It was RESOLVED that the following be approved for submission to Full Council: a) the revised projections to the 2020/21 revenue budget and remainder of the current Medium Term Financial Strategy (MTFS) as referred to in Appendix A of the report, as a result of the impact of Covid-19; b) the revised projections to the Capital Programme for 2020/21 and the impact on the Capital Programme over the MTFS as referred to in Appendix B of the report; c) the changes to the Transformation Strategy as referred to in Appendix C of the report; d) the Council Tax Hardship Fund Policy Paper as referred to in Appendix D of the report and its current application; e) the strategy of utilising in-year budget efficiencies, the Organisation Stabilisation reserve, reviewing the use of existing reserves, reduced use of Voluntary Revenue Provision and therefore use of New Homes Bonus; as fiscal levers so the Council balances the budget and delivers its corporate objectives, as referred to in paragraph 4.8.6 of the report ; and f) the transfer of three reserves totalling to £0.524m, as referred to in paragraph 4.8.7 of the report, to the Organisation Stabilisation Reserve from 2020/21 and the revised anticipated position over the next five years as referred to in Appendix E of the report.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1This report provides an expected outturn budget for the year 2020/21 and the remainder of the current Medium Term Financial Strategy (MTFS). This is based upon the latest government guidance regarding the release from lockdown and estimated impact based on current trends and information available such as government funding. The situation is fluid with the anticipated financial deficit this year estimated at £0.422m and for 2021/22 £1.91m. The Council’s normal governance arrangements through Cabinet and Corporate Overview Group will report on the changing position and the MTFS will be reported to Full Council in March 2021.
1.2Full Council approved the 2020/21 balanced budget on 5 March 2020. The Covid-19 pandemic has caused significant financial pressures including loss of income (e.g. property and car parks), additional costs (namely supporting the Leisure Centres and additional anti-social measures) and reductions in Council Tax and Business Rates income. Government funding has been received that mitigates some of the losses however further measures are needed to address the remaining budget gap.
1.3Officers have reported the potential financial impact of the emerging Covid-19 situation each month to Cabinet since the Covid-19 pandemic began. Although lockdown restrictions have been further eased, gradually returning to normality there will be some irrecoverable losses from the lockdown period in addition to the legacy issues that are likely to impact on the financial position for the remainder of the year. There is also a risk of a second wave of the virus or a local outbreak and therefore a return to a local lockdown cannot be ruled out.
1.4This report is to be considered by Cabinet with recommendations to Full Council. 2. Recommendation
It is RECOMMENDED that Cabinet approves for Full Council:
a) the revised projections to the 2020/21 revenue budget and remainder of the current MTFS in Appendix A as a result of the impact of Covid-19;
b) the revised projections to the Capital Programme for 2020/21 and the impact on the Capital Programme over the MTFS in Appendix B;
c) the changes to the Transformation Strategy in Appendix C;
d) the Council Tax Hardship Fund Policy Paper at Appendix D and its current application;
e) the strategy of utilising in-year budget efficiencies, the Organisation Stabilisation reserve, reviewing the use of existing reserves, reduced use of Voluntary Revenue Provision and therefore use of New Homes Bonus; as fiscal levers so the Council balances the budget and delivers its corporate objectives (paragraph 4.8.6); and
f) the transfer of three reserves totalling to £0.524m as stated at paragraph 4.8.7 to the Organisation Stabilisation Reserve from 2020/21 and the revised anticipated position over the next 5 years (Appendix E).
Reasons for recommendation
To ensure that the expected outturn is incorporated into the 2020/21 budget along with proposals to manage losses ensuring a balanced budget.
4. Supporting Information
4.1Revenue
4.1.1 A number of changes have been made to the budget projections including additional costs and loss of income. It is too soon to estimate how quickly the pre-COVID situation will return, if at all this year or when in the medium term, with uncertainty surrounding consumer confidence. However, prudent estimates have been made upon the level of income expected in line with current government guidance for the phased release of lockdown.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.