Highway Asset Management Policy, Strategy and Plan 2015-2021

Approved Committee 5 papers

Commissioner Manzie's Meeting approved this item on Wednesday 7 October 2015. Below is the council's own wording, with the papers it was decided on.

Item105

Resolved

Minded to Grant Decision :- (1) That the Highways Management Policy statement, Strategy and the HAMP covering the period 2015-2021 be endorsed. (2) That the report be referred to the Improving Places Select Commission (3) Subject to any changes made following the Improving Places Select Committee recommended to Council for adoption. Reason :- To seek endorsement of the Council’s Highways Asset Management Policy, Strategy and revised Highway Asset Management Plan ( HAMP ) which covered the period 2015 – 2021. Date of Publication of the Minded to Grant Decision :- Friday, 9 th October, 2015. Representations upon the decision are invited from Councillors, members of the public, partner agencies and any interested body or individual within five working days from the date of publication and must be received by Debbie Pons [email protected] no later than 5.00 p.m. on Friday, 16 th October, 2015. Date Representations Received :- None Representations Received :- None Date of Commissioner Manzie’s Final Decision :- Monday, 19 th October, 2015. - (1) That the Highways Management Policy statement, Strategy and the HAMP covering the period 2015-2021 be endorsed. (2) That the report be referred to the Improving Places Select Commission (3) Subject to any changes made following the Improving Places Select Committee recommended to Council for adoption.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Commissioner Manzie's Meeting, 7 pages

Recommendation

1. Endorses the Highways Management Policy statement, Strategy and the HAMP covering the period 2015-2021. 2. Refers the report to the Improving Places Select Commission and recommends the report to Council for adoption.

List of Appendices Included

1. Highway Asset Mgt Policy

2. Highway Asset Mgt Strategy

3. Highway Asset Mgt Plan 2015-2021 Background Papers

Highway Infrastructure Asset Management Guidance Highways Maintenance Efficiency Programme (HMEP). DfT Local Highways Maintenance Capital Block Funding 2015/16 – 20/21 Local Maintenance Capital Funding self-assessment questionnaire and guidance

Consideration by any other Council Committee, Scrutiny or Advisory Panel The report will be presented to the Improving Places Select Commission on the 14th October 2015.

Council Approval Required Yes

Exempt from the Press and Public No Title Highway Asset Management Policy, Strategy and Plan 2015-2021

Recommendations

1.1Endorses the Highways Management Policy statement, Strategy and the HAMP covering the period 2015-2021. 1.2 Refers the report to the Improving Places Select Commission and recommends the report to Council for adoption.

Background

2.1The Council is responsible for maintaining approximately 700 miles of roads and 1,300 miles of footways and Public Rights of Way. The highway network is the Council’s single biggest asset with a value of around £1.726b (gross replacement value) – see table 1.

Table 1: Size and value of major highway assets

Estimated Depreciated Gross Replacement Asset Type Quantity Replacement Cost (DRC) Cost (£m) (£m) Carriageways 1,143 km £1,257m £1,202m Footways 1,689 km £219m £192m 45,500 chambers, gullies etc. and 35 Included in Included in Drainage km of drainage carriageway carriageway pipes/chambers costs costs

Street 35,216 street lights Lighting/Furniture £72.5m £67m columns 185 structures - bridges, culverts and Structures £164m £157m underpasses

107 traffic signalised junctions and Traffic Signals £13.5m £6m pedestrian crossings

Total Cost £1.726bn £1,625bn 2.2 The Council’s approach to highway maintenance is based on two principles:

• The primary objective is to keep Rotherham’s roads and footways in a safe condition and to nationally recognised standards. • To carry out programmed maintenance as cost-effectively as possible (not necessarily works on roads that are in the worst condition).

2.3Good asset management assists in meeting the four Corporate Priorities and in particular CP3 - All areas of Rotherham are safe, clean and well maintained.

2.4Based on the latest information available from the DfT national data set (2013/14), the condition of the road network is as follows:

• The percentage of Principal Roads (‘A’ roads, which amount to 12% of the total road length) requiring significant works is 3%, with national average at 4%. Note: A £5m capital investment programme reduced this from 5% in 2008.

• The percentage of Non-Principal Roads (‘B/C’ roads, which amount to 23% of the total road length) requiring significant works is 7%, with the national average at 8%. Note: The recently completed 3- year (£3m) investment programme reduced this from 8% in 2011.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Asset Mgt PolicyAppendix 1 3 pages Download
PDF
Highway Asset Mgt StrategyAppendix 2 8 pages Download
PDF
Highway Asset Mgt Plan 2015-2021Appendix 3 108 pages Download
PDF
Highway Asset Management Policy, Strategy and Plan 2015-2021Decisions 2 pages Download
PDF
Highway Asset Mgt Policy Strategy and Plan 2015 to 2021 cover reportReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Highway Asset Management Policy, Strategy and Plan 2015-2021This decision
  2. Highway asset management policy, strategy and plan 2015-2021Approved
  3. Highways Asset Management Planning and Guidance for 3rd Round of Local Transport PlansNoted
  4. Highways Asset Management Plan - Progress ReportNoted
  5. Proposed extension of term for the Highway Asset Management PlanDecided
  6. Highways Asset Management Plan - UpdateNoted

More from Rotherham Commissioner Manzie's Meeting

All decisions
MeetingDecisionOutcome
28 Jan 2016 Report of Overview and Scrutiny Management Board following discussion of saving proposals held on the 15th and 22nd January, 2016Minded to Grant Decision :- That the comments and recommendations from the Overview and Scrutiny Management Board on ... Noted Open
28 Jan 2016 Early Help and Youth Services - Financial Implication of Development Programme, for referral to Overview and Scrutiny Management BoardMinded to Grant Decision :- That the savings proposals enclosed at Appendix A be referred to the Overview and Scrutin... Decided Open
28 Jan 2016 Response to Central Government Consultation on Proposed Changes to National Planning PolicyMinded to Grant - (1) That the Council’s consultation response attached at Appendix 1 be endorsed for submission to c... Decided Open
28 Jan 2016 Exemption from Standing Orders for renewal of selected software contracts for the ROCC housing repairs ordering systemMinded to Grant Decision :- (1) That this renewal be exempt from the provisions of Standing Order 47.6.2 (requirement... Decided Open
7 Jan 2016 Revenue Budget Monitoring Report for the period ending 30th November 2015Minded to Grant Decision :- (1) That the forecast overspend and the need to maintain continuous close scrutiny of spe... Noted Open