Resolved
Resolved :- (1) That Sheffield City Council be thanked for the opportunity to comment on this application. (2) That Sheffield City Council be informed that this Council did not wish to object to the above proposal.
Planning Board decided this item on Thursday 21 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- (1) That Sheffield City Council be thanked for the opportunity to comment on this application. (2) That Sheffield City Council be informed that this Council did not wish to object to the above proposal.
That Sheffield Council be informed that the Council raise no objections to the proposal. Background
This is a ‘courtesy’ consultation as required due to the close proximity of Rotherham Borough to the application site. RMBC are invited to provide Sheffield Council with comments on the application and the impact of the proposal on Rotherham in terms of such planning related issues as the environment, flooding, traffic etc.
Site Description & Location
The site comprises approximately 20.5ha of brownfield land, located immediately south-west of Junction 34 of the M1 northbound, 8 miles from Sheffield City Centre. The site fronts Sheepcote Lane with railings and old factory walls enclosing the site along this boundary. Greasbrough Road bounds the site to the north and north east, and to the south and east are other industrial units / warehouse.
The site was formerly used by British Steel and most recently Outokumpu, whose facility closed in 2005. The site was cleared in 2011 and has remained vacant since..
The boundary of RMBC’s administrative area is approximately 1km to the east of the site, and the nearest residential dwellings on Bawtry Road, Brinsworth are a similar distance to the east.
Proposal
The application submitted to Sheffield has been described as a hybrid application seeking both full and part outline (with access) permission for up to 77, 845sq. m of B1 (c), B2 and B8 uses.
The full application seeks permission for units 1 and 2. Unit 1 comprises of 4,174sq.m and will be split between B2/B8 floorspace (3,756sq.m) and B1c) ancillary office floorspace (417sq.m). This unit will be 12m to eaves and 14.3m to ridge. Unit 2 comprises of 12,441sq. m and will be split the betweenB2/B8 (11,366sq. m) and B1c) ancillary office (1,075sq. m) The building will be 13.8m to eaves and 15.5m to ridge.
Units 1 and 2 the northern part of the site, with the buildings running east – west.
The outline element of the proposal comprises the larger part of the whole site (14ha). The indicative masterplan shows three buildings of varying sizes for B1c), B2 and B8 use and will be served by a new access on Sheepcote Lane.
Both the full and outline elements would also incorporate hard and soft landscaping. Consultations
RMBC - Transportation and Highways Design: Have no objections.
RMBC – Air Quality: No objections.
RMBC – Environmental Health: Have no issues. Appraisal
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Courtesy Consultation in respect of proposed Phase 1 (full application) Erection of 2 units: 16,615 sq. m of B1c/B2/B8 floorspace and provision of associated access and landscaping; Phase 2 (Outline application) Details of access for upto 61,230 sq. m of B1c/B2/B8 floorspace at former Outokumpu, ShReport | 762 KB | DownloadRead as text |
PDF |
Director of Planning: 21st June, 2018 Appendix 1Appendix | 1.8 MB | Download |
Follow Planning Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Minutes of the previous meeting held on 8th October 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 8 th October, 2026, be ... | Approved | Open |
| 29 Oct 2026 | Development Proposals- (1 ) That , on the development proposals now considered, the requisite notices be issued and be made available on t... | Approved | Open |
| 29 Oct 2026 | Report of the Service Director for Planning, Regeneration and Transport - Whitestone Solar Farm - Nationally Significant Infrastructure Project Update- That the update be received and the contents noted. | Noted | Open |
| 8 Oct 2026 | Minutes of the previous meeting held on 17th September, 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 17 th September, 2026, ... | Approved | Open |
| 8 Oct 2026 | Development Proposals- (1) That, on the development proposals now considered, the requisite notices be issued and be made available on the... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.