Approval of tender for a seventeen classroom building at Wickersley School and Sports College.
NotedCommittee1 paper
Children, Young People and Families' Services noted this item on Wednesday 13 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That the report be received and its contents noted. (2) That the tender submitted by George Hurst Ltd., in the sum of £2,400,274.44 (dated 4 th November 2013) and the total project cost of £3,027,130.94, as detailed in the report now submitted, be approved in respect of the construction of the new school building at the Wickersley School and Sports College.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Children, Young People and Families' Services, 4 pages
Summary
To seek authorisation and acceptance of a tender for the development of a 17 classroom building at Wickersley School and Sports College, including the provision of SEN classrooms, reception area and circulation space.
Recommendations
That the Cabinet Member for Children, Young People and Families’ Services accepts the tender submitted by George Hurst Ltd in the sum of £2,400,274.44, dated 4th November, 2013, and the total project approval of £3,027,130.94, under his Delegated Powers. 7. Proposals and Details
This report covers approval of a contract to provide a new development of accommodation and facilities consisting of 17 classrooms, reception area and circulation Space at Wickersley School and Sports College. The teaching space will be located within a stand alone building based on 3 floors and situated within the existing grounds in a prominent position facing Bawtry Road.
Wickersley School and Sports College is rated by Ofsted as an Outstanding school and has attracted an increase in numbers of pupils wanting to attend. There has also been a large housing development in Flanderwell where children from this development now attend Flanderwell, Bramley Sunnyside and Bramley Grange Schools, which are the feeder schools to Wickersley School and Sports College.
The number on roll at Wickersley School and Sports College is now 2018 (as of 23rd October, 2013) and it is likely to approximately 2100 or even 2150. The School’s admission’s number is 300 and they constantly, throughout the year, have many applications in all year groups. They are thus running at around 310 per year group and 320 would be a sensible and fairer admissions number.
Wickersley School and Sports College also have the most successful 6th form of the Rotherham Secondary schools and currently have 473 in the sixth form at the moment. This will soon top 500 with the possibility of 550 as a plateau mark. Hence the figures lead to 1600 (11-16) with 550 (16-18) 6th formers which leads to a “full” figure of 2150; 300 more students than the PFI new build capacity number of 1850.
The Planning Application has been submitted with a view to continuing the development out of the ground once approval has been granted. The ground works and enabling works will continue at risk while the planning application is approved. The aim is for the building is to be a modern bright building maximising teaching space which will include current IT facilities and sustainable materials, that is considerate to the existing environment in terms of design and space, using energy saving materials. The design of the building is to create a stimulating, exciting and friendly school environment that will link in well with the existing schools teaching vision.
It is proposed that the contract be awarded to George Hurst Ltd as procured through the Yorbuild Contractors Framework through a Rotation tender.
The submitted tender price from George Hurst and Sons is £2,400,277.44.
G Hurst has been working closely with the project design team at risk because of the tight delivery programme. The programme for the work is a start on site date of the 18th November with a completion date of 25th October 2014.
The benefit of early contractor appointment is the early involvement of the contractors supply chain, design advice, and securing best value through early supply chain management.
This framework requires the operation of an Employment and Skills Plan (ESP), providing opportunities such as a number of apprentice weeks, school visits and qualifications gained. The ESP for this project has been agreed and delivery will be monitored.
George Hurst holds a valid CIS certificate and is also part of the Considerate Contractors Scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children, Young People and Families' Services at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.