Planning Board, Thursday 16 July 2026

Development Proposals

Agreed Planning 2 papers

AI summaryRotherham Planning Board approves National Grid's 400kV substation on Grey Belt land at Whiston, secured with a £24,954 biodiversity monitoring payment. Three other applications in Melton, North Anston and Swallownest also approved.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubstation and three other planning applications
Money£24,954Biodiversity Net Gain monitoring over 30 years
What happens nextSign Section 106 agreementThen grant permission subject to conditions
Who it affectsWhiston, North Anston, Melton, SwallownestSubstation, dwellings, apartments, commercial building

What was decided

Approved application RB2025/1468 for a 400kV Gas Insulated Switchgear substation on land at Long Lane, Whiston, subject to a Section 106 legal agreement for £24,954 biodiversity monitoring and the planning conditions listed in the report. Report P12, P174

Approved application RB2026/0241 for roller shutter doors, palisade fencing and replacement roof at Rear of 94 to 100 Melton High Street West Melton, with an additional condition for structural improvements to be agreed by the Chair and Vice-Chair and implemented within one month.

Approved applications RB2026/0371 for 5 residential dwellings at 13 Quarry Lane North Anston, and RB2026/0480 for 4 apartments at 41 Worksop Road Swallownest, subject to the planning conditions listed in the report.

Why

The site is assessed as Grey Belt land under NPPF paragraph 155, with the proposal meeting a demonstrable unmet need for renewable energy transmission infrastructure, in a sustainable location, and not fundamentally undermining Green Belt purposes. Report P113, P126, P127, P128, P129, P139, P140, P141, P142, P146

The scheme delivers biodiversity net gain well above the 10% statutory minimum, with a calculated uplift of approximately 158.67% in habitat units and 38.68% in hedgerow units, to be secured through a 30-year Habitat Management and Monitoring Plan. Report P171, P172, P173, P174

The development is not considered EIA development under the 2017 Regulations, and the noise impact assessment, flood risk assessment, ecological surveys, and archaeological evaluation conclude that impacts can be appropriately mitigated by conditions. Report P10, P187, P188, P189, P191, P198, P204, P205

What happens next

The Council will enter into a Section 106 legal agreement with National Grid Electricity Transmission Plc to secure the £24,954 biodiversity monitoring payment over 30 years, before the planning permission is granted. Report P174

Conditions will be applied including a Construction Environmental Management Plan for Biodiversity, a Written Scheme of Investigation for archaeology, a Habitat Management and Monitoring Plan, a flood preparedness plan, and an Arboricultural Method Statement and Tree Protection Plan. Report P168, P173, P182, P190, P198

For RB2026/0241, details of structural improvements must be agreed by the Chair and Vice-Chair, with the works implemented within one month of the decision.

The money

  • £24,954 Biodiversity Net Gain Monitoring over thirty years, secured via Section 106 legal agreement Report P174

Options considered

  • Chosen: Approve RB2025/1468 subject to Section 106 agreement and planning conditions. Site is Grey Belt land meeting unmet need for renewable infrastructure, with significant biodiversity net gain and no significant environmental harm subject to mitigation Report P146, P172
  • Rejected: Refuse RB2025/1468 on Green Belt, flood risk, or environmental grounds. No strong policy reason to refuse; flood risk, heritage, and ecological impacts can be addressed through conditions, and very special circumstances are accepted as a fallback Report P124, P125, P146, P147

Implications

  • Financial: Developer pays £24,954 to the Council for biodiversity monitoring over 30 years via Section 106 agreement, avoiding the monitoring cost burden on the authority. Report P174
  • Climate: Scheme supports net zero by providing transmission infrastructure for renewable energy as part of National Grid's Great Grid Upgrade, with significant weight given to the proposal's contribution to a net zero future. Report P103, P132, P133, P135, P136, P137, P139
  • Legal: Whiston Footpath 10 to be permanently realigned through a diversion process; multiple planning conditions to be applied covering archaeology, ecology, trees, and noise. Report P13, P91, P198
  • Risk: Flood risk on Long Lane could occasionally cut off the unmanned substation; welfare facilities will be available on site and maintenance visits will be deferred during flood events. Report P31, P190
  • Other: Biodiversity net gain significantly exceeds the 10% statutory minimum, with 158.67% habitat units uplift and 38.68% hedgerow units uplift, secured for a minimum 30 year period. Report P172, P173, P174
  • Other: Application attracted 345 letters of objection, one letter of support, and a 61 signature petition, with objections from seven parish councils. Report P54, P55, P56

Who and where

  • National Grid Electricity Transmission Plc, the applicant for the Whiston substation
  • 345 individual objectors and 61 petition signatories Report P54, P55
  • Thurcroft, Treeton, Aston, Uley, Conisborough, Whiston and Killamarsh Parish Councils Report P56
  • Users of Whiston Footpath 10, which will be permanently realigned Report P13, P91
  • Whiston Meadows Local Wildlife Site and surrounding Habitats of Principal Importance Report P166
  • A&J Real Estate 2021 Limited, the applicant for Melton High Street
  • Eton Home Developments Ltd., the applicant for North Anston dwellings
  • The applicant for 4 apartments at 41 Worksop Road, Swallownest

Timeline

  • 6th March 2014: National Planning Practice Guidance launched by the Department for Communities and Local Government Report P48
  • 10th September 2014: Rotherham Core Strategy adopted as part of the Local Plan Report P42
  • 27th June 2018: Rotherham Sites and Policies Document adopted Report P42
  • 20th June 2025 to 28th June 2025: Unattended noise survey undertaken at the most exposed receptor location Report P22
  • 16 July 2026: Planning Board approves all four applications, with the substation subject to a Section 106 agreement

Plain English for the jargon

  • GIS: Gas Insulated Switchgear, substation equipment enclosed in a gas filled building
  • NPPF: National Planning Policy Framework, the national planning policy document for England
  • Grey Belt: Land in the Green Belt that does not strongly contribute to its main purposes, as defined in the NPPF
  • EIA: Environmental Impact Assessment, a formal assessment of a project's likely environmental effects
  • BNG: Biodiversity Net Gain, a measurable improvement in biodiversity resulting from development
  • BMV: Best and Most Versatile agricultural land, the highest quality farmland (Grades 1, 2 and 3a)
  • S106: Section 106 of the Town and Country Planning Act 1990, used to secure planning obligations
  • SGT: Supergrid Transformer, a large transformer used in high voltage electricity transmission
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item20

Resolved

- (1) That, on the development proposals now considered, the requisite notices be issued and be made available on the Council’s website and that the time limits specified in Sections 91 and 92 of the Town and Country Planning Act 1990 apply. In accordance with the right to speak procedure the following people attended the meeting and spoke about the applications below:- - Erection of a new 400kV Gas Insulated Switchgear (GIS) substation including gantries, internal access roads, a GIS building, parking, drainage, emergency diesel generator, lighting and CCTV, permanent access road from Long Lane, earthworks, landscaping and biodiversity enhancement, and fencing and the permanent realignment of Whiston Footpath 10 at land at Long Lane Whiston for National Grid Electricity Transmission Plc (RB2025/1468) [name removed] (Applicant) [name removed] (Objector) [name removed] (Objector) [name removed] (Objector) [name removed] - Treeton Parish Council (Objector) A statements was also read out on behalf of:- [name removed] (Objector) - Installation of steel roller shutter doors, galvanised steel palisade fence and gates, and replacement roof at Rear of 94 to 100 Melton High Street West Melton for A&J Real Estate 2021 Limited (RB2026/0241) [name removed] (Objector) [name removed] (Objector) - Demolition of existing dwelling and garage, and erection of 5 residential dwellings at 13 Quarry Lane North Anston for Eton Home Developments Ltd. (RB2026/0371) [name removed] (Agent) [name removed] (Objector) [name removed] (Objector) - Construction of 4 apartments over existing buildings with rooms in roofspace, balconies to front and stairs and access balcony to rear, conversion of laundrette to cycle/bin store and erection of 2.1m high fence at 41 Worksop Road Swallownest for [name removed] (RB2026/0480) [name removed] (on behalf of the Applicant) A statement was also read out on behalf of:- [name removed] (Objector) (2) That in relation to application RB2025/1468 :- (a) That the Council enter into a legal agreement with the developer under Section 106 of the Town and Country Planning Act 1990 for the purposes of securing the following:- · £24,954 towards Biodiversity Net Gain Monitoring over a period of thirty years. (b) subject to the satisfactory signing of the agreement application RB2025/1468 be granted for the reasons adopted by Members at the meeting and subject to the relevant conditions listed in the submitted report. (3) That application RB2026/0241 be granted for the reasons adopted by Members at the meeting, subject to the relevant conditions listed in the submitted report and subject to the addition of a further condition requiring improvements to the structural appearance of the development, the details of which shall be delegated to, and agreed by the Chair and Vice-Chair. Such improvements shall be implemented within one month of the date of the decision. (4) That applications RB2026/0371 and RB2026/0480 be granted for the reasons adopted by Members at the meeting and subject to the relevant conditions listed in the submitted report.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Planning Board

Background

RB1990/1779 - Outline for erection. of a centre for industrial/employment regeneration – WITHDRAWN

Adjacent application under consideration:

RB2025/1420 - Outline planning application for the construction of up to 170 dwellings with associated landscaping, open space, drainage infrastructure and associated works (all matters reserved except access from Long Lane)

EIA Screening Opinion

The proposed development falls within the description contained at Paragraph 3(a) “Industrial installations for the production of electricity, steam and hot water” of Schedule 2 of the Town and Country Planning (Environment Impact Assessment) (England and Wales) Regulations 2017 and meets the criteria set out in column 2 of the table in Schedule 2 i.e. the area of the development exceeds 0.5 hectares (when the blue edged plan is considered as well as the red edge plan). However, the Borough Council as the relevant Local Planning Authority has taken into account the criteria set out in Schedule 3 to the Regulations and it is considered that the development would not be likely to have a significant effect on the environment by virtue of factors such as its nature, size and location. The development has been assessed against the following three factors:

• Major developments of more than a local importance; • Development in particularly environmentally sensitive or vulnerable locations; • Developments with unusually complex and potentially hazardous environmental effects.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
COMREP160726Report 756 KB DownloadRead as text
PDF
Development ProposalsReport 12 KB Download

At this meeting

Whole meeting

Who was there

14 of 16 attended
JM
Councillor James MaultChair, present
TA
Councillor Terry AdairMember, apologies
AA
Councillor Angham AhmedMember, present
RB
Councillor Rajmund BrentMember, present
SC
Councillor Simon CurrieMember, present
LD
Councillor Liz DuncanMember, present
RE
Councillor Rob ElliottMember, present
DF
Councillor David FisherMember, present
AH
Councillor Ashiq HussainMember, present
DJ
Councillor Dave JacksonVice-Chair, apologies
DL
Councillor Denise LelliottMember, present
GR
Councillor Greg ReynoldsMember, present

All 16 on the meeting page

On this subject at Rotherham

Search all
  1. Development ProposalsThis decision
  2. Development ProposalsApproved
  3. Development ProposalsApproved
  4. Development ProposalsApproved
  5. Development ProposalsApproved
  6. Development ProposalsApproved

More from Rotherham Planning Board

All decisions
MeetingDecisionOutcome
29 Oct 2026 Minutes of the previous meeting held on 8th October 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 8 th October, 2026, be ... Approved Open
29 Oct 2026 Development Proposals- (1 ) That , on the development proposals now considered, the requisite notices be issued and be made available on t... Approved Open
29 Oct 2026 Report of the Service Director for Planning, Regeneration and Transport - Whitestone Solar Farm - Nationally Significant Infrastructure Project Update- That the update be received and the contents noted. Noted Open
8 Oct 2026 Minutes of the previous meeting held on 17th September, 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 17 th September, 2026, ... Approved Open