CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council
Commissioner Kenny's Meeting, Monday 3 August 2015

Site for a town centre HE Campus.

Approved Committee 2 papers

Commissioner Kenny's Meeting approved this item on Monday 3 August 2015. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Minded to Grant Decision :- (1) That the in principle disposal of the Doncaster Gate site, or part of, to Rotherham College be approved on terms to be agreed. (2) That the disposal and terms for the disposal be delegated to the Director of Housing, Asset Management and Neighbourhood Services. (3) That upon completion of negotiations, a report be submitted to Commissioner Kenny for a final decision on the disposal of the site. Date of Publication of the Mind to Grant Decision :- Monday, 3 rd August, 2015. Representations upon the decision are invited from Councillors, members of the public, partner agencies and any interested body or individual within five working days from the date of publication and must be received by Hannah Etheridge [email protected] no later than 5.00 p.m. on Monday, 10 th August, 2015. Representations received :- None received. Date of Commissioner Kenny’s final decision :- 11 th August, 2015.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Commissioner Kenny's Meeting, 4 pages

Summary

6.1The purpose of this report is to seek in principle approval for the disposal of the Doncaster Gate site to Rotherham College for the construction of a Higher Education (H.E.) Campus.

Recommendations

7.1That Commissioner Kenny agrees:-

7.2The in principle disposal of the Doncaster Gate site, or part of, to Rotherham College on terms to be agreed.

7.3That the disposal and the terms for disposal is delegated to the Director of Housing, Asset Management and Neighbourhood Services.

Background

8.1Rotherham is the only town, of significant size, within the Sheffield City Region without a Higher Education Centre, which partially contributes to level 4 and above attainment in Rotherham being 12.7 percentage points below the national average and 4.8 percentage points below the regional average. This level of underachievement needs to be addressed to provide the skilled workforce necessary to attract inward investors and grow existing businesses.

8.2Rotherham College currently has 335 students studying on higher education programmes including Computing and Systems Development, Applied Computing, Mechanical Engineering, Electrical and Electronic Engineering, Graphic Design, Production – Specialist Make Up. The College has proactively driven the development of Higher Education within the confines of HEFCE’s funding constraints and the significant increase in student numbers has led to a 53% increase in funding over a 3 year period. For the 2015/16 academic year the HEFCE constraints have been removed and the College has developed further Higher Education programmes to continue its programme of developing high quality local provision. The College has ambitious plans to double the size of the HE population in 3 years and the HE Campus is needed to facilitate this.

8.3In June 2014 the College underwent its QAA Higher Education Review and received an excellent report on the quality of its management and delivery of the provision. The College plans to build on this excellent reputation to further extend its range of qualifications from level 4 through to level 6.

8.4Local businesses will be at the heart of the campus, with provision being industry led rather than academic. They will be involved in establishing, informing and delivering the project for Rotherham.

Building and site requirements

8.5As there will be crossover of staff delivering current FE provision and some sharing of existing vocational equipment and facilities; the HE Campus needs to be in close proximity to the College’s existing buildings. Five minute’s walk is the figure quoted.

8.6Assuming that the Campus could eventually house 1,000 students, and that certain specialist activities can be delivered within the existing College buildings, then the Campus will require a gross internal floor area of around 4,100 m2.

8.7The preference is for the building to be open by September 2017 for the 2017/18 academic year, although there is flexibility to put back to 2018/19 if it is essential. The requirement of the Capital Skills funding is that work must start on site by no later than September 2016.

8.8With these requirements, plus a preference for an RMBC owned site to keep the process as simple as possible, there are 3 potential sites:-

• The upper part of the Drummond Street car park • As part of a redevelopment of the Markets Complex • Doncaster Gate

8.9All the sites have pros and cons, which are set out in the table below.

Site Pros Cons Drummond Street Only requires 40% of car park with Perception that RMBC are cutting back on current average usage is about 60%. car parking with impact on local business.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PJW HE Campus report: Cmmr KennyReport 4 pages DownloadRead as text
PDF
Site for a town centre HE Campus.Decisions 2 pages Download

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Site for a town centre HE Campus.This decision
  2. Recommendation from cabinet - council delivery of new homes on rotherham town centre sitesApproved
  3. Recommendation from cabinet - swinton town centre redevelopment - development brief and acquisition of integral siteApproved
  4. Swinton Town Centre Redevelopment - Development Brief and Acquisition of Integral SiteApproved
  5. Weirside (formerly Westgate Demonstrator Project - Site 4), Rotherham Town CentreApproved
  6. Upfilling earthworks operation and raising of site levels at land at Don Street, Rotherham Town Centre for R. U. Estates Ltd. (RB2011/0426)Approved

More from Rotherham Commissioner Kenny's Meeting

All decisions
MeetingDecisionOutcome
11 Jan 2016 Decision sheet and minutes from the previous meeting held on 7th December, 2015.The decision sheet and minutes of Commissioner Kenny’s last meeting held on 7 th December, 2015, were considered and ... Decided Open
11 Jan 2016 Response to petition regarding disposal of land at Catcliffe.Commissioner Kenny requested further work on the submitted report before making her decision. The updated report woul... Decided Open
11 Jan 2016 Response to consultation on the Sheffield Local Plan.Minded to grant decision: - (1 ) That the consultation response within Appendix One be endorsed for submission to She... Approved Open
7 Dec 2015 Decision sheet and minutes of the previous meeting held on 2nd November, 2015.The decision sheet and minutes of Commissioner Kenny’s last meeting held on 2 nd November, 2015, were considered and ... Decided Open
7 Dec 2015 RMBC Market Fees and Charges Report - November 2015.Minded to grant decision: - That the 2015/2016 Market Fees and Charges be approved, as set out in Appendix One includ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies