CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rushcliffe Borough Council
Cabinet, Tuesday 11 November 2025 at 7.00pm

Conservation Area Review Project - Summary

Decided Executive 2 papers

AI summaryRushcliffe Cabinet acknowledged completion of a three-year Conservation Area review covering 33 appraisals, including two new areas adopted, taking the borough total to 34.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSuccessful completion of Conservation Area review noted by Cabinet
MoneyNo new moneyCosts covered within existing 2022-25 budgets
What happens nextFinal two appraisals to be finalisedProject effectively complete once last two appraisals finalised
Who it affectsConservation Areas and planning applicantsUpdated appraisals used as material planning considerations

What was decided

Cabinet acknowledged the successful completion of the three-year Conservation Area review project. Report P7, P35

Why

The review discharged the local planning authority's duty under Section 69 of the Planning (Listed Building and Conservation Areas) Act 1990 to review Conservation Areas from time to time. Report 1.4, 4.10, P27

Updated Conservation Area Appraisals are material considerations when deciding planning applications and help guard against inappropriate development. Report 1.3, 5.2

Community involvement through 12 community-led reviews was essential to completing the programme on schedule. Report 4.4, 4.9

What happens next

The remaining two appraisals are being finalised, at which point the review project is effectively complete. Report 3.2

No further action is required from Cabinet; updated appraisals will be used as a material planning consideration going forward. Report 1.3, P20

Options considered

  • Rejected: Not review Conservation Areas and their appraisals. Out of date or absent appraisals risk inappropriate development and loss of historic features Report 5.2

Implications

  • Legal: Review meets the Section 69 duty to determine which areas are of special architectural or historic interest. Report P27
  • Financial: No new financial implications; fixed-term post costs were included in approved 2022-25 budgets. Report P26
  • Equalities: No equalities implications arising from the recommendation. Report P28
  • Other: No adverse crime and disorder implications under Section 17 of the Crime and Disorder Act 1998. Report P30
  • Other: No biodiversity net gain implications. Report P32

Who and where

  • Residents in the 34 Conservation Areas across Rushcliffe Report 4.4, P34
  • Planning applicants within or affecting Conservation Areas Report 1.3
  • Twelve communities that took part in community-led appraisal reviews Report 4.4, 4.9

Timeline

  • 2008 to 2011: Previous borough-wide review of Conservation Areas Report 1.5
  • July 2022 to beginning of July 2025: Fixed-term post covered the three-year review period Report 1.5
  • 2022: Funding identified for additional resource to undertake full review Report 1.5
  • 2025-11-11: Cabinet acknowledged successful completion of the review project

Plain English for the jargon

  • Conservation Area Appraisal: A document identifying the special qualities of a designated Conservation Area and how it can be improved, used as a material planning consideration once adopted.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28

Resolved

It was RESOLVED that the successful completion of the review project be acknowledged.
Word for word from the decision Rushcliffe published for this meeting. Source: democracy.rushcliffe.gov.uk

Follow this further

Built from Rushcliffe's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1Section 69 of the Planning (Listed Building and Conservation Areas) Act 1990 (the 1990 Act) imposes a duty on local planning authorities to designate as Conservation Areas any ‘areas of special architectural or historic interest the character or appearance of which it is desirable to preserve or enhance’.

1.2Conservation Area Appraisals identify the special qualities of a designated Conservation Area and set out how the Conservation Area can be improved, along with the local priorities for enhancements.

1.3Once adopted, Conservation Area Appraisals are a material consideration when considering planning applications within the Conservation Area. The adoption of appraisals will allow for positive management and change within a designated area and its setting whilst safeguarding historic character and appearance.

1.4The designation of Conservation Areas and the adoption of Conservation Area Appraisals should be continually reviewed. Section 69(2) states that “It shall be the duty of a local planning authority from time to time to review the past exercise of functions under this section and to determine whether any parts or any further parts of their area should be designated as conservation areas; and, if they so determine, they shall designate those parts accordingly.”

1.5A review of Conservation Areas across the Borough was last undertaken in the period 2008 to 2011. In 2022, funding was identified to appoint additional resource across a three-year period to review the complete set of appraisals. This led to the appointment of a fixed term contract position beginning in July of 2022 through to the beginning of July 2025.

1.633 Conservation Area Appraisals have successfully been reviewed, including 31 reviews of existing Conservation Areas, and the adoption of two new Conservation Areas. 2. Recommendation

It is RECOMMENDED that Cabinet considers the information contained within this report and acknowledges the successful completion of this review project.

Reasons for recommendation

3.1Across the three years, the review of Conservation Areas successfully updated appraisals for the 31 Conservation Areas, as well as adopting two additional Conservation Areas.

3.2This report is presented as an update for Cabinet at the conclusion of the review, which will effectively be complete at the point that the final two appraisals have been finalised.

4. Supporting Information

4.1A copy of a table showing the timetable of review and identifying which appraisals were undertaken by the community and which were undertaken by officers is appended to this report (Appendix A).

4.2It was always appreciated that reviewing appraisals across three years would be a challenging task. To that end, the two most recent appraisals for Conservation Areas in Kneeton (adopted 2018) and Cropwell Bishop (adopted 2021), which had been designated as new Conservation Areas since the last major review in 2008/11 could be treated as ‘optional’.

4.3In addition to completing reviews of all the existing Conservation Areas, including the two referenced above, which were not considered high priority, it was also possible to adopt two new Conservation Areas with accompanying appraisals. These were heavily reliant upon community involvement to ensure that delivering them did not prejudice the completion of the main task of reviewing existing appraisals and as such, the communities in these two areas should be particularly acknowledged for their input and work in bringing forward these two new areas for adoption as Conservation Areas.

4.4Of the now 34 Conservation Areas within the Borough, 22 have had the review undertaken as an officer-led process, and 12 were reviewed on a community- led basis.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Conservation Area Review MatrixAppendix A 145 KB Download
PDF
Conservation Area Review Project: SummaryReport 198 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 17 attended
CC
Charlotte Caven-AtackOfficer, expected
NC
Councillor Neil ClarkeChair, present
AB
Councillor Abby BrennanVice-Chair, present
RI
Councillor Rob InglisCommittee Member, present
RU
Councillor Roger UptonCommittee Member, present
DV
Councillor Davinder VirdiCommittee Member, apologies
JW
Councillor Jonathan WheelerCommittee Member, present
LA
Leanne AshmoreOfficer, in attendance
DB
Dave BanksOfficer, in attendance
RC
Rachel ClackOfficer, in attendance
AH
Adam HillOfficer, in attendance
PL
Peter LinfieldOfficer, in attendance

All 17 on the meeting page

On this subject at Rushcliffe

Search all
  1. Conservation Area Review Project - SummaryThis decision
  2. Draft Revised Character Appraisal and Conservation Area for Colston BassettApproved
  3. Draft Character Appraisal and Proposed Conservation Area for ScrevetonApproved
  4. Adoption of Cropwell Bishop Conservation AreaApproved
  5. Aslockton Conservation Area ConsultationAgreed
  6. Draft Character Appraisal and Proposed Conservation Area for Cropwell BishopApproved

More from Rushcliffe Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Local Centre Investment PlansIt was RESOLVED that Cabinet: a) supports the creation of a £1m Towns Fund to be recommended for inclusion in the Med... Approved Open
13 Oct 2026 Council Tax Policy Changes (Second Homes Premium and Relief for Terminally Ill Residents and Foster Carers)It was RESOLVED that the recommendations from Communities Scrutiny Group be considered and that: a) the revocation of... Approved Open
13 Oct 2026 Ratcliffe on Soar Local Development OrderIt was RESOLVED that : a) the should remain in force in its current form and that no amendments are required at the p... Decided Open
8 Sep 2026 Quarter 1 Finance ReportIt was RESOLVED that the report be approved and the following be noted: a) the projected revenue budget efficiency fo... Approved Open
14 Jul 2026 Financial Outturn 2025-26It was RESOLVED that: a) the 2025/26 revenue position and efficiencies identified in Table 1 and Appendix A and B be ... Noted Open