Proposed Shared Use Footway: A633 corridor between St Ann's Roundabout and Great Eastern Way Roundabout, Parkgate

Noted Committee 4 papers

Regeneration and Development noted this item on Monday 2 September 2013. Below is the council's own wording, with the papers it was decided on.

Item38

Resolved

- (1) That the report be received and its contents noted. (2) That the o bjection to the proposed scheme be not acceded to. (3) That approval be granted for detailed design work to be undertaken in relation to this proposed shared use footway scheme along the A633 between Rotherham and Parkgate and for the scheme to be implemented during the 2013/2014 financial year. (4) That the footways identified on drawings numbered 129/ LSTF /A633.consult1 and 129/ LSTF /A633.consult2 be designated as shared pedestrian and cycle use under Sections 66(4) and 65(1) of the Highways Act 1980. (5) That negotiations commence with land owners for the purchase of land to enable the proposed shared use footway to be widened to 3.0 metres in the locations shown on plan number 129/ LSTF /A633/LAND/01 and subject to completion of successful negotiations for the land to be purchased, the detailed design be undertaken and works be implemented before the end of the 2014/2015 financial year.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Regeneration and Development, 4 pages

Recommendations

It is recommended Cabinet Member resolve that:

i) The objection to the proposed scheme be not acceded to;

ii) Approval be given for detailed design work to be undertaken in relation to this proposed scheme, and for the scheme to be implemented in the 2013/2014 financial year.

iii) The footways identified on Drawing Numbers 129/LSTF/A633.consult1 and 129/LSTF/A633.consult2 be designated as shared pedestrian and cycle use under Section 66(4) and 65(1) of the Highways Act 1980.

iv) Negotiations commence with Land Owners for purchasing land to enable the proposed shared use footway to be widened to 3.0 metres in the locations shown on plan number 129/LSTF/A633/LAND/01 and subject to successful negotiations for land to be purchased, detail design to be undertaken and works be implemented before the end of the 2014/2015 financial year.

Page 1 7. Proposals and Details In 2010 the Government announced the creation of the Local Sustainable Transport Fund (LSFT) and made £560 million of funding available nationally for projects over a four year period to 2014-15. South Yorkshire successfully bid for £24.6M from the fund. This success of the bid was the subject of a report to Cabinet Member on 28 August 2012, Minute 33 refers, when the programme of LSTF funded projects to be delivered over 2012-15 was approved.

One of the schemes within the successful bid is to improve cycling connectivity between employment opportunities and residential areas in the Town Centre and Parkgate / Rawmarsh area.

The proposed scheme involves the creation of an off carriageway footway/cycleway by designating the existing footways as ‘shared use’ between the St Ann’s and Great Eastern Way roundabouts.

This would involve the following changes to the highway: • Widening of some sections of existing footway to achieve a 3.0m wide shared use footway/cycleway. In certain areas this will require the purchase of land in private ownership, where agreement can be reached, to create a 3.0m wide shared use footway/cycleway • Designating other sections of footway as shared use, nominal width of these sections is 2.0m • Increasing the height of bridge parapets where these are adjacent to the proposed shared use footway/cycleway • Conversion of existing Puffin/Pelican pedestrians crossings on St Ann’s Road, at Forge Way (access to BQ) and close to the Parkgate shopping centre into Toucan crossings so that these can be used by cyclists • Improvement will be made to the crossing of side roads to reduce the width that pedestrians and cyclist have to cross • De-cluttering of existing street furniture within the footways

Detail of the scheme is shown on drawing numbers 129/LSTF/A633.consult1 and 129/LSTF/A633.consult2 attached as Appendix A and B.

Details of the areas of land required to widen into land in private ownership are shown on drawing number 129/LSTF/A633/LAND/01 attached as Appendix C.

The A633 is a narrow highway with physical constraints and as such the footway cannot be widened to 3.0m in certain sections. These are: • River Don and Railway Bridges • Underneath the existing railway bridge to the north of Retail World Roundabout where the overall width available between the two parapet walls is relatively narrow and as such, signing will be installed informing cyclists to dismount for this short section.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A633 cycle link: Appendix AAppendix 1 pages Download
PDF
A633 cycle link: Appendix BAppendix 1 pages Download
PDF
A633 cycle link: Appendix CAppendix 1 pages Download
PDF
Proposed Shared Use Footway: A633 corridor between St Ann's Roundabout and Great Eastern Way Roundabout, ParkgateReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Proposed Shared Use Footway: A633 corridor between St Ann's Roundabout and Great Eastern Way Roundabout, ParkgateThis decision
  2. Proposed extension of existing shared use footway on Bawtry Road (between the Worrygoose and Rotherway roundabouts) towards CanklowNoted
  3. Proposed Shared Use Footpath Improvements - Footpath No.23 at SwintonNoted
  4. B6098 Bolton Road, Manvers; Ward 19 Wath - Proposed New Shared Use Pedestrian / Cycle FootwayNoted

More from Rotherham Regeneration and Development

All decisions
MeetingDecisionOutcome
2 Jun 2014 Minutes of the previous meetings held on 6th May 2014 and on 8th May 2014Resolved :- That the minutes of the meetings of the Cabinet Member and Advisers for Regeneration and Development, hel... Approved Open
2 Jun 2014 A633 Rotherham to Parkgate - Bus Priority MeasuresResolved :- (1) That the report be received and its contents noted. (2) That the principle of a bus and cycle only la... Noted Open
2 Jun 2014 Objections to Proposed Waiting Restrictions - Areas of Wellgate and Moorgate, RotherhamResolved :- (1) That the report be received and its contents noted. (2) That, after due consideration by Elected Memb... Noted Open
2 Jun 2014 Petition - Condition of the Carriageway - Temple Crescent, BramleyResolved :- (1) That the petition and report be received and their contents noted. (2) That the lead petitioner be in... Noted Open
2 Jun 2014 Petition - Condition of the Carriageway - Cook Avenue, MaltbyResolved :- (1) That the petition and report be received and their contents noted. (2) That the lead petitioner be in... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies