Resolved :- (1) That the report be received and its contents noted. (2) That the transfer of the gardening scheme to Age UK (Rotherham), the expansion of the scheme and the provision of an enhanced service to appropriate Council housing tenants, which have enabled caretaking staff to focus on core responsibilities, be noted.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Improving Places Select Commission, 4 pages
Summary
Up until 2nd June, Rotherham MBC provided a partial gardening scheme to some vulnerable tenants across the borough. The service, delivered by Morrison FS, was insufficient and impacted on the contractor’s core work of delivering estate based caretaking services. The service was transferred to Age UK, to ensure that it could provide an enhanced service to existing customers and have the potential to expand in line with demand.
This report provides detail on the alternative delivery arrangements implemented to alleviate these issues.
Recommendations
That Improving Places Overview and Scrutiny Select Commission
• Note the decision to expand the gardening scheme to enable it to provide an enhanced service to appropriate council housing tenants, and enable caretaking staff to focus on core responsibilities. 7. Background and Details
Up until 2nd June 2013, Rotherham MBC provided a partial gardening scheme to help Council tenants over 65 and those with disabilities of any age with basic gardening, for example mowing the lawn and trimming hedges. The scheme was only open to people who did not have a relative to help them.
The scheme was at full capacity with 185 tenants receiving a basic gardening service, there were also 18 tenants on the waiting list. Tenants paid £10 - £20 per visit and received 2 – 3 cuts per annum.
Following the transfer of the repairs & maintenance service to external contractors, the gardening scheme has been delivered by Morrison FS. Morrison FS ran the scheme using estate based caretakers rather than employing dedicated gardeners as the scheme was only needed between March and November (the growing season).
Up until March 2013 the caretaking service itself was largely reactive, relying on individual reports of problems as a means of allocating work. As a consequence of this approach there was no routine scheduled maintenance of estate and garage sites by the caretaking service. In this context it was possible to prioritise gardening within the caretakers workloads. However following a review of the caretaking service it was felt that a reactive approach was inadequate as work was only being undertaken if it was identified and reported. As a means of improving the quality of estates, a cyclical planned work programme was introduced borough wide. This approach meant it was difficult to release the 2 caretakers required for the gardening scheme.
As well impacting on cyclical caretaking works, there were also other issues with how the scheme was being delivered;
• Not enough capacity to maintain gardens to desirable standard i.e. grass cutting was relatively ad hoc and resources not sufficient to cut at least every six weeks • The service was heavily subsidised by RMBC i.e. cost of two caretakers on a seasonal basis (March to November). This introduces equity issues for tenants in effect paying for a caretaking service they did not receive. • Poor income recovery by Morrison FS who did not have the resource to chase debts from tenants who didn’t pay upon completion of works • No assessment criteria. (in effect it was first come first served system) • MFS were unable to accept new requests for service due to their limited capacity • No process for informing when tenancy ended.
As the roll out of the cyclical works programme was due to commence in April 2013 and with the start of the growing season, a review of the gardening scheme was urgently needed.
3 options were initially identified for the continuation of the garden scheme;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.