Resolved :- (1) That the report be received and its contents noted. (2) That an allocation of £30,750 Rotherham Economic Regeneration Fund revenue monies be approved in respect of the feasibility and investigate works for potential development projects within the Rotherham Borough area, in accordance with the details contained in the report now submitted.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
1. Meeting: Cabinet Member and Advisers for Regeneration and Development 2. Date: Monday 10th December 2012
3. Title: RERF - Rotherham Development Projects
4. Programme Area: Environment and Development Services
5. Summary This report seeks approval of an allocation of £30,750 RERF revenue towards providing a fund to provide feasibility and investigative works for potential development projects within the borough.
6. Recommendations That £30,750 of RERF revenue is approved towards feasibility and investigate work for potential development projects.
7. Proposals and Details
The fund will be used support the earlier works commissioned which will help to bring forward various projects each with its own outputs. Overall the funding will assist in bringing forward Westgate Chambers for redevelopment, Indoor/Outdoor markets, as part of the wider Tesco redevelopment, Forge Island if a decision is taken to implement option to purchase and works to improve the pedestrian route from the Rail station to Main Street. There may be other opportunities to progress other as yet unidentified projects.
With the closure of Yorkshire Forward and the ending of Single Pot funding the main source of finance to deliver the Rotherham Town Centre Renaissance has been removed.
Despite this a number of projects have been, or are being, delivered, including:- Rail Station Minster Gardens Riverside House Civic Site redevelopment.
There are still some pots of public funding available (i.e. Regional Growth Fund and Growing Places Fund) and the Council are also working much more closely with the private sector on joint projects. However, in order to attract the support and funding for these projects we need to have the projects work up to a certain level, which often requires drawings, feasibility work, site surveys, taking a site to the market, etc. Where possible work will be carried out by RMBC staff, retaining the RERF monies for those times when funding to procure work is required (which is often the case internally for architects, landscape design, valuation etc).
The application has been appraised by the RMBC Regeneration Team and been judged to be eligible to receive RERF support.
8. Finance Status of funding. Approved/ Total Awaiting Funding Approval 2012/2013 2013/2014 RERF Capital - Revenue 30,750 - 30,750 TOTAL RERF 30,750 - 30,750
Other Funding Sources - - TOTAL OTHER FUNDING - - - Grand Total 30,750 - 30,750
There is currently £33,750 of revenue money available under the RERF programme. This is sufficient to fund this project and the Work & Skills Portfolio project (£3,000), which is also being discussed at today’s meeting. The funding must be spent during 2012/13 or will be lost to RERF.
9. Risks and Uncertainties Further funding will be required to deliver the projects developed using the Fund. This will be difficult in the current economic climate, but innovative and new ways of financing the projects will be one of the issues covered by the feasibility work.
10. Policy and Performance Agenda Implications The Masterplan will contribute to the following strategic priorities under the Achieving Theme of the Community Strategy:- - Revitalise the town centre - Promote business start ups, growth and investment - Improve access and remove barriers to employment. 11. Background Papers and Consultation
Consultation will be a major part of any feasibility or development work which is carried out using the RERF monies.
A copy of the full RERF application form for this project is available on request.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.