Resolved
RESOLVED that: a) the report be noted. b) the projected revenue and capital budget positions for the year of £370,000 revenue efficiencies, and £10,587,000 from capital scheme re-phasing and potential savings be noted.
Corporate Governance Group noted this item on Thursday 8 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: a) the report be noted. b) the projected revenue and capital budget positions for the year of £370,000 revenue efficiencies, and £10,587,000 from capital scheme re-phasing and potential savings be noted.
1.1This report presents the budget position for revenue and capital as at 31 December 2017 along with the appropriate recommendations for referral to Cabinet. Given the current financial climate it is imperative that the Council maintains due diligence with regards to its finances and ensures necessary action is taken to maintain a robust financial position.
It is RECOMMENDED that the Corporate Governance Group note:
a) the projected revenue and capital budget positions for the year of £370,000 revenue efficiencies, and £10,587,000 from capital scheme re- phasing and potential savings.
3.1To demonstrate good governance in terms of scrutinising the Council’s on-going financial position and compliance with Council Financial Regulations.
4. Supporting Evidence
Revenue Monitoring
4.1The revenue monitoring statement by service area is attached at Appendix A with detailed variance analysis as at 31 December 2017 attached at Appendix B. This shows projected efficiency savings of £193,000 and additional funding of £197,000. This could improve throughout the remainder of the year as managers continue to drive cost savings, and raise income, against existing budgets and there wil be likely requests for carry forwards.
4.2Appendix A includes a Minimum Revenue Provision (MRP) of £1 million. This is a provision that the Council is required to make each year to cover the internal borrowing costs for the Arena which will be funded by New Homes Bonus.
4.3As documented at Appendix B the financial position to date reflects a number of positive variances including employee cost savings, savings from contracts, additional green waste income, investment income and recovery in housing benefit overpayments. The Council has also received an additional S31 grant for Flexible Homelessness Support which will support additional staffing resources included in the 2018/19 budget. 4.4 There are several negative variances, including an increase in the cost of insurance, variations in the cost of contracts, and an increase in the cost of NNDR (Business Rates) at East Leake Leisure Centre and the Arena following the 2017 national rates revaluation exercise.
4.5Following the close of a consultation exercise in January 2018 the Ministry of Housing, Communities and Local Government has indicated that the methodology for calculating the compensation for Small Business Rate Relief will be changing. The current projected year-end efficiency position does not include this alteration and the impact of additional reliefs announced by the Government in the Spring budget.
4.6At October Cabinet the use of a maximum of £20k of the revenue efficiencies towards a business case feasibility assessment concerning Bingham Leisure Centre was approved. This will reduce the projected revenue efficiencies for the year to £370,000.
Capital Monitoring
4.7The updated Capital Programme monitoring statement as at 31 December 2017 is attached at Appendix C which provides further details and the progress of the schemes and both re-phasing and potential savings of £10,587,000. A summary of the projected outturn and funding position is shown in the table below:-
CAPITAL PROGRAMME MONITORING - DECEMBER 2017
EXPENDITURE SUMMARY Current Projected Projected Budget Actual Variance £000 £000 £000 Transformation 17,027 8,151 (8,876) Neighbourhoods 2,208 1,267 (941) Communities 399 229 (170) Finance & Corporate Services 8,381 7,781 (600) Contingency 270 270 - 28,285 17,698 (10,587) FINANCING ANALYSIS
Capital Receipts (15,277) (13,222) 2,055 Government Grants (5,167) (1,947) 3,220 Other Grants/Contributions (1,969) (1,340) 629 Use of Reserves (3,189) (289) 2,900 Internal Borrowing (2,683) (900) 1,783 (28,285) (17,698) 10,587 NET EXPENDITURE - - -
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revenue & Capital Budget MonitoringAgenda | 369 KB | DownloadRead as text |
Follow Corporate Governance Group at Rushcliffe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Feb 2019 | Internal Audit Progress Report - Quarter 3 2018/19It was RESOLVED that the internal Audit Progress Report – Quarter 3 be noted. | Noted | Open |
| 7 Feb 2019 | External Audit Strategy 2019It was RESOLVED that the External Audit Strategy be approved. | Approved | Open |
| 7 Feb 2019 | Internal Audit Strategy 2019 - 2022RESOLVED that the Internal audit Strategy and Audit Plan for 2019/22 be approved. | Approved | Open |
| 7 Feb 2019 | Capital and Investment Strategy 2019/20RESOLVED that the Group approve the following for Full Council on 7 March 2019. a) The Capital Strategy and Prudentia... | Approved | Open |
| 7 Feb 2019 | Revenue and Capital Budget Monitoring - Quarter 3 2018/19It was RESOLVED that report be referred to Cabinet for approval noting: a) The projected revenue position for the yea... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.