Rushcliffe Borough Council
Cabinet, Tuesday 13 January 2026 at 7.00pm

East of Gamston/North of Tollerton Development Framework Supplementary Planning Document

Approved Executive 4 papers

AI summaryRushcliffe Cabinet pauses the Gamston/Tollerton urban extension planning document pending a highways solution, with the aim of bringing it back to Cabinet by 10 March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPending more detailed highways information, especially A52 connectivity
MoneyNot stated
What happens nextCabinet by 10 March 2026Further consideration after highways solution is provided
Who it affects247 hectare Gamston/Tollerton strategic siteMixed-use allocation including housing, employment, community facilities

What was decided

Cabinet continues to support the principle of a Development Framework SPD for the Gamston/Tollerton Sustainable Urban Extension.

The current SPD approval process is paused in response to comments made to the public consultation, while more detailed highways information is requested, especially on connectivity of the site to and across the A52.

The Leader of the Council will write to the site owners, developers and promoters, including Nottinghamshire County Council as landowner of part of the site, and to National Highways, asking them to work at pace to reach a satisfactory highways solution.

Why

Concerns about highways, particularly the A52, were raised during the public consultation that ran from 1 October 2025 to 5 November 2025. Report 1.12

Access arrangements to the site from the A52 have not yet been determined and are still the subject of discussion with the highways authorities. Report 2.9

The site is a long-term commitment for the Council in meeting the borough's growth needs and is expected to create a new neighbourhood within Rushcliffe. Report 1.5, 2.1

What happens next

The Leader will write to landowners, developers, promoters, the County Council as Highways Authority and National Highways, so the SPD can return to Cabinet by 10 March 2026.

Any further detailed highways and Infrastructure Delivery Plan information will be published for public consultation if appropriate.

Future recommendations from the Local Development Framework Group will be considered.

Options considered

  • Rejected: Continue with current SPD approval process. Public consultation comments highlighted the need for a satisfactory highways solution, particularly A52 connectivity, before approval.
  • Chosen: Pause SPD approval while more detailed highways information is sought. Allows the Leader to press for an urgent highways solution with site owners, the County Council and National Highways, with a return to Cabinet by 10 March 2026.

Implications

  • Legal: SPDs are material planning considerations when deciding planning applications but do not form part of the statutory development plan and cannot introduce new policies; the pause means the document is not yet adopted. Report 1.7
  • Risk: Delivery of the allocation is dependent on a satisfactory highways solution; without it, the SPD cannot progress and the site cannot be developed in line with Policy 25. Report 2.9
  • Other: The site includes Nottingham Airport, which will close and cease operations; no new dwellings on the allocation will be permitted to be occupied while the airport is still operating. Report 2.13
  • Other: Nottingham Airport closure is expected to free up the brownfield area for redevelopment as part of the wider mixed-use allocation. Report 2.13, 1.16

Who and where

  • Site owners, developers and promoters, including Nottinghamshire County Council as landowner of part of the site
  • Nottinghamshire County Council as Highways Authority and National Highways
  • Existing residents of Tollerton and Bassingfield, whose separation from the new development must be preserved through green buffer and Green Belt boundaries Report 1.17, 3.9
  • Future residents and users of the planned new neighbourhood, expected to be delivered over 15 to 20 years Report 2.1, 2.10

Timeline

  • 2014-12: Rushcliffe Local Plan Part 1: Core Strategy adopted Report 1.21
  • 2025-02: Tollerton Neighbourhood Plan adopted, covering the strategic allocation site Report P66
  • 2025-10-01 to 2025-11-05: Public consultation on the draft Gamston/Tollerton SPD Report 1.12
  • 2026-01-13: Cabinet decision to pause the SPD approval process
  • by 2026-03-10: SPD to return to Cabinet for further consideration
  • 2026: Emerging Greater Nottinghamshire Strategic Plan due for adoption Report 3.1
  • Up to 2028: Around 2,500 dwellings planned within the allocation Report 1.1
  • Post 2028: Up to a further 1,500 homes planned within the allocation Report 1.1

Plain English for the jargon

  • SPD: Supplementary Planning Document, providing more detailed guidance on policies in an adopted local plan but not forming part of the development plan
  • SUE: Sustainable Urban Extension, a planned large-scale mixed-use development on the edge of an existing settlement
  • IDP: Infrastructure Delivery Plan, setting out the strategic infrastructure needed and its anticipated indicative cost
  • A52(T): A52 trunk road, the major road running along the western side of the allocation
  • NPPF: National Planning Policy Framework, the national planning policy document
  • SuDS: Sustainable Drainage System, a drainage approach required as part of the development
  • NCA: National Character Area, a landscape classification produced by Natural England
  • BHL: Building for a Healthy Life, a design guidance tool for assessing new development
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item53

Resolved

It was RESOLVED that Cabinet: a) continues to support the principle of a Development Framework Supplementary Planning Document (SPD) for the Gamston/Tollerton Sustainable Urban Extension; b) pauses the current SPD approval process in response to comments made to the public consultation, whilst more detailed information is requested on highways, especially the connectivity of the site to and across the A52. c) requests the Leader of the Council to write to: · the site owners/developers/promoters, including Nottinghamshire County Council as landowner of part of the site, to ask them to urgently provide the outstanding highways solution; and · Nottinghamshire County Council as Highways Authority and National Highways to work proactively and at pace to reach a satisfactory highways solution; so that this SPD can be brought back to Cabinet by 10 March 2026 for further consideration; d) requires that any further detailed highways and Infrastructure Delivery Plan information is published for public consultation if appropriate; e) considers any future recommendations made by the Local Development Framework Group; and f) thanks Council officers and others for the significant amount of work that has been done.
Word for word from the decision Rushcliffe published for this meeting. Source: democracy.rushcliffe.gov.uk

Follow this further

Built from Rushcliffe's papers

What the report saysPro

Report to Cabinet

Appendix 1: Revised Draft East of Gamston/North of Tollerton Development Framework Supplementary Planning Document East of Gamston/North of Tollerton Development Framework Supplementary Planning Document

Date: TBC 1. Introduction

Purpose and Role of this SPD Preparation of this SPD The Allocation and Context Planning Policy Background National Guidance Introduction

This Supplementary Planning Document (SPD) has been prepared as a collaboration between Rushcliffe Borough Council and the main landowners and developers of the site East of Gamston and North of Tollerton.

Purpose and Role of this SPD

1.1This SPD concerns the Local Plan allocation known as “Strategic Allocation East of Gamston/ North of Tollerton”. The purpose of this document is to provide further guidance and a development framework for the whole of the strategic site allocation at Gamston, which is the subject of an allocation for mixed-use development including around 2,500 dwellings up to 2028, up to a further 1,500 homes post 2028, around 13.7 additional hectares of employment, neighbourhood centres, blue and green infrastructure, Biodiversity Net Gain and a range of community facilities.

1.2Given the multiple ownerships on-site, the allocation is likely to be developed through a number of planning applications coming forward at different times. This SPD sets out specific requirements of the local authority, the local highway authority, the local education authority and health providers to ensure those submitting applications are informed about the requirements from the outset. The locations of proposed infrastructure on Figure 41 45 show the preferred location of infrastructure to create a sustainable new neighbourhood, subject to any refinements required as a result of detailed work and additional evidence that emerges through the development management process.

1.3The Council will only accept variations to the preferred locations on Figure 40 44 and Figure 41 45 where proposals are supported by robust evidence and, in circumstances involving the relocation of infrastructure between landowners, where the Council is satisfied that the infrastructure will be delivered in full and at the appropriate time and in general accordance with the approach and provisions outlined within this SPD. 1.4. The SPD guidance and a development framework in this document, including contributions expected to both on-site and off-site infrastructure requirements, will apply to all areas within the strategic allocation, including any development/re- development of the existing residential areas and their associated land (e.g. equine paddocks) on Tollerton Lane and any redevelopment of existing employment land located to the south of Spire Hospital. Nevertheless, the new (and existing and re-developed) employment uses on the site would be exempt from certain contributions towards Infrastructure such as education provision.

1.5The site is a long-term commitment for the Council in meeting the growth needs of the Borough and it will continue to be built beyond the local plan period. Once built, it will create a new neighbourhood within Rushcliffe, and it is thus important for the Council and developers of the site to ensure this meets the highest possible standard.

1.6This SPD fulfils the requirement of Policy 25 of the Local Plan which requires that the design and layout of the proposal be determined through a masterplanning process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
East of Gamston/North of Tollerton Development Framework Supplementary Planning DocumentSupplementary 230 KB Download
PDF
Enc. 1 for Gamston Strategic Urban Extension SPDReport 4.7 MB DownloadRead as text
PDF
Enc. 2 for Gamston Strategic Urban Extension SPDReport 857 KB Download
PDF
Enc. 3 for Gamston Strategic Urban Extension SPDReport 386 KB Download

At this meeting

Whole meeting
50Minutes of the Meeting held on 25 November and 9 December 2025On the agenda
53East of Gamston/North of Tollerton Development Framework Supplementary Planning DocumentThis decision

Who was there

6 of 17 attended
NC
Councillor Neil ClarkeChair, present
AB
Councillor Abby BrennanVice-Chair, present
RI
Councillor Rob InglisCommittee Member, present
RU
Councillor Roger UptonCommittee Member, present
DV
Councillor Davinder VirdiCommittee Member, present
JW
Councillor Jonathan WheelerCommittee Member, present
LA
Leanne AshmoreOfficer, in attendance
DB
Dave BanksOfficer, expected
CC
Charlotte Caven-AtackOfficer, expected
RC
Rachel ClackOfficer, in attendance
AH
Adam HillOfficer, in attendance
PL
Peter LinfieldOfficer, in attendance

All 17 on the meeting page

On this subject at Rushcliffe

Search all
  1. East of Gamston/North of Tollerton Development Framework Supplementary Planning DocumentThis decision
  2. East of Gamston/North of Tollerton Development Framework Supplementary Planning DocumentApproved
  3. East of Gamston/North of Tollerton Development Framework Supplementary Planning DocumentApproved

More from Rushcliffe Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Local Centre Investment PlansIt was RESOLVED that Cabinet: a) supports the creation of a £1m Towns Fund to be recommended for inclusion in the Med... Approved Open
13 Oct 2026 Council Tax Policy Changes (Second Homes Premium and Relief for Terminally Ill Residents and Foster Carers)It was RESOLVED that the recommendations from Communities Scrutiny Group be considered and that: a) the revocation of... Approved Open
13 Oct 2026 Ratcliffe on Soar Local Development OrderIt was RESOLVED that : a) the should remain in force in its current form and that no amendments are required at the p... Decided Open
8 Sep 2026 Quarter 1 Finance ReportIt was RESOLVED that the report be approved and the following be noted: a) the projected revenue budget efficiency fo... Approved Open
14 Jul 2026 Financial Outturn 2025-26It was RESOLVED that: a) the 2025/26 revenue position and efficiencies identified in Table 1 and Appendix A and B be ... Noted Open