RESOLVED that the Corporate Overview Group: a) considered the detailed information contained within the annual Health and Safety Report b) noted the change ... view the full minutes text for item 10.
Corporate Overview Group noted this item on Tuesday 5 September 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Corporate Overview Group: a) considered the detailed information contained within the annual Health and Safety Report b) noted the change ... view the full minutes text for item 10.
OFFICIAL
HEALTH AND SAFETY ANNUAL REPORT
April 2022 to end March 2023 OFFICIAL
1.0INTRODUCTION
1.1This annual report sets out the Council’s occupational health and safety performance during the twelve month period 1 April 2022 to 31 March 2023. As with previous reports it is split into a number of sections highlighting the key issues. It also sets out new policies which have been implemented as part of the control measures within the corporate health and safety framework.
1.2Furthermore the update provides an indication of the effectiveness and success of the health and safety control measures the Council has in place with evidence showing training delivered, progress towards meeting health and safety aims and objectives and the number of accidents recorded.
2.0CHANGES TO RISK PROFILE
2.1This financial year has seen a number of changes which have resulted in altering the health and safety risk profile of the Council.
2.2As you will be aware Streetwise services came back in-house in September 2022, resulting in a change from having a contractual overview of health and safety compliance, to the team being a part of the Council’s establishment. Significant work was undertaken in the lead up to the transfer including audits see section 4.3, but also since September to support the team with the transition into health and safety policies and procedures at Rushcliffe. This has resulted in an increase in the establishment head count from 259 to 312 employees, and sees the Council providing more higher risk services such as litter picking of high speed roads and arboriculture work.
2.3Bingham Arena opened its doors to the public in February 2023, adding a great facility to the Council’s portfolio. This resulted in significant health and safety work for the contract and project management team during development but has provided the Council with a modern safe facility. This has enabled us to remove services from the previous Bingham Leisure Centre site which as expected was high maintenance to ensure health and safety compliance of the building. Toothill sports centre will remain open with provision of leisure services through Parkwood who will provide regular update reports on health and safety compliance.
2.4Rushcliffe Oaks was officially opened for services on 3 April 2023. The delivery of a new crematorium service has required regular health and safety input and support to ensure its successful opening. The running of the electric powered cremator is an obvious risk on the new site, but in addition to this there are nine acres of memorial grounds to maintain. The health and safety performance at this site will be included and reported on moving forward.
3.0PROVISION OF HEALTH AND SAFETY ADVICE AND SUPPORT
3.1As explained in the annual report last year, the delivery of the health and safety advisor function is delivered on a day to day basis through the Strategic HR Manager but with the support from Bolsover District Council for the delivery of the proactive areas such as audits, inspections and policy reviews. The Strategic HR Manager works closely with the Bolsover Team to ensure effective support from Bolsover as and when required. OFFICIAL
4.0KEY ACTIVITIES
4.1COVID-19 In April 2022 the COVID restrictions were lifted and all the previous guidance documents and risk assessments were reviewed and updated to ensure they were reflecting the Governments guidance to “Living with COVID and Respiratory Illnesses”. Once completed the health and safety involvement in COVID was dramatically reduced, but still overseeing areas such as provision of PPE and supporting staff and managers with risk assessing when staff tested positive for COVID.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enc. 1 for Health and Safety Annual ReportReport | 439 KB | DownloadRead as text |
PDF |
Health and Safety Annual ReportReport | 155 KB | Download |
Follow Corporate Overview Group at Rushcliffe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Consideration of Scrutiny Group Work ProgrammesIt was agreed that the Assistant Director for Growth, Property and Projects would meet with Councillor’s Combellack a... | Agreed | Open |
| 16 Jun 2026 | Diversity Annual Report and update on the Equality and Diversity StrategyRESOLVED that the Corporate Overview Group: a) considered and endorsed the information provided for the Diversity Ann... | Decided | Open |
| 16 Jun 2026 | Consideration of Scrutiny Group Work ProgrammesIt was agreed that the item was not suitable for scrutiny at this time and should be revisited when national changes ... | Agreed | Open |
| 24 Feb 2026 | Mid-point Review of the Corporate StrategyRESOLVED that Corporate Overview Group: a) Considered the information provided outlining the Council’s progress towar... | Approved | Open |
| 24 Feb 2026 | Consideration of Scrutiny Group Work ProgrammesRESOLVED that the Corporate Overview Group: a) Considered any additional items for scrutiny from current Cabinet Forw... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.