CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council
Audit Committee, Tuesday 25 November 2025

Risk Management Guide Refresh 2025

Noted Finance 2 papers

AI summaryRotherham Metropolitan Borough Council's Audit Committee received the report, approved the refreshed Risk Management Guide and requested risk management training for all elected members as soon as possible. [D] The refresh has no direct budget impact. [6.1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTraining requested for all elected members [D]
MoneyNo direct financial implications [6.1]No additional cost or procurement issues [6.1]
What happens nextGuide on staff intranet [5.1]Elected member training as soon as possible [D]
Who it affectsCouncil staff and elected members [2.11] [D]Risk roles, processes and training [2.5] [D]

What was decided

The Audit Committee received the report and noted its contents. [D]

It approved the refreshed Risk Management Guide. [D]

It asked for risk management training for all elected members to be arranged as soon as possible. [D]

Why

No significant changes were required because the Council's management and governance arrangements and specific risk processes remained broadly unchanged. [1.3] [2.2] [2.3] Report 1.3, 2.2, 2.3

The main update makes clearer how risks move up or down between registers, following recommendation IR2 from the 2023/24 Value for Money arrangements. Sections 4.7.5 and 4.7.6 were added for this purpose. [2.3] Report 2.3

An Internal Audit review in March 2024 against ISO31000 found that the controls provided substantial assurance, the highest level possible. [2.1] Report 2.1

What happens next

The Head of Policy, Performance and Intelligence will put the approved guide on the staff intranet and communicate it to staff once approved. [5.1] Report 5.1

Risk management training for all elected members is to be arranged as soon as possible. [D]

HR colleagues are supporting delivery of the training scheduled for 2026. An additional course will be provided through the external consultant. [8.1] [2.10] Report 8.1, 2.10

Options considered

  • Chosen: Refresh the Risk Management Guide. The report considered only the guide refresh, with no specific alternative options. Report 3.1

Implications

  • Financial: The recommendations have no direct effect on the Council's budget. The guide needs no additional cost and raises no procurement issues. Risks may still need extra resources, with additional costs reported to the Strategic Leadership Team and elected members for consideration. [6.1] Report 6.1
  • Legal: There are no direct legal implications. Actions responding to identified risks will take account of any specific legal implications. [7.1] Report 7.1
  • Equalities: Proposals for addressing individual risks incorporate equalities and human rights considerations where appropriate. [10.1] Report 10.1
  • Climate: The refresh supports the Council's net zero aim by improving risk management and allowing climate risks to be identified and managed. It has no direct significant impact on emissions but may help reduce them indirectly. [11.1] [11.2] Report 11.1, 11.2
  • Risk: New sections set out arrangements for moving risks up or down between registers. Risks in the Council's registers need ongoing management action and continued review. [2.3] [6.1] [13.1] Report 2.3, 6.1, 13.1
  • Staffing: The programme for new starters and managers at M2 grade or above reaches approximately 150 managers a year. All staff have an online training module, and training for all elected members was requested. [2.8] [2.9] [D] Report 2.8, 2.9
  • Other: The guide's objectives include effective corporate governance, a satisfactory Annual Governance Statement and clear roles. Council approval was not required, there was no external consultation, and the report was not exempt from the press and public. [2.5] [P7] [P8] [4.1] [P9] [P10] Report 2.5, P7, P8, 4.1, P9, P10
  • Other: Risk arrangements identify Children and Young People's Services risks where appropriate. There are no direct partner implications, although the Strategic Leadership Team has a responsibility to promote a risk management culture with partners and stakeholders. [9.1] [12.1] Report 9.1, 12.1

Who and where

  • All elected members
  • Council staff Report 2.11, 5.1
  • New starters and managers at M2 grade or above Report 2.8
  • Strategic Leadership Team Report 2.6, 6.1
  • Directorate Leadership Teams Report 2.6
  • Risk owners Report 2.6
  • Risk Management Group and Risk Champions Report 2.7
  • Children and Young People's Services Report 9.1

Timeline

  • 24th November 2015: The Audit Committee approved the revised Risk Policy and Guide. Report 1.2
  • 23rd January 2023: Cabinet considered the Risk Management Policy. Report 1.2
  • 28th November 2023: The Audit Committee last considered the Risk Management Guide. Report 1.2
  • March 2024: Internal Audit reviewed the risk management process against ISO31000. Report 2.1
  • 29th July 2025: The Audit Committee received the Risk Management Annual Summary for 2024-25. Report 1.4
  • 2025-11-25: The Audit Committee received the report, approved the refreshed guide and requested training for all elected members.
  • 2026: An additional risk management course will be provided through the external consultant, with HR support. Report 2.10, 8.1
  • by 2028: The Risk Management Policy is due to be refreshed. Report 1.2

Plain English for the jargon

  • Risk Management Guide: The document underpinning the Council's risk management approach and explaining how risks are captured, managed and reported. [2.11] [13.1]
  • Risk Management Policy: The Council's policy underpinning its risk management training and risk registers. [2.11]
  • Corporate Strategic Risk Register: The Council's corporate risk register, reviewed quarterly by the Strategic Leadership Team and twice a year by the Audit Committee. [1.5] [2.6]
  • Directorate Risk Registers: Registers for individual directorates, reviewed monthly by Directorate Leadership Teams and presented to the Audit Committee on an annual rolling programme. [1.5] [2.6]
  • ISO31000: The international risk management standard used for the Annual Summary and the Internal Audit review. [1.4] [2.1]
  • Annual Governance Statement: A statement to which effective risk management is intended to contribute. [2.5]
  • Risk owner: The role responsible for monitoring risks on an ongoing basis. [2.6]
  • Substantial assurance: The highest assurance level that Internal Audit said could be derived from the controls in place. [2.1]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item52

Resolved

- (1) That the report be received and the contents noted. (2) That the refreshed Risk Management Guide be approved. (3) That risk management training for all Elected Members be arranged as soon as possible.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Audit Committee, 6 pages

Recommendations

The Audit Committee is asked to approve the Risk Management Guide 2025.

List of Appendices Included

Appendix 1 Revised Risk Management Guide 2025 Background Papers

Report to Audit Committee: 29 July 2025 (Risk Management Annual Summary for 2024-25 and Corporate Strategic Risk Register Update) Report to Audit Committee: 14 January 2025 (Corporate Strategic Risk Register) Report to Audit Committee 28 November 2023 (Risk Management Guide Refresh) Report to Cabinet: 23 January 2023 (Risk Management Policy)

Consideration by any other Council Committee, Scrutiny or Advisory Panel

None

Council Approval Required

No

Exempt from the Press and Public

No

Page 2 of 6 Risk Management Guide Refresh 2025

Background

1.1This report aims to inform the Committee of the results of a refresh of the Council’s Risk Management Guide.

1.2The Council introduced a completely revised Risk Policy and Guide in late 2015 which was approved by the Audit Committee on 24th November 2015. The Policy was considered by Cabinet on the 23rd January 2023 and is due to be refreshed by 2028, and the Guide was last considered by the Audit Committee on 28th November 2023.

1.3Whilst previous reviews have included significant changes (in 2021 due to the impact of the pandemic for example), there are no significant changes required this year.

1.4The Risk Management Annual Summary for 2024-25 was presented to the Audit Committee on the 29th July 2025, in accordance with the risk management standard ISO31000. The report summarised the principal risk management activity carried out in the Council throughout the financial year.

1.5The Corporate Strategic Risk Register is presented to Audit Committee twice a year and directorate risk registers are presented to Audit Committee annually as part of a rolling programme.

2. Key Issues

2.1The risk management process was subject to an Internal Audit review in March 2024 against the requirements of the relevant international standard, ISO31000. The review concluded that substantial assurance could be derived from the controls that were in place. This is the highest assurance level possible.

2.2There have been no significant changes to the Council’s overall management and governance arrangements since the Risk Management Guide was last updated in November 2023. Meanwhile, the specific risk management processes in which the Council operates have remained broadly unchanged.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Guide 12 11 25 no commentsAppendix A 24 pages Download
PDF
Risk Management Guide Refresh 2025Report 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 7 attended
JB
Councillor Jamie BaggaleyChair, present
SA
Councillor Sarah Ann AllenVice-Chair, apologies
JB
Councillor John BlackhamMember, present
RE
Councillor Rob ElliottMember, present
CM
Councillor Cameron McKiernanMember, present
AH
Alison HutchinsonGuest, apologies
MO
Michael Olugbenga-BabalolaGuest, present

On this subject at Rotherham

Search all
  1. Risk Management Guide Refresh 2025This decision
  2. Risk Management Annual Summary 2025-2026 and Corporate Strategic Risk Register UpdateDecided
  3. Risk Management Directorate Presentation - Finance and Customer ServicesNoted
  4. Risk Management Directorate Presentation - Regeneration and EnvironmentNoted
  5. Risk Management Directorate Presentation - Adult Care, Housing and Public HealthNoted
  6. Risk Management Directorate Presentation - Children and Young People's ServicesNoted

More from Rotherham Audit Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for... Decided Open
24 Sep 2026 Minutes of the previous meeting held on 28th July, 2026- That the minutes of the previous meeting of the Audit Committee be approved as a correct record of proceedings. Approved Open
24 Sep 2026 External Audit Progress Report and Sector Update- That the progress and sector updates be noted. Noted Open
24 Sep 2026 Code of Corporate Governance- That the refreshed version of the be received and noted. Noted Open
24 Sep 2026 Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies