Resolved
- That the Highways Management Policy statement, Strategy and the Highway Asset Management Plan ( HAMP ) covering the period 2015-2021 be approved and adopted. Mover:- Councillor Read Seconder:- Councillor Watson
Council Meeting approved this item on Wednesday 21 October 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the Highways Management Policy statement, Strategy and the Highway Asset Management Plan ( HAMP ) covering the period 2015-2021 be approved and adopted. Mover:- Councillor Read Seconder:- Councillor Watson
1. Council adopts the Highways Management Policy statement, Strategy and the HAMP covering the period 2015-2021.
List of Appendices Included
1. Highway Asset Mgt Policy
2. Highway Asset Mgt Strategy
3. Link to Highway Asset Mgt Plan 2015-2021 Background Papers
Highway Infrastructure Asset Management Guidance Highways Maintenance Efficiency Programme (HMEP). DfT Local Highways Maintenance Capital Block Funding 2015/16 – 20/21 Local Maintenance Capital Funding self-assessment questionnaire and guidance
Consideration by any other Council Committee, Scrutiny or Advisory Panel The report will be presented to the Improving Places Select Commission on the 14th October 2015.
Council Approval Required Yes
Exempt from the Press and Public No Title Highway Asset Management Policy, Strategy and Plan 2015-2021
1.1Council adopts the Highways Management Policy statement, Strategy and the Highway Asset Management Plan (HAMP) covering the period 2015- 2021.
2.1The Council is responsible for maintaining approximately 700 miles of roads and 1,300 miles of footways and Public Rights of Way. The highway network is the Council’s single biggest asset with a value of around £1.726b (gross replacement value) – see table 1.
Table 1: Size and value of major highway assets
Estimated Depreciated Gross Replacement Asset Type Quantity Replacement Cost (DRC) Cost (£m) (£m) Carriageways 1,143 km £1,257m £1,202m Footways 1,689 km £219m £192m 45,500 chambers, gullies etc. and 35 Included in Included in Drainage km of drainage carriageway carriageway pipes/chambers costs costs
Street 35,216 street lights Lighting/Furniture £72.5m £67m columns 185 structures - bridges, culverts and Structures £164m £157m underpasses
107 traffic signalised junctions and Traffic Signals £13.5m £6m pedestrian crossings
Total Cost £1.726bn £1,625bn 2.2 The Council’s approach to highway maintenance is based on two principles:
• The primary objective is to keep Rotherham’s roads and footways in a safe condition and to nationally recognised standards. • To carry out programmed maintenance as cost-effectively as possible (not necessarily works on roads that are in the worst condition).
2.3Good asset management assists in meeting the four Corporate Priorities and in particular CP3 - All areas of Rotherham are safe, clean and well maintained.
2.4Based on the latest information available from the DfT national data set (2013/14), the condition of the road network is as follows:
• The percentage of Principal Roads (‘A’ roads, which amount to 12% of the total road length) requiring significant works is 3%, with national average at 4%. Note: A £5m capital investment programme reduced this from 5% in 2008.
• The percentage of Non-Principal Roads (‘B/C’ roads, which amount to 23% of the total road length) requiring significant works is 7%, with the national average at 8%. Note: The recently completed 3- year (£3m) investment programme reduced this from 8% in 2011.
• The percentage of Unclassified Roads (‘U’ roads, which accounts for the remaining 65% of our total road length) requiring significant works is 21%, compared with the national average at 18%.
3. Key Issues
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Asset Mgt Policy 2015Appendix 1 | 2 pages | Download |
PDF |
Highway Asset Mgt StrategyAppendix 2 | 8 pages | Download |
PDF |
HIGHWAY ASSET MANAGEMENT POLICY, STRATEGY AND PLAN 2015-2021Report | 7 pages | DownloadRead as text |
Follow Council Meeting at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Nov 2026 | Minutes of the previous Council MeetingThat the minutes of the Council meeting held on 9 September 2026 be approved for signature by the Mayor. Mover: Counc... | Approved | Open |
| 4 Nov 2026 | PetitionsThat the report be received. 2. That the relevant Executive Director be required to respond to the lead petitioners, ... | Decided | Open |
| 4 Nov 2026 | Care Leavers' CharterThat Council: 1. Adopt the Rotherham Care Leavers’ Charter as a statement of the Council's commitment to Care Leavers... | Approved | Open |
| 4 Nov 2026 | Cabinet's Response to the Health Select Commission’s Recommendations – MenopauseThat Council note the response to the recommendations, as detailed in the Cabinet report of 14 September 2026. Mover:... | Noted | Open |
| 4 Nov 2026 | Thriving Neighbourhoods - Updates from Ward Councillors for Rawmarsh EastThat the update report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.