Request for Extension of Timescales for Implementation of Adults' Liquidlogic Social Care Case Management System and Capitalisation of Additional Costs
AgreedExecutive1 paper
Cabinet and Commissioners' Decision Making Meeting (during Government Intervention agreed this item on Monday 18 January 2016. Below is the council's own wording, with the papers it was decided on.
That a revised implementation date for the new Liquidlogic Adults’ social care case management and ContrOCC finance systems of 13 th December 2016 be agreed. 2. That an increase of £291,977 to the already approved capital allocation for this project in 2016/17 be agreed and that this be added to the Capital Programme. 3. That Council be recommended to approve an increase in the Capital Programme by £291,977.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Cabinet and Commissioners' Decision Making Meeting (during Government Intervention, 12 pages
Summary
In its inspection findings in November 2014, Ofsted identified that Rotherham’s social care case management system did not support good practice. Ofsted found that workers were unable to locate key case documents, chronologies were rarely up to date, and most chronologies had significant gaps.
“The local authority’s ability to measure the performance of children’s social care was limited by the capacity of the electronic recording systems, which primarily report on compliance measures such as timescales.” Further to this, Louise Casey published her report; “Report of Inspection of Rotherham Metropolitan Borough Council” in February 2015. This report identified that “The IT systems supporting social workers are not fit for purpose.”
In April 2015, a contract for the implementation of a new social care IT system for Children’s and Adults’ services was awarded to Liquidlogic, following a process of competitive tendering. The contract between Rotherham Metropolitan Borough Council (RMBC) and Liquidlogic was signed on the 30th June 2015. A programme plan was developed which included a proposed implementation date of the 8th February 2016 for the Children’s system, and the 12th April 2016 for the Adults’ system. It was identified that the implementation of Liquidlogic would provide the social care workforce with the market-leading case management system. Liquidlogic will support staff in maintaining accurate, timely and comprehensive case records, facilitate robust management oversight and improve performance management and quality assurance.
In September 2015, the Programme Sponsor commissioned a report from a consultant from ICT Revolutions. Following this, an internal audit of the new system implementation programme was commissioned by the Council’s internal audit services, and received in January 2016.
Both reports made a number of common recommendations, and identified programme critical issues, including issues relating to data migration, staff training and performance reporting.
In response to these recommendations, this report recommends the extension of the proposed implementation date, and sets out the resource and budgetary implications of this extension. This extension is required to enable additional rounds of data migration, allow completion and testing of the interface files required to pay and charge people, provide sufficient timescales to conduct robust testing of the whole solution and ensure that the project does not fail.
A separate report regarding the Children’s implementation of Liquidlogic/ContrOCC was approved by Cabinet on the 26th May 2016. This report recommended an extension of the timescales to implementation from 11th April to 31st October 2016 and an increase to the Capital budget of £351, 610.
Recommendations
Cabinet is asked to:
• Agree a revised implementation date for the new Liquidlogic Adults’ social care case management and ContrOCC finance systems of 13th December 2016 • Agree to an increase of £291,977 to the already approved capital allocation for this project in 2016/17 and that this be added to the Capital Programme. • Recommend to Council to approve an increase in the Capital Programme by £291,977
List of Appendices Included Nil
Background papers
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Request for Extension of Timescales for Implementation of Adults' Liquidlogic Social Care Case Management System and Capitalisation of Additional CostsReport
52Request for Extension of Timescales for Implementation of Adults' Liquidlogic Social Care Case Management System and Capitalisation of Additional CostsThis decision
Request for Extension of Timescales for Implementation of Adults' Liquidlogic Social Care Case Management System and Capitalisation of Additional CostsThis decision
Follow Cabinet and Commissioners' Decision Making Meeting (during Government Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
Questions from Members of the Public.Decision Making Meeting had been published on 19 May 2016, complying the access to information rules within the Counc...
Questions from Members of the PublicDecision Making Meeting held on 26 May 2016, regarding his compliance with the council’s Constitution and whether adv...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.