CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council
Planning Board, Thursday 25 June 2026

Updates

Noted Planning 1 paper

AI summaryPlanning Board notes update on Call for Sites for a new Rotherham Local Plan, opening 22 June 2026 for 10 weeks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCall for Sites process endorsed for information gathering
MoneyNot stated
What happens nextCall for Sites opens 22 June 2026Runs for 10 weeks, closing 28 August 2026
Who it affectsLandowners, developers, public bodies, residentsAnyone may submit potential development sites

What was decided

The Planning Board received and noted the update on the Call for Sites for the new Local Plan. Report P1

The Council will not progress the Core Strategy Partial Update and will instead prepare a new Local Plan covering needs into the 2040s. Report P2, P3

The Call for Sites will open on 22 June 2026 and run for 10 weeks until 28 August 2026. Report P5

Why

The existing Local Plan covers 2013 to 2028 and is being replaced in light of the Levelling-up and Regeneration Act 2023 and wider planning reforms. Report P2

A new Local Plan is needed to identify sufficient land to meet development needs into the 2040s, with formal plan-making expected to start later in 2026. Report P3

The Call for Sites is an early-stage information-gathering exercise and does not allocate land, confirm suitability for development, or grant planning permission. Report P6

What happens next

Submissions will be made through the Council's Citizenspace platform, with support available from the Planning Policy team by email, telephone, Microsoft Teams or in person at Riverside House Library. Report P7

Submitted sites will be published on an online map at a later stage, with personal data managed in line with data protection requirements. Report P16

Three stages of public consultation are planned during the formal 30-month plan-making period, with public feedback on site options anticipated at the second consultation stage in mid-2027. Report P17

Options considered

  • Rejected: Progress the Core Strategy Partial Update. Replaced by a new Local Plan following review of the Core Strategy and changes introduced through the Levelling-up and Regeneration Act 2023 and wider planning reforms. Report P2
  • Chosen: Prepare a new Local Plan and run a Call for Sites. Needed to identify sufficient land to meet development needs into the 2040s and to align with current planning reforms. Report P2, P3

Implications

  • Legal: Submitting a site does not allocate land, confirm suitability, or grant planning permission; all submissions will be assessed at a later stage. Report P6
  • Other: Only key site details will be made public when submitted sites are published on an online map; personal data will be handled in line with data protection requirements. Report P16
  • Other: Residential sites should generally be at least 0.25 hectares or capable of delivering five or more dwellings; employment, commercial and retail sites should generally deliver 500 square metres or more of floorspace. Report P11, P12

Who and where

  • Landowners Report P10
  • Developers Report P10
  • Public bodies Report P10
  • Members of the public Report P10
  • Planning Policy team Report P7

Timeline

  • 22 June 2026: Call for Sites opens Report P5
  • 28 August 2026: Call for Sites closes after 10 weeks Report P5
  • Later 2026: Formal plan-making stages expected to commence Report P3
  • Mid-2027: Public feedback on site options and emerging strategy anticipated at second consultation stage Report P17
  • Into the 2040s: Period the new Local Plan is intended to cover for development needs Report P3

Plain English for the jargon

  • Local Plan: The council's planning document setting out policies and land allocations for the borough.
  • Call for Sites: An early-stage invitation for anyone to submit potential development sites for consideration in the Local Plan.
  • Core Strategy: The council's existing strategic planning policy document, which is being replaced.
  • Citizenspace: The council's online consultation platform used to submit sites.
  • SLT: The council's Senior Leadership Team, informed at its June meeting.
  • Levelling-up and Regeneration Act 2023: Act of Parliament introducing wider planning reforms that have prompted preparation of a new Local Plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

- That the updated be received and the contents noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Planning Board

Planning Board Update: Call for Sites for the New Local Plan Strategic Context

The existing Local Plan covers 2013 to 2028. Following review of the Core Strategy and wider changes introduced through the Levelling-up and Regeneration Act 2023 and associated planning reforms, the Council will not progress the Core Strategy Partial Update and will instead prepare a new Local Plan.

The new Local Plan will need to identify sufficient land to meet development needs into the 2040s. The Call for Sites is therefore a key enabling step ahead of the formal plan-making stages expected to commence later in 2026.

Key Process Points

The Call for Sites opens on 22 June 2026 and will run for 10 weeks until 28 August 2026.

This is an early-stage information-gathering exercise to identify potential sites across the borough for a wide range of land uses. It does not allocate land, confirm suitability for development, or grant planning permission. All submissions will be assessed at a later stage and further information may be requested to understand suitability, scale, deliverability and site constraints.

Submissions will be made through the Council’s consultation platform (Citizenspace). The Planning Policy team can provide support with completing the form. They can be contacted by email at [email protected] to arrange assistance via telephone, Microsoft Teams, or in person at the Riverside House Library.

Scope of Sites Sought

The Council is seeking a broad range of potential sites, including housing, employment and commercial uses, retail and leisure, environmental uses, infrastructure and community facilities, renewable energy, waste management and minerals.

Sites may be submitted by any interested party, including landowners, developers, public bodies and members of the public. Previously promoted sites must be re-submitted to ensure the Council holds current and consistent information.

Residential sites should generally be at least 0.25 hectares or capable of delivering five or more dwellings, although some smaller specialist housing opportunities may also be relevant.

Employment, commercial and retail sites should generally be capable of delivering 500 square metres or more of floorspace.

Planning Board Update – 04 June 2026 Engagement and Transparency

The call for sites will be publicised through the Council’s website, Local Plan consultee database, press releases, ward newsletters, and social media.

SLT has been informed in June meeting and Members has been informed by a briefing note before the start of the call for sites.

Submitted sites will be published on an online map at a later stage of the plan-making process, with only key site details made public. Personal data will be managed in line with data protection requirements.

There will be three stages of public consultation during the formal 30-month plan-making period. Public feedback on site options and the emerging strategy is currently anticipated at the second consultation stage in mid-2027 in accordance with the approved Local Development Scheme.

For further information, please email to [email protected]

Planning Board Update – 04 June 2026

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UpdatesReport 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 15 attended
JM
Councillor James MaultChair, present
TA
Councillor Terry AdairMember, present
AA
Councillor Angham AhmedMember, present
RB
Councillor Rajmund BrentMember, present
SC
Councillor Simon CurrieMember, present
LD
Councillor Liz DuncanMember, present
RE
Councillor Rob ElliottMember, present
DF
Councillor David FisherMember, present
AH
Councillor Ashiq HussainMember, apologies
DJ
Councillor Dave JacksonVice-Chair, present
DL
Councillor Denise LelliottMember, present
GR
Councillor Greg ReynoldsMember, apologies

All 15 on the meeting page

On this subject at Rotherham

Search all
  1. UpdatesThis decision
  2. Thriving Neighbourhoods - Updates from Ward Councillors for Rawmarsh EastNoted
  3. Thriving Neighbourhoods - Updates from Ward Councillor for Rawmarsh WestNoted
  4. Improving Lives Select Commission - Sub and Project Group UpdatesNoted
  5. UpdatesNoted
  6. Thriving Neighbourhoods - Updates from Ward Councillors for Kilnhurst and Swinton EastNoted

More from Rotherham Planning Board

All decisions
MeetingDecisionOutcome
29 Oct 2026 Minutes of the previous meeting held on 8th October 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 8 th October, 2026, be ... Approved Open
29 Oct 2026 Development Proposals- (1 ) That , on the development proposals now considered, the requisite notices be issued and be made available on t... Approved Open
29 Oct 2026 Report of the Service Director for Planning, Regeneration and Transport - Whitestone Solar Farm - Nationally Significant Infrastructure Project Update- That the update be received and the contents noted. Noted Open
8 Oct 2026 Minutes of the previous meeting held on 17th September, 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 17 th September, 2026, ... Approved Open
8 Oct 2026 Development Proposals- (1) That, on the development proposals now considered, the requisite notices be issued and be made available on the... Approved Open