Rotherham Metropolitan Borough Council

BDR Managers Report

Agreed Committee 1 paper

AI summaryThe Joint Waste Board agreed a £380,000 operational management budget for 2026/27, shared equally by Barnsley, Doncaster and Rotherham, and noted the managers' report. [D] [P11]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedThe Board also noted the managers' report. [D]
Money£380,000 agreed [D] [P11] [P15]Up from £340,000, split equally between three councils. [P11]
What happens nextManage the budget [P12] [P16]Adjust headings if needed; monitor Biffa's performance. [P12] [P34]
Who it affectsBarnsley, Doncaster and Rotherham [P11]Each council pays one third of the operational budget. [P11]

What was decided

The Board agreed the budget for 2026/27.

The agreed operational management budget is £380,000, up from £340,000. Each council will pay one third. Report P11, P15

The Board noted the managers' report.

Why

The proposal meets the team's anticipated requirements for 26/27. Report P11

The increase reflects annual pay increases, temporary pay uplifts for manager cover and higher consultant fees. Report P11

All of the 2026/27 budget may be needed, and significant savings are not anticipated. Report P16

What happens next

Individual budget headings may be moved between during the year. The hope is that costs and savings will be neutral overall. Report P12

The BDR team will continue to manage the operational budget proactively. Report P16

The team will keep monitoring contractual performance and raise issues with Biffa promptly. Report P34

The money

  • £380,000 Agreed 2026/27 operational management budget. Report P11, P15
  • £340,000 Previous operational management budget. Report P11
  • £30,025,798.64 Forecast total 2026/27 invoice payment to Biffa. Report P24
  • £6,443,880.09 Forecast total anticipated credits. Report P25
  • £23,581,918.55 Forecast total 2026/27 budget position. Report P26
  • £172,468.27 Agreed 2026/27 CELO budget. Report P119
  • £22,371.85 CELO spend to the end of September 2026. Report P120
  • £1.13M Initial Joint Insurance Cost Report claim, rejected. Report P70, P71

Options considered

  • Chosen: Approve the 2026/27 operational management budget of £380,000.. It meets anticipated requirements and funds staff pay, temporary manager cover and consultant fees. Report P11, P15
  • Chosen: Take the budget proposal to the next meeting.. The 6th July 2026 meeting was not quorate, meaning it lacked enough members to decide the proposal, so it moved to 16th November 2026. Report P11

Implications

  • Financial: The operational management budget rises from £340,000 to £380,000, with an equal share paid by each council. Report P11
  • Financial: The unitary charge forecast is £30,025,798.64, with £6,443,880.09 in anticipated credits and a £23,581,918.55 final budget position. Report P24, P25, P26
  • Financial: All of the operational management budget may be used, and significant savings are not anticipated. Report P16
  • Financial: No Energy Gainshare Payment is expected in 2026/27 because the rolling electricity price average no longer meets the payment trigger. Report P28
  • Risk: New permit requirements and original acid scrubber design errors may require an enhanced system. Biffa may claim extra costs, but the team will test any claim and seek to prevent costs above requirements passing to the councils. Report P80, P81, P84, P86
  • Risk: The contractor may pursue the rejected joint insurance cost claim as a dispute. The contract time limit for taking the rejection through the dispute process has lapsed. Report P73
  • Legal: The request to replace Renewi PLC as guarantor was rejected because Biffa Bid Co did not meet the contract requirements. Renewi PLC remains guarantor while the position is reviewed. Report P60
  • Staffing: The BDR Manager has handed in a notice to retire and the post is to be advertised. The Senior Contract Officer is acting as interim manager. Report P4

Who and where

  • Barnsley Council Report P11, P19
  • Doncaster Council Report P11, P19
  • Rotherham Council Report P11, P19
  • Biffa, the waste treatment operating contractor Report P24, P31
  • The BDR Team and its external advisers Report P3, P6
  • Residents and businesses using the waste treatment service Report P42, P50

Timeline

  • 22/23: The operational management budget was last increased to £340,000. Report P11
  • 25th of March 2025: A rejection letter for the fifth Joint Insurance Cost Report was sent to the contractor. Report P70
  • September 2025: The BDR Manager began an extended absence. Report P4
  • 6th July 2026: The meeting was not quorate, meaning it lacked enough members to decide the budget proposal. Report P11
  • 16th November 2026: The Board agreed the 2026/27 operational management budget and noted the managers' report. Report P11, P13
  • 2027: The acid scrubber permit compliance date now looks likely to move to 2027. Report P83
  • January 2027: The sixth Joint Insurance Cost Report is due. Report P75
  • 2030: The possible budget impact of the new emissions trading scheme is under review. Report P8

Plain English for the jargon

  • BDR: The waste partnership for Barnsley, Doncaster and Rotherham. [P3] [P11]
  • PFI: The waste treatment contract for the BDR Partnership and the Bolton Road facility. [P3] [P6]
  • Unitary Charge: The annual contract charge invoiced to each council and adjusted for anticipated credits. [P19] [P24] [P25]
  • JICR: Joint Insurance Cost Report, covering the contractor's claim for increased insurance costs. [P67] [P70]
  • QCiL: Qualified Change in Law, a possible contractual claim for extra costs caused by legal change. [P8] [P84] [P86]
  • RPIX: The January figure used to index the PFI unitary charge. [P22]
  • Parent Company Guarantee: A contract guarantor. Renewi PLC remains the guarantor. [P60]
  • Energy Gainshare: A payment calculated over a three year rolling average of electricity prices. [P28]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

That the budget for 2026/27 be agreed. 2. That the report be noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Barnsley, Doncaster and Rotherham Joint Waste Board

Item 5 BDR WASTE PFI CONTRACT

BDR MANAGER REPORT 2026-27 1 Governance 1.1 BDR Team

1.1.1 The BDR Team continues to work flexibly across the BDR Partnership and the PFI Waste Treatment facility at Bolton Road, and home working.

1.1.2 The BDR Team comprises: 1.1.2.1 BDR Manager – Paul Hutchinson has formally handed in his notice to retire following an extended absence from September 2025. His post will be going out to advert in due course. 1.1.2.2 The BDR Legal and Financial Advisors were available to function as mentors, support, gatekeepers, and critical friends for the BDR Team on matters contractual for the team during this time. 1.1.2.2.1 RMBC’s Waste Manager functioned as a mentor for the team on administrative matters within the RMBC system (Budgets, HR, Governance structure, and Rules). 1.1.2.2.2 Waste Managers from BMBC and CoDC functioned as mentors for the team on matters of BDR Partnership and Council/Site interface. 1.1.2.3 Senior Contract Officer – Carl Hewlett (stepped up as BDR Manager in the interim) 1.1.2.4 Technical Officer / Admin – Rhonda Fletcher

1.2External Support 1.1.3 The BDR Team continues to receive external legal, financial, and technical advice from specialists who have been advising the BDR Team on PFI matters and partnership working. 1.1.3.1.1 Neil Tindall Legal Services (Legal) 1.1.3.1.2 Roamine Advisory Limited - Craig Pember (Finance) 1.1.3.1.3 Stantec UK Limited (Technical) 1.1.3.1.4 IDRisk (Insurance)

1.1.4 The BDR Team and their external advisers continue to work on major and minor variations to the contract to improve the overall service delivery, processes, performance, and contractual interaction between BDR and the contractor.

1.1.5 Advisors are / will be assisting with negotiation / due diligence on: 1.1.5.1 Contract Parent Company Guarantee (PCG) change request - rejected. 1.1.5.2 Ferrybridge offtake contract Parent Company Guarantee (PCG) change request – Awaiting Detail from Biffa. 1.1.5.3 Deliverable Matrix Variation – ongoing. 1.1.5.4 Dispute Resolution Pannel agreement. 1.1.5.5 Landfill diversion Incentive - DRIM (annually).

1 1.1.5.6 Change in Law implications for the contract (and cost mitigation) arising from the Environment Act 2021 (R&WS, EPR, DRS & Simpler Recycling, etc) 1.1.5.6.1 Biffa indicated they wish to discuss potential implications to contract resulting from this. 1.1.5.7 Joint Insurance Cost Report (Bi-annually – Number 5 Received Jan 25 - Rejected) 1.1.5.7.1 Biffa indicated may wish to take to dispute but nothing further currently. 1.1.5.8 Annual Insurance Placement (24/2/25 for 2026) and waiver request for some aspects of Insurance requirements 1.1.5.9 Change request to remove the old Fire suppression system. 1.1.5.10 Qualified Change in Law (QCiL) claim for Environmental Permit changes and installation of Best Available Technologies (BAT’s) 1.1.5.10.1 BDR Team awaiting technical and financial date from Biffa (for QCiL claim) to allow due diligence and interrogation. 1.1.5.11 Changes/rebuild of AD Pasteurisation Tunnels and Acid Scrubber due to errors in the original design. 1.1.5.12 Review of new carbon Emissions Trading Scheme (ETS) requirements on Energy from Waste (EfW) sites (Ferrybridge) and potential (2030) budgetary impact on BDR Councils. Possibly including financial burden mitigation options/initiatives 1.1.5.13 Review of maintenance plans and lifecycle of Bolton Road plant and equipment. 1.1.5.14 Any future amendments to managing Persistent Organic Pollutants (POP’s) from EA directives. 1.1.5.15 Site condition survey and hand back obligation for Barnsley transfer station.

2 2 Financial

2.126/27 Operational Management Budget

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BDR Managers ReportReport 442 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 4 attended
GJ
Councillor Glyn JonesMember, expected
LM
Councillor Lynda MarshallMember, expected
DG
Councillor David GoddardMember, expected
RF
Rhonda FletcherCouncil Staff, expected

On this subject at Rotherham

Search all
  1. BDR Managers ReportThis decision
  2. BDR Managers ReportNoted
  3. BDR Managers ReportNoted
  4. BDR Managers ReportNoted
  5. BDR Managers ReportNoted
  6. BDR Managers Report 2018-19Noted

More from Rotherham Barnsley, Doncaster and Rotherham Joint Waste Board

All decisions
MeetingDecisionOutcome
16 Nov 2026 Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. Approved Open
16 Nov 2026 BiffaThat the update be noted. Noted Open
16 Nov 2026 Risk RegisterThat the report be noted. Noted Open
3 Feb 2026 Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. Approved Open
3 Feb 2026 Any Other Business- The next meeting of the Barnsley, Doncaster and Rotherham Joint Waste Board will be held on Monday 6 July 2026, com... Decided Open