It was RESOLVED that the report be approved and the following be noted: a) the expected revenue budget efficiency for the year of £1.786m and proposals to earmark this for cost pressures at Paragraph 4.6 and Table 2 to the report; b) the projected capital budget efficiencies of £3.598m including the reprofiling of schemes totalling £1.435m at Paragraph 4.9 and Table 3 to the report; c) the removal of £1m from the Capital Programme for travellers site acquisition and £1.5m to be added in relation to carbon offsetting land acquisitions for the 2024/25 programme going forward at Paragraph 4.10 to the report; and d) the expected largely balanced outturn position for special expenses at Paragraph 4.7 to the report.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1This report presents the budget position for revenue and capital as at 30 September 2024.
1.2The financial climate is beginning to show signs of improvement; however, the effect of recent high inflation has impacted both residents’ cost of living and created cost pressures for the Council’s budget. It is imperative that the Council maintains due diligence with regards to its finances and ensures necessary action is taken to ensure a balanced budget is maintained.
1.3At Quarter two 2024/25, there is a predicted net revenue efficiency of £1.786m. Significant variances are highlighted in Table 1. This represents a variance of 11.75% against budgeted Net Service Expenditure. This is proposed to be earmarked for additional cost pressures and financial challenges discussed below, in particular meeting challenges with regards to demand for ongoing homes for resettled Ukraine nationals, improving economic growth, providing for increased demand for Disabled Facilities Grants and modernising council technology infrastructure. The position may change as further variances are identified during the year.
1.4There is a capital budget underspend projected of £3.598m, this includes rephasing of £1.525m to 2025/26 and the acceleration of £90k due to vehicle replacement for a new tanker from 2025/26, now required for 2024/25.
1.5The report has been scrutinised by Corporate Overview Group on 19 November 2024, and no significant issues were raised.
Recommendation
It is RECOMMENDED that Cabinet approves the attached report noting:
a) the expected revenue budget efficiency for the year of £1.786m and proposals to earmark this for cost pressures given at paragraph 4.6 and Table 2; b) the projected capital budget efficiencies of £3.598m including the reprofiling of schemes totalling £1.435m (paragraph 4.9 and Table 3);
c) the removal of £1m from the Capital Programme for travellers site acquisition and £1.5m to be added in relation to carbon offsetting land acquisitions for the 2024/25 programme going forward (paragraph 4.10); and
d) the expected largely balanced outturn position for special expenses (paragraph 4.7).
Reasons for recommendation
To demonstrate good governance in terms of scrutinising the Council’s on- going financial position and compliance with Council Financial Regulations.
4. Supporting Information
Revenue Monitoring
4.1For 2024/25, the overall budget variance is expected to be an efficiency of £1.786m with proposals to earmark the in-year efficiencies for specific reserves as detailed in Appendix A, should this direction of travel be maintained.
4.2Table 1 below summarises the main pressures and efficiencies with a full summary of all significant variances at Appendix B.
Table 1: Main Pressures and Efficiencies
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.