th October subsidence was found in the dam crest. This subsidence originates within the dam structure such that structural safety of the dam is now of concern. The All Reservoirs Panel Engineer visited the site on Tuesday 9th October and has asked for a variety of measures to be taken to best ensure the immediate safety of the dam. These include draining the reservoir to a level 2m below its normal top water level and ground investigation to determine the likely structure of the dam and the possible extent of voids within it, and further analysis of the results in order to determine a plan of action to stabilise the dam structure in the short term.

Firsby has no operational drawdown equipment. Pumping will therefore be required for the required drawdown. Existing disused drawdown equipment will be re-evaluated to see if it can be brought back into operation to reduce pumping costs.

It is proposed to assemble appropriate specialists and contractors in the fields of dam design, pumping, geotechnical engineering, diving and valve refurbishment, and civil engineering in order to deal with the immediate need to ensure the safety of the dam. Specialists and contractors will be drawn from recent experience at Ulley and Thrybergh reservoirs.

8. Finance

The immediate need is expected to be approximately £100,000 across the five principal specialisms detailed in section 7. These works will be funded through existing Council Capital and Revenue funds.

9. Risks and Uncertainties

These works are essential to ensure reservoir safety. Failure to act may result in enforcement action and emergency repair by the Environment Agency.

10. Policy and Performance Agenda Implications

The services ensure the immediate safety of the dam and reservoir at Firsby Reservoir.

11. Background Papers and Consultation

Consultation has taken place with the Director of Legal and Democratic Services and with the Strategic Director of Resources on the proposed exemptions and both support this report.

Contact Names: David Phillips, Team Manager, Transportation and Highways Projects, Planning, Streetpride Department, Tel. ext. 2950, [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Firsby Reservoir: Urgent Repair WorksReport 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Firsby Reservoir - Urgent Repair WorksThis decision
  2. Firsby ReservoirApproved

More from Rotherham Regeneration and Development

All decisions
MeetingDecisionOutcome
2 Jun 2014 Minutes of the previous meetings held on 6th May 2014 and on 8th May 2014Resolved :- That the minutes of the meetings of the Cabinet Member and Advisers for Regeneration and Development, hel... Approved Open
2 Jun 2014 A633 Rotherham to Parkgate - Bus Priority MeasuresResolved :- (1) That the report be received and its contents noted. (2) That the principle of a bus and cycle only la... Noted Open
2 Jun 2014 Objections to Proposed Waiting Restrictions - Areas of Wellgate and Moorgate, RotherhamResolved :- (1) That the report be received and its contents noted. (2) That, after due consideration by Elected Memb... Noted Open
2 Jun 2014 Petition - Condition of the Carriageway - Temple Crescent, BramleyResolved :- (1) That the petition and report be received and their contents noted. (2) That the lead petitioner be in... Noted Open
2 Jun 2014 Petition - Condition of the Carriageway - Cook Avenue, MaltbyResolved :- (1) That the petition and report be received and their contents noted. (2) That the lead petitioner be in... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies