Resolved :- (1) That the report be received and its contents noted. (2) That an exemption be granted from standing order 47.6.2 (requirement to invite two oral or written quotations for a contract with an estimated value of between £5,000 and £20,000) and the contract for the works for the refurbishment of the penstocks at the Rother Valley Country Park Main Lake Reservoir be awarded to Commercial Diving and Marine Services.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
To report on progress following the Supervising Engineer’s Inspection of Rother Valley Country Park Main Lake Reservoir of 27th June 2012 and to seek an exemption from standing order 47.6.2 (requirement to invite two oral or written quotations for a contract with an estimated value of between £5000 and £20,000) in order that that Commercial Diving and Marine Services may be appointed to carry out the refurbishment of the penstocks in the penstock chamber.
Recommendations
It is recommended that:
(i) An exemption from standing order 47.6.2 ((requirement to invite two oral or written quotations for a contract with an estimated value of between £5000 and £20,000) be granted and the contract for the works for the refurbishment of the penstocks be awarded to Commercial Diving and Marine Services. 7. Proposals and Details
The annual Supervising Engineer’s statutory inspection for Rother Valley Country Park Main Lake Reservoir undertaken on 27th June revealed that one of the penstock valves to be inoperable by the ranger team. The penstocks are used to drain excess water from the lake, including at those times when the lake is flooded as part of the River Rother catchment plan. Follow up investigations and surveys have been undertaken by a specialist diving team and have determined it will be necessary that:
• A temporary sealing plate be installed on the inlet pipe within the lake. • The penstock gate removed and refurbished ‘in the dry’ • The penstock frame be refurbished insitu • The head gear be stripped down and refurbished and fixing bolts replaced as necessary.
The devised solutions and works are to be completed as soon as possible in order to prevent a more formal notice being served by the Supervising Engineer.
The investigations and surveys have developed a bespoke proposal for this situation, complicated by the fact that there is no valve on the inlet pipe within the lake. The specialist contractor appointed for the inspection and survey were Commercial Diving and Marine Services, who visited the site over two days and devised the proposals for this situation using the deep water diving expertise that they possess in what is a potentially hazardous environment.
The estimate for all of the above works is £15,450.
Rather than seek one further quotation for this specialist and bespoke work, it is proposed to exempt these works from the Council’s Standing Orders under the provisions of clause 38 on the basis of the already completed inspection and survey, the familiarity of the team with the draw off infrastructure and the best methods and procedures employed to deal with the hazards it presents. A further quotation would require a further underwater/confined spaces inspection and assessment by a second specialist team with the associated cost of such an inspection. The relatively small and one off nature of these works means that risks in respect of (lack of) value for money are very low. Also, prompt commissioning of these works will ensure that the works can be undertaken as soon as possible and the penstocks be brought back into operation.
8. Finance
For these works, estimated at £15,450, Standing Order 47.6.2 – 2 quotations - would normally apply. It is intended that these works will be funded through Council Capital funds - Maintenance Capital Investment Programme.
9. Risks and Uncertainties The bespoke nature of these works means that the scope of works may change during the works operation but this risk is low due to the extensive investigation and surveys already undertaken. Prompt commissioning of these works ensures minimised risk to health and safety due to the inoperative state of the penstocks and ensures that effective deadlines for provision will be met.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.