Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 3 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That the spend and forecast position to the end of Period 10 (January, 2014) be noted. (2) That the total slippage of £1,263,067 be approved. (3) That the use of £362,853 of Capital receipts to fund reduction of Private Sector Adaptations backlog be approved.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Safe and Attractive Neighbourhoods (August 2010-February 2015)
Summary
This report provides an update of the Housing Investment Programme 2013-14 to end of Period 10 January 2014.
As at the end of Period 10 January 2014, total spend on the Housing Investment Programme was £15,631,246 compared to a budget provision of £17,878,163 representing an under spend to date of £2,246,917 (-12.5%) variance against planned expenditure.
The report will provide details of savings and slippage on the individual schemes of work within the overall programme, and highlights the fact that the resources not profiled to be drawn down in 2013/14 will be carried forward into next financial year.
Recommendations
That Cabinet Member receives and notes the spend and forecast position to the end of Period 10 January 2014.
The Cabinet Member approves total slippage of £1,263,067.
The Cabinet Member approves use of £362,853 of Capital receipts to fund reduction of Private Sector Adaptations backlog.
Page 1 of 10 7.0 Proposals and Details
7.1.1 This budget report is based upon the outturn position for the Housing Investment Programme (HIP) up to Period 10 January 2014.
7.1.2 There has been a total spend of £15,631,246 against the revised budget of £17,878,163 which has resulted in an under spend to end January 2014 of £2,246,917.
2013-14 2013-14 Actual Forecast Forecast Budget £ Revised spend to spend to Variance to end Budget £ P10 £ 31 March March 2014 £ 14 £
Refurbishments 14,303,000 14,609,863 5,196,763 12,408,782 -2,201,081 Other Capital Works 9,934,000 10,377,546 5,267,340 10,534,216 156,670 Sub Total - Capital 24,237,000 24,987,409 10,464,103 22,942,998 -2,044,411 Works to properties Fair Access to All 3,091,000 3,784,215 2,552,137 3,808,361 24,146 Regeneration/Neigh 2,960,000 3,398,624 1,922,029 3,263,613 -135,011 bourhood Renewal Other Public Sector 2,166,000 725,335 692,978 740,729 15,394
Total Revised 32,454,000 32,895,583 15,631,246 30,755,701 -2,139,882 Capital Programme
There has been a total increase in forecast spend to 31st March 2014 within month of £1,063,420. This has reduced the forecast underspend from £3,203,302 to £2,139,882 prior to slippage.
7.2Details 7.2.1 Housing Improvement Programme 2013-14 Capital Works
Appendix A provides the full programme breakdown of budget, forecast outturn, variance and slippage by project line and should be referred to in conjunction with the following explanations.
Refurbishments is comprised of Internal Works (Decent Homes) and External Works (Roofing, pointing, cladding). Total spend to the end of January 2014 was £5,196,763.
The existing programme primarily focuses on External works to dwellings such as replacement roofs, external works to blocks of flats and replacement of facsia’s, soffits and rainwater goods. The programmes have taken longer than anticipated to tender and mobilise, this has resulted in reduced forecast spend. Discussions have concluded with Keepmoat, resulting in an increased scope of works to now include full replacement of fascia boards and felt membrane beneath tiles abutting rainwater goods. This has subsequently increased spend forecasts on the fascia’s, Page 2 of 10 soffits and bargeboard replacement programme so reducing the forecast underspend from P9 to P10. This financial year we have completed improvements to 1,714 properties through this programme.
7.2.3 Other Capital Works (Revised Budget £10,377,546 Forecast Outturn £10,534,216 Variance £156,670)
The sections below, breakdown individual spend within the Other Capital Works budget. Collectively across all projects there has been an increased forecast spend within month of £223,620.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.