Resolved
That the budget for 2026/27 be agreed. 2. That the report be noted.
AI summaryThe Joint Waste Board agreed a £380,000 operational management budget for 2026/27, shared equally by Barnsley, Doncaster and Rotherham, and noted the managers' report. [D] [P11]
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the budget for 2026/27 be agreed. 2. That the report be noted.
Item 5 BDR WASTE PFI CONTRACT
BDR MANAGER REPORT 2026-27 1 Governance 1.1 BDR Team
1.1.1 The BDR Team continues to work flexibly across the BDR Partnership and the PFI Waste Treatment facility at Bolton Road, and home working.
1.1.2 The BDR Team comprises: 1.1.2.1 BDR Manager – Paul Hutchinson has formally handed in his notice to retire following an extended absence from September 2025. His post will be going out to advert in due course. 1.1.2.2 The BDR Legal and Financial Advisors were available to function as mentors, support, gatekeepers, and critical friends for the BDR Team on matters contractual for the team during this time. 1.1.2.2.1 RMBC’s Waste Manager functioned as a mentor for the team on administrative matters within the RMBC system (Budgets, HR, Governance structure, and Rules). 1.1.2.2.2 Waste Managers from BMBC and CoDC functioned as mentors for the team on matters of BDR Partnership and Council/Site interface. 1.1.2.3 Senior Contract Officer – Carl Hewlett (stepped up as BDR Manager in the interim) 1.1.2.4 Technical Officer / Admin – Rhonda Fletcher
1.2External Support 1.1.3 The BDR Team continues to receive external legal, financial, and technical advice from specialists who have been advising the BDR Team on PFI matters and partnership working. 1.1.3.1.1 Neil Tindall Legal Services (Legal) 1.1.3.1.2 Roamine Advisory Limited - Craig Pember (Finance) 1.1.3.1.3 Stantec UK Limited (Technical) 1.1.3.1.4 IDRisk (Insurance)
1.1.4 The BDR Team and their external advisers continue to work on major and minor variations to the contract to improve the overall service delivery, processes, performance, and contractual interaction between BDR and the contractor.
1.1.5 Advisors are / will be assisting with negotiation / due diligence on: 1.1.5.1 Contract Parent Company Guarantee (PCG) change request - rejected. 1.1.5.2 Ferrybridge offtake contract Parent Company Guarantee (PCG) change request – Awaiting Detail from Biffa. 1.1.5.3 Deliverable Matrix Variation – ongoing. 1.1.5.4 Dispute Resolution Pannel agreement. 1.1.5.5 Landfill diversion Incentive - DRIM (annually).
1 1.1.5.6 Change in Law implications for the contract (and cost mitigation) arising from the Environment Act 2021 (R&WS, EPR, DRS & Simpler Recycling, etc) 1.1.5.6.1 Biffa indicated they wish to discuss potential implications to contract resulting from this. 1.1.5.7 Joint Insurance Cost Report (Bi-annually – Number 5 Received Jan 25 - Rejected) 1.1.5.7.1 Biffa indicated may wish to take to dispute but nothing further currently. 1.1.5.8 Annual Insurance Placement (24/2/25 for 2026) and waiver request for some aspects of Insurance requirements 1.1.5.9 Change request to remove the old Fire suppression system. 1.1.5.10 Qualified Change in Law (QCiL) claim for Environmental Permit changes and installation of Best Available Technologies (BAT’s) 1.1.5.10.1 BDR Team awaiting technical and financial date from Biffa (for QCiL claim) to allow due diligence and interrogation. 1.1.5.11 Changes/rebuild of AD Pasteurisation Tunnels and Acid Scrubber due to errors in the original design. 1.1.5.12 Review of new carbon Emissions Trading Scheme (ETS) requirements on Energy from Waste (EfW) sites (Ferrybridge) and potential (2030) budgetary impact on BDR Councils. Possibly including financial burden mitigation options/initiatives 1.1.5.13 Review of maintenance plans and lifecycle of Bolton Road plant and equipment. 1.1.5.14 Any future amendments to managing Persistent Organic Pollutants (POP’s) from EA directives. 1.1.5.15 Site condition survey and hand back obligation for Barnsley transfer station.
2 2 Financial
2.126/27 Operational Management Budget
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BDR Managers ReportReport | 442 KB | DownloadRead as text |
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Nov 2026 | Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. | Approved | Open |
| 16 Nov 2026 | BiffaThat the update be noted. | Noted | Open |
| 16 Nov 2026 | Risk RegisterThat the report be noted. | Noted | Open |
| 3 Feb 2026 | Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. | Approved | Open |
| 3 Feb 2026 | Any Other Business- The next meeting of the Barnsley, Doncaster and Rotherham Joint Waste Board will be held on Monday 6 July 2026, com... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.