Rushcliffe Borough Council
Cabinet, Tuesday 9 February 2021 at 7.00pm

Crematorium Update

Decided Executive 1 paper

Cabinet decided this item on Tuesday 9 February 2021. Below is the council's own wording, with the papers it was decided on.

Item46

Resolved

It was RESOLVED that the allocation of an additional £2m in the 2021/22 capital programme for the delivery of a new crematorium, to be included in the Council’s Medium Term Financial Strategy be supported.
Word for word from the decision Rushcliffe published for this meeting. Source: democracy.rushcliffe.gov.uk

Follow this further

Built from Rushcliffe's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1The Council’s Corporate Strategy Action Plan (2019-2023) identifies the development of a crematorium in the Borough by 2022 as a priority: to deliver this important community infrastructure in order to offer additional capacity for cremations in Rushcliffe.

1.2In July 2020, Cabinet authorised the Chief Executive to appoint a multi- disciplinary design team to develop detailed designs for the crematorium and provide a pre-tender build estimate. The Council appointed Ridge and Partners who have been working with a team of specialists and the Council to design a high quality, efficient and fit for purpose facility. The estimated cost plan is greater than the budget previously agreed by Cabinet and this report provides further details outlining the reasons why; the impact on the business case; and requests approval for a further allocation in the Council’s capital programme.

1.3Cabinet also requested the Chief Executive to continue investigations into new technologies to enable the delivery of a greener crematorium for the Borough. Further information about the outcome of these investigations is included in this report.

Recommendation

It is RECOMMENDED that Cabinet supports the allocation of an additional £2m in the 2021/22 capital programme for the delivery of a new crematorium, to be included in the Council’s Medium Term Financial Strategy.

Reasons for recommendation

3.1There is demand within the Borough for a modern and efficient crematorium, the development of the proposed crematorium will meet this demand and investment in the facility makes sound economic sense for the Council.

3.2The crematorium will provide a modern, accessible, community facility for the residents of Rushcliffe, a Borough which has been tasked by Government with delivering a large increase in housing (an additional 13,150 homes with the OFFICIAL

adoption of the Local Plan), and will therefore see a corresponding growth in population and services required.

3.3The project costs have increased for three specific reasons, as outlined in section 4 below. Costs have been scrutinised and challenged and a benchmark exercise has been undertaken which demonstrates the pre-tender estimate is within an acceptable range.

3.4Based on a project cost of £8.5m (including land), it is expected that the crematorium will provide the council with an estimated revenue cash return of £68m over the next 40 years with the in-house operating model. This represents an internal rate of return of 9%.

4. Supporting Information

Background

4.1.1. In 2018, Cabinet approved the principle of providing a new crematorium in Stragglethorpe to provide much needed additional community infrastructure to serve Rushcliffe residents. £6.5m was included in the Council’s capital programme to purchase the site and develop a crematorium.

4.1.2. In July 2020, Cabinet authorised the Chief Executive to undertake a procurement exercise to appoint a multi-disciplinary design team to develop detailed designs for the crematorium and perform contract administration and management duties for the construction contract. Following a procurement exercise, in September 2020, Ridge and Partners was appointed having demonstrated a clear understanding of the unique design requirements of a crematorium and an innovative approach and commitment to environmental credentials.

4.1.3. Officers have been working with Ridge to develop designs for the crematorium and ensure that the facility will provide the best possible experience for our residents and contribute to our carbon neutral ambitions.

4.1.4. After a substantial amount of collaborative work with a keen focus on value engineering, Ridge has prepared a pre-tender estimate for the project, which exceeds the allocated budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Crematorium UpdateReport 351 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
SR
Councillor Simon RobinsonChairman, present
AE
Councillor Andy EdyveanVice-Chairman, present
AB
Councillor Abby BrennanCommittee Member, present
RI
Councillor Rob InglisCommittee Member, present
GM
Councillor Gordon MooreCommittee Member, present
RU
Councillor Roger UptonCommittee Member, present
LA
Leanne AshmoreOfficer, in attendance
DB
Dave BanksOfficer, in attendance
PL
Peter LinfieldOfficer, in attendance
KM
Kath MarriottOfficer, in attendance
DM
Dave MitchellOfficer, expected
SS
Sanjit SullOfficer, in attendance

All 16 on the meeting page

On this subject at Rushcliffe

Search all
  1. Crematorium UpdateThis decision
  2. CrematoriumAgreed
  3. Strategic Land Acquisition for Potential CrematoriumApproved

More from Rushcliffe Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Local Centre Investment PlansIt was RESOLVED that Cabinet: a) supports the creation of a £1m Towns Fund to be recommended for inclusion in the Med... Approved Open
13 Oct 2026 Council Tax Policy Changes (Second Homes Premium and Relief for Terminally Ill Residents and Foster Carers)It was RESOLVED that the recommendations from Communities Scrutiny Group be considered and that: a) the revocation of... Approved Open
13 Oct 2026 Ratcliffe on Soar Local Development OrderIt was RESOLVED that : a) the should remain in force in its current form and that no amendments are required at the p... Decided Open
8 Sep 2026 Quarter 1 Finance ReportIt was RESOLVED that the report be approved and the following be noted: a) the projected revenue budget efficiency fo... Approved Open
14 Jul 2026 Financial Outturn 2025-26It was RESOLVED that: a) the 2025/26 revenue position and efficiencies identified in Table 1 and Appendix A and B be ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies