Resolved :- (1) That the report be received and its contents noted. (2) That the corporate risk register summary, as now included with the submitted report, be noted. (3) That the current assessment of the Council’s principal corporate risks be confirmed.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Attached to this report is the current corporate risk register summary. The summary shows the risks associated with the Council’s most significant priorities and projects, and actions being taken to mitigate these risks.
The Council’s key current risks continue to relate to the financial pressures faced by the Council and the implications of the Welfare Reforms. The report summarises the management actions that are being taken to mitigate these and other risks in the register.
Risks relating to funding the capital programme, personalisation of adults care services, commissioning and highways have been removed from the corporate risk register. This does not mean these risks will no longer be monitored; rather they will now be reviewed at directorate level. They can be re-instated at corporate level at any point in time in the future if/as appropriate.
New risks relating to economic growth and public health and well-being have been added to the register and an entry has been included recognising opportunities to promote the Council’s achievements and enhance its reputation.
Recommendations
The Audit Committee is asked to:
• note the corporate risk register summary attached at Appendix A
• confirm the current assessment of the Council’s top corporate risks
• indicate any further risks or opportunities that it feels should be added to the risk register. 7 Proposals and Details
7.1Format This report contains the latest position on the Corporate Risk Register. The corporate risk register summary is attached at Appendix A. The corporate risk register summary reflects the current risk assessments for each corporate priority or project in the corporate risk register.
This covering report highlights the top inherent risks.
There are 3 overall categories of risk (RED, AMBER, GREEN) representing varying degrees of exposure. Each category contains a range of risk scores, so there are varying degrees of risk within each category. Appendix A shows the risk category and score for each priority or project included in the register before and after risk mitigation actions.
7.2Highest inherent risks The risk register summary shows risks in descending inherent risk order, to emphasize the most significant risks faced by the Authority. The top risks are:
• Managing Government budget reductions - unable to maintain key services due to budgetary limits. Budget proposals for 2013/14 have been finalised. Cabinet and Strategic Leadership Team (SLT) continue to meet on a regular basis and plan to begin early to consider the landscape for 2014/15 onwards. Ultimately, Cabinet will make decisions that ensure the Council can provide priority services within available resources. Government announcements indicate austerity measures will continue for several years yet, including further cuts for local government.
• Welfare Reforms Various Government reforms, including proposals relating to Council Tax and Benefits, could have major implications for residents and services. Corporate and partnership working groups are considering the implications and identifying actions required, and key reports are being presented to Members as appropriate.
• Unable to deliver effective Children’s Services within budget. Ongoing action is being taken by management to provide services within the budget available. Cabinet is being kept informed of the relevant financial challenges as part of the budget monitoring and budget setting processes and makes decisions accordingly.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for...
Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.