Resolved
That the minutes of the meeting of 3 February 2026 be approved.
Barnsley, Doncaster and Rotherham Joint Waste Board approved this item on Monday 16 November 2026. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting of 3 February 2026 be approved.
03/02/26 1
BARNSLEY, DONCASTER AND ROTHERHAM JOINT WASTE BOARD Tuesday 3 February 2026 at 1.30pm
Present:- Councillor Higginbottom (in the Chair); Councillors Jones and Marshall.
Also in attendance were Paul Castle, Sam Barstow, Rhonda Fletcher, Jim Busby and Carl Hewlett.
35 APOLOGIES FOR ABSENCE
Apologies were received from Matt O’Neill.
The Chair asked for it to be noted that the Board wished to extend their sincere condolences to Paul Hutchinson, BDR Manager, who had recently suffered the loss of his wife.
36 DECLARATIONS OF INTEREST
There were no declarations of interest
37 MINUTES OF THE PREVIOUS MEETING HELD ON 7 OCTOBER 2025 (COPY ATTACHED) AND ANY MATTERS ARISING
Resolved:- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings.
38 BDR MANAGERS REPORT
At the invitation of the Chair, the Interim BDR Manager (BDR Manager) provided an update relating to the BDR Managers Report, during which the following points of note were highlighted and discussed:
• The Operational Management Budget Forecast showed a projected underspend of £68,401. If not spent, this underspend would be rolled into the 2026-27 financial year. Delays had been experienced in obtaining information from the contractor relating to outstanding issues and ongoing projects, which meant that planned work was not carried out and would continue into the next financial year. It was also hoped that staffing costs could be better forecasted in the next financial year and the budget would need to cover potential increases in pay and increased consultant fees. It was noted that the BDR budget had not increased since the financial year 2022-23.
• The forecasted Unitary Charge had been sent to all councils for the 2026-27 financial year. Once the January RPIX figure was confirmed in February, it would be updated and sent again as this was the figure used under the contract. This figure would be confirmed to Members once available. 03/02/26 2
• There were no major issues to report on contract delivery. KPI targets were being met. Some delays to waste deliveries at the Manvers site had been experienced before Christmas, due to issues at the Ferrybridge Energy from Waste (EfW) site, which were compounded by equipment issues on site. The Contract Director from Biffa had thanked the councils for their patience over this period in a recent meeting.
• Due to these issues before Christmas and higher stock levels, landfill figures had increased but were still below the contractually allowed amount.
• There had been no recent complaints, which was to be expected at this time of year, as fly activity did not usually become an issue on sites until the spring.
• The insurance for the BDR waste facility had switched to AON as their insurance broker, following the sale to Biffa. AON had reported an increased appetite from insurers to accept more options for PFI arrangements, such as the BDR waste facility, due to the good preventative and control measures in place. The insurance had been placed and confirmed on 24 th December 2025, as required. The Board’s insurance consultant was currently reviewing the policy to ensure that sufficient cover was provided.
• Delays were still being experienced in obtaining the information from the Contractor for the updates to the Acid Scrubber. It was reported that the deadline set by the Environment Agency of April 2026 would not be met and that service had been promised an update on the current position by mid-February 2026. Once received, the BDR team and its consultants would carry out due diligence and review all material as required, to ensure that it meets the needs of the contract, while minimising financial risk to the Councils.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meeting held on (copy attached)Minutes | 90 KB | DownloadRead as text |
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Nov 2026 | BDR Managers ReportThat the budget for 2026/27 be agreed. 2. That the report be noted. | Agreed | Open |
| 16 Nov 2026 | BiffaThat the update be noted. | Noted | Open |
| 16 Nov 2026 | Risk RegisterThat the report be noted. | Noted | Open |
| 3 Feb 2026 | Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. | Approved | Open |
| 3 Feb 2026 | Any Other Business- The next meeting of the Barnsley, Doncaster and Rotherham Joint Waste Board will be held on Monday 6 July 2026, com... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.