Resolved
Resolved :- That the report be received and the information noted.
Planning Board noted this item on Thursday 6 June 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the report be received and the information noted.
Pupil numbers are increasing within the Borough and creating a shortage of places available in certain areas. There is increasing pressure on school places due to the numbers of pupils and it is necessary to increase the number of school places available to meet demand. This report outlines the recent and future projects being undertaken to increase place availability within the Borough.
It is recommended that the content of the report be accepted as an overview of the current position and future direction of travel.
Proposals and Details
Pupil numbers are increasing in the Borough and there is increasing pressure on school places particularly in Key Stage 1 and it is necessary to increase the number of primary school places available in certain areas of the Borough.
The information below provides details of work carried out to date and planned to provide additional school places.
Recently Completed Consultations to increase Published Admission Numbers (PAN) include:
Expansion of Thornhill Primary (30 – 45) – 4 additional classrooms Expansion of Flanderwell Primary (30 – 45) – 4 additional classrooms and SEN unit Expansion of Aston Hall J & I (30 – 45) - 4 additional classrooms Expansion of Herringthorpe Infant and Junior schools (70 – 90) – 5 additional classrooms (2 Infant and 3 Junior)
Increase in Admission numbers at:
Treeton Primary School (37 – 45) by addition of additional classrooms Catcliffe Primary School (25 – 30) by addition of additional classrooms Sunnyside Infant and Junior Schools (80 – 90) Bramley Grange Primary School (40 – 45) Kilnhurst Primary School (28 – 30)
Total number of eventual permanent through school places created = 665 September 2013 Admissions – Potential Pressure Points and Action:
Central (South and East)
Admissions for 2012/13 and 2013/14 have been to present capacity and this trend looks to be continued. There are also steadily increasing numbers with new arrivals to the borough. Birth statistics show an increase of 58 births for entry in 2014/15.
Current proposals to cater for the increase in pupil population in the Central and surrounding area are shown below:
Herringthorpe Infant and Junior Schools (70 – 90) A modular build will provide 5 additional teaching and learning areas. A tender has been received for £1.8m and negotiations are currently on going with a contractor. Completion for October 2013. Planning permission granted 8th April 2013.
Listerdale Primary School (30 to 45 = 105 eventual through School places) Approval granted by the Cabinet Member for Children, Young People and Family Services following positive negotiations with the Governing Body on proposals to increase the admission number from 30 to 45 in FS2 and Y1 from September 2013 and subsequent FS2 year groups there after until 31st August 2016. This is with a view to expanding the school on a permanent basis by undertaking a full consultation to make a prescribed alteration to the school. The expansion will provide 4 permanent traditional built classroom 4 classrooms in total will cost approximately £800K in total and will be completed at the latest by August 2014. Design in early stages.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
School Places PlanningReport | 7 pages | DownloadRead as text |
Follow Planning Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Minutes of the previous meeting held on 8th October 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 8 th October, 2026, be ... | Approved | Open |
| 29 Oct 2026 | Development Proposals- (1 ) That , on the development proposals now considered, the requisite notices be issued and be made available on t... | Approved | Open |
| 29 Oct 2026 | Report of the Service Director for Planning, Regeneration and Transport - Whitestone Solar Farm - Nationally Significant Infrastructure Project Update- That the update be received and the contents noted. | Noted | Open |
| 8 Oct 2026 | Minutes of the previous meeting held on 17th September, 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 17 th September, 2026, ... | Approved | Open |
| 8 Oct 2026 | Development Proposals- (1) That, on the development proposals now considered, the requisite notices be issued and be made available on the... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.