Resolved :- (1) That the report be received and its contents noted. (2) That the latest financial projection against budget for the 2013/14 financial year, for the Environment and Development Services Directorate, based on actual income and expenditure to 31st July 2013, be noted. (3) That the report be referred to the Self Regulation Select Commission for information.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
To report on the performance against budget for the Environment and Development Services Directorate Revenue Accounts at the end of July 2013 and to provide a forecast outturn for the whole of the 2013/14 financial year.
Members are asked to note the forecast outturn position of an overspend of £856k for the Environment & Development Services Directorate based on expenditure and income as at July 2013.
Recommendations
That the Cabinet Member notes the latest financial projection against budget for the year based on actual income and expenditure to the end of July 2013, and that this report is referred to the Self Regulation Overview and Scrutiny Select Commission for information. 7 Proposals and Details
7.1.1 Cabinet Members receive and comment upon budget monitoring reports on a monthly basis. This report reflects the position against budget for the period 1 April 2013 to 31 July 2013.
7.1.2 The table below summarises the forecast outturn against approved budgets for each service division:
Division of Service Net Forecast Variation Variation Budget Outturn
£000 £000 £000 % Business Unit 748 746 -2 Regeneration, Planning 7,452 8,040 +588 and Cultural Services Streetpride 29,354 29,624 +270
Total Environmental and 37,554 38,410 +856 2.27% Development Services
Following the July cycle of budget monitoring the Directorate has identified that it is likely to be overspent by £856,000 (2.27%) against its total net revenue budget of £37,554,060. All possible actions to mitigate this are being taken.
7.1.3 The details below offer explanations of the material variances by Division of Service.
Business Unit (-£2k)
The Business Unit is forecasting a small under spend of -£2k.
Regeneration, Planning and Cultural Services (+£588k)
Regeneration and Planning (£254k+)
Planning Services have a pressure of £274k+, from Land Charges £147k+ ( £127k+ of this was identified by Internal Audit for monies due to HMRC re Vat, £20k+ pressure is due to loss of income). The remaining £127k+ is due to a shortfall of income from planning applications. There are further smaller pressures across the Service of £26k+. These pressures are being mitigated by savings from Business Centres £39k-, due to higher than expected occupancy levels, and savings £7k- within Rotherham Investment Development Office (RIDO) from staff vacancy. Customer and Cultural Services (£334k+)
Heritage Services are projecting a £55k+ pressure due to the change in venue for celebratory services to Clifton Park Museum. Cultural Services is now showing an additional £30k+, due to unfunded Business Rates for various sites which it is unlikely can be contained in 2013/14. This is being partially mitigated by £15k- savings within Theatres and Arts. There is an unachievable saving from 2012/13 of £80k+ (the remaining element of the £250k savings target) and a further £120k+ from the 2013/14 savings proposals remains outstanding. There is a pressure within the Contact Centre of £64k+, work is ongoing to mitigate this.
Streetpride (+£270k)
Network Management is projecting a pressure of £85k+.
Parking Services have a pressure of £137k+ due to inflated income assumptions and a downturn in customers requiring parking permits, and customers seeking alternative parking arrangements. This figure has been mitigated by a reduction in TUPE payments to South Yorkshire Police. Further pressures within Network Management total £15k+, which are being offset by total savings of £67k-, from energy savings £37k- and one off additional income on Streetworks Enforcement £11k- and savings on Highways Maintenance £19k-.
Waste Services £276k+
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.