Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 16 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That the report be received and its contents noted. (2) That the year end out-turn position for the Housing Investment Programme 2013/2014, as at 31st March 2014, as detailed in the report now submitted, be approved. (3) That the slippage of £730,800 allocated resources from 2013/14 to 2014/15, as detailed in the report now submitted, be approved.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Safe and Attractive Neighbourhoods (August 2010-February 2015), 9 pages
Summary
This report provides details of the year end out-turn position for the Housing Investment Programme 2013-14 at 31 March 2014.
As at the end of Period 12 March 2014, total spend on the Housing Investment Programme was £29,058,584 compared to a budget provision of £31,687,516 representing an under spend of £2,628,933 (-8%) against planned expenditure.
The report will provide details of savings and slippage on the individual schemes of work within the overall programme.
Recommendations
That Cabinet Member receives and notes the spend position to the end of Period 12, 31 March 2014.
That Cabinet Member approves the slippage of £730,800 resources from 2013-14 to 2014-15 as detailed within the body of the report. 7.0 Proposals and Details
7.1.1 This budget report is based upon the outturn position for the Housing Investment Programme (HIP) up to Period 12 March 2014.
7.1.2 There has been a total spend of £29,058,584 against the revised budget of £31,687,516 which has resulted in an under spend to the end March 2014 of £2,628,933.
2013-14 2013-14 2013-14 Actual Forecast Original Revised Revised spend to Variance to end Budget £ Budget £ Budget £ P12 £ March 2014 £ Jan 14
Refurbishments 14,303,000 14,609,863 14,109,863 11,455,683 -2,654,180 Other Capital Works 9,934,000 10,377,546 9,821,069 10,096,931 275,862 Sub Total - Capital 24,237,000 24,987,409 23,930,932 21,552,614 -2,378,318 Works to properties Fair Access to All 3,091,000 3,784,215 4,002,068 3,911,977 -90,091 Regeneration/Neigh 2,960,000 3,398,624 3,029,181 2,902,844 -126,338 bourhood Renewal Other Public Sector 2,166,000 725,335 725,335 691,149 -34,186
Total Revised 32,454,000 32,895,583 31,687,516 29,058,584 -2,628,933 Capital Programme
There has been a total reduction between forecast and actual spend to 31st March 2014 of £1,180,994. This has increased the underspend to - £2,628,933.
7.2Details 7.2.1 Housing Improvement Programme 2013-14 Capital Works
Appendix A provides the full programme breakdown of budget, actual outturn, and variance by project line and should be referred to in conjunction with the following explanations.
Refurbishments is comprised of Internal Works (Decent Homes) and External Works (Roofing, pointing, cladding).
The programme focused on External works to dwellings such as replacement roofs, external works to blocks of flats and replacement of facsia’s, soffits and rainwater goods. The programmes have taken longer than anticipated to tender and mobilise, this has resulted in reduced spend. This financial year we have completed improvements to 1,376 properties through this programme. 7.2.3 Other Capital Works (Revised Budget £9,821,069 Outturn £10,096,931 Variance £275,862)
The sections below, breakdown individual spend within the Other Capital Works budget.
Total spend to the end of March 2014 was £206,617. This project includes the completion of bin stores, paths and landscaping works around the Pike Road area and is fully complete.
7.2.5 Other Environmental Works (Revised Budget £1,130,574 Outturn £921,118 Variance -£209,456)
Total spend was £921,118. There has been a reduction in actual spend from P11 forecast of -£227,158. This was a result of delays in tender for a number of schemes and ongoing leasehold consultation.
A variety of environmental schemes are now complete and include:
Briery Walk, Munsbrough
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.