Resolved
That the Phase Two RMBC Corporate Improvement Plan be endorsed.
Cabinet and Commissioners' Decision Making Meeting (during Government Intervention decided this item on Monday 18 January 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Phase Two RMBC Corporate Improvement Plan be endorsed.
1. As part of the Secretary of State Directions on 26th February 2015 appointing Commissioners to Rotherham MBC, there was a requirement for the Commissioners to agree an improvement plan with Government within three months of their appointment. This led to the publication of the ‘Fresh Start’ Corporate Improvement Plan, which covered key improvement priorities for the Council over a two year period from May 2015 to May 2017. This Plan was endorsed by Council on 22nd May 2015, prior to its formal submission to Secretaries of State on 26th May 2015.
2. The Fresh Start Plan was divided into two phases, the first to May 2016, focusing on establishing the core building blocks of an effective local authority. There were a total of 132 identified actions within this first phase, the delivery of which has been overseen by a Joint Board of Commissioners and Elected Members (including the Council Leader and Leader of the Opposition Group). The second phase, from May 2016, focuses on embedding strong leadership and a new culture “where the improvements made are embedded via revitalised political and managerial leadership which can deliver an aspirational and inspirational vision for a better Rotherham”.
3. It was always the case that the outline actions for the second phase set out in the original Fresh Start document would need to be re-considered in the light of the experience of Phase One.
1 4. A draft set of Phase Two objectives and actions was therefore considered at the most recent Joint Board meeting on 23rd May 2016. This reflected a number of ongoing priority actions, a number of actions in the first phase that had not yet been completed, as well as a re-assessed set of outline Phase Two actions from the original document. The Joint Board signed off this Phase Two Plan to form a key focus of targeted improvement activity through to May 2017, and a copy is enclosed at Appendix A.
5. The Joint Board will continue to oversee the performance and delivery of the Phase Two plan at its monthly meetings, with the Chief Executive, Senior Leadership Team and Assistant Directors collectively responsible for progress reporting to the Board.
Cabinet is asked to:
• Provide its endorsement of the Phase Two RMBC Corporate Improvement Plan (enclosed at Appendix A).
List of Appendices Included
Appendix A – Phase Two RMBC Corporate Improvement Plan
Background Papers/Information
RMBC “Fresh Start” Corporate Improvement Plan (2015-2017), 26th May 2015
Report to Council on the RMBC “Fresh Start” Corporate Improvement Plan (2015- 2017), 22nd May 2015
Secretary of State Directions to Rotherham MBC, 26th February 2015; and revised Directions, 11th February 2015
Consideration by any other Council Committee, Scrutiny or Advisory Panel
Possibility of pre-scrutiny consideration prior to Cabinet (1st July 2016)
Council Approval Required Yes
Exempt from the Press and Public No
2 Title (Main report)
Phase Two RMBC Corporate Improvement Plan
1.1For Cabinet provide its endorsement of the Phase Two RMBC Corporate Improvement Plan (enclosed at Appendix A).
2.1As part of the Secretary of State Directions in February 2015 appointing Commissioners to Rotherham MBC, there was a specific requirement for the Managing Director Commissioner to lead on the establishment of a corporate improvement plan for the Council and agree this with Government within three months of their appointment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix: Improvement Plan Phase 2Appendix | 22 pages | Download |
PDF |
Phase Two RMBC Corporate Improvement PlanReport | 9 pages | DownloadRead as text |
Follow Cabinet and Commissioners' Decision Making Meeting (during Government Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jan 2016 | Out of Area Cross Charging Policy for Sexual Health ServicesResolved :- That the out of area cross charging policy, based on the agreed regional approach endorsed by the Yorkshi... | Agreed | Open |
| 18 Jan 2016 | Questions from Members of the Public.Decision Making Meeting had been published on 19 May 2016, complying the access to information rules within the Counc... | Agreed | Open |
| 18 Jan 2016 | Questions from Members of the PublicDecision Making Meeting held on 26 May 2016, regarding his compliance with the council’s Constitution and whether adv... | Agreed | Open |
| 18 Jan 2016 | Minutes of the previous meeting held on 9th July 2018- That the minutes of the meeting held on 9th July 2018 be agreed as a true and correct record of the proceedings. | Agreed | Open |
| 18 Jan 2016 | Minutes of the previous meeting held on 6 August 2018- That the minutes of the Cabinet and Commissioners’ Decision Making Meeting held on 6 th August, 2018, be agreed as ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.