Resolved
Resolved :- That the report be received and the indicative 2012/13 outturn position be noted.
Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 17 June 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the report be received and the indicative 2012/13 outturn position be noted.
This report represents the outturn position for the 2012/13 Capital Programme.
As at the end of 2012/13, the final spend (subject to external audit) on the Housing Investment Programme was £21.890m compared to a budget provision of £22.777m, an underspend of £887k (-3.90% variance).
The report will provide details of savings and slippage on the individual schemes of work with the overall programme, and highlights the fact that the resources not drawn down in 2012/13 will be carried forward into next year.
That Cabinet Member receives and notes the 2012/13 outturn position. 7.0 Proposals and Details
7.1.1 This budget report is based upon the outturn position for the Housing Investment Programme (HIP) 2012/13.
7.1.2 The outturn position, which is subject to external audit, is total spend of £21.889,938 against the revised budget of £22.777,199 which has resulted in an underspend of £887,261 as demonstrated within the table below.
*Quarter 3 Final Out-turn Variance Budget Budget 2012/13 Reported 12/13 £,000s £,000s to Cabinet £,000s
Refurbishments 12,094 11,987 12,339 353 Other Capital Works 5,656 5,317 4,492 -824 Total Capital Works to properties 17,750 17,303 16,832 -471 Fair Access to All 3,504 3,109 3,254 145 Regeneration/Neighbourhood Renewal 2,470 1,829 1,614 -214 Other Public Sector 934 535 188 -346
Total Revised Capital Programme 24,658 22,777 21,889 -887
*It should be noted that the last forecast reported to Cabinet for Safe and Attractive Neighbourhoods (18th February 2013 - Minute No. 61 refers) was at Quarter Three Outturn. In the last quarter the budget was revised from £24.658m to £22.777m.
The revisions to the budget from Quarter 3 to the Final Budget were for the following reasons: • Extreme weather events of heavy snow and sustained low temperatures below 5 degrees impacted adversely on Capital Works. • Window and door supply chain issues resulted in significant programme revision. • Private sector schemes at Canklow and Dinnington were re-profiled to accommodate protracted legal procedures • A number of strategic property acquisitions to generate new council homes were deferred to 13/14.
The balance of this report will provide an overview on the £887k (-3.90% variance) underspend outturn position against Final Budget on the main spending heads of the HIP Programme 2012/13.
7.2Details 7.2.1 Capital Works to Properties
Appendix A provides the full programme breakdown of budget, outturn and variance by project line and should be referred to in conjunction with the following explanations. 7.2.2 Refurbishments (Budget £10.884m Outturn £9.718m Variance £-1.165m)
Refurbishments is comprised of Internal Works (Decent Homes) and External Works (Roofing, pointing, cladding).
• Internals: Previous report identified that there has been a high level of refusals by tenants for internal refurbishment works. During the year any savings arising through refusals has been utilised to bring forward works scheduled to be undertaken during 2013/14. Tenant access issues resulted in a modest underspend at year end.
• Externals: Major capital investment to external elements of dwellings such as replacement roofs and external works to blocks of flats was reduced in the last quarter as monitoring across the programmes revealed that the forecast for central heating replacement was under pressure; investment was increased in boilers in order to reduce revenue repair costs.
Actual Internal refurbishments completed to 457 properties. Actual External refurbishment work completed on 432 dwellings and 77 blocks of flats.
7.2.3 Windows (Budget £183,004 Outturn £40,651 Variance £-142,353)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Investment Programme 2012-13 Indicative OutturnReport | 12 pages | DownloadRead as text |
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Feb 2015 | Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... | Noted | Open |
| 2 Feb 2015 | Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. | Agreed | Open |
| 2 Feb 2015 | Housing Investment Programme 2014/15 update- That the report be received and its content noted. | Noted | Open |
| 2 Feb 2015 | Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... | Noted | Open |
| 2 Feb 2015 | Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.