RESOLVED that ( i ) the recommendations for the allocation of grant funding, totalling £43,530.37, as set out in Table 1 of Appendix 1 of the Corporate Director’s Report No. CD1502 ,be approved; (ii) the recommendations for the allocation of funding, subject to further details, as set out in Table 2 of Appendix 1, be approved; (iii) applications requiring further details be determined by the Cabinet Member for Environment and Service Delivery, in consultation with the Corporate Director, subject to the applications continuing to meet the Scheme’s criteria and the total budget not being exceeded; and (iv) a composite project for Grosvenor Road / Upper Union Street and Station Road be developed, in conjunction with the applicants.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
2.1The aim of the Shop Front Improvement Scheme is to stimulate the improvement of shop fronts and building facades and support the economic vitality and attractiveness of the area.
2.2Owners or occupiers of commercial buildings within Aldershot town centre were invited to apply for a grant to improve and enhance their shop fronts, windows, doors and signage in a traditional and sympathetic manner, either through repair of existing traditional features or reinstatement of historic architectural details.
2.3The scheme prioritises small and independent businesses, and preference is given to those businesses with less than five locations in the UK, although applications from larger businesses are not excluded.
3.0APPLICATION PROCESS AND ADMINISTRATION
3.1The deadline for applications was 18 May 2015, and a total of 36 applications were received.
3.2The applications have been evaluated by officers, in conjunction with the Environment and Service Delivery Portfolio Holder, and recommendations for the allocation of grant funding are attached as Appendix 1.
3.3The recommendations fall into three categories:
Fully costed applications, which are recommended for approval (Table 1) Applications where further details are required before final approval can be granted (Table 2) Applications which are recommended for refusal (Table 3) 4.0 COMPOSITE PROJECTS
4.1During the evaluation process, it was noted that very similar outline applications had been received from neighbouring premises in Grosvenor Road and Upper Union Street and between 14 – 20 Station Road. Appendix 2 provides a map showing the location of the premises and an initial sketch of the proposed shop front.
4.2In view of the works already undertaken as part of Activation Aldershot in Grosvenor Road and the prominent location of the properties in Station Road, it is felt that there is potential to develop these applications into schemes which really exemplify the benefits of the Shop Front Improvement Scheme.
4.3It is therefore proposed that officers will work with the applicants for these premises to develop a single coherent scheme, which will be agreed by the Environment and Service Delivery Portfolio Holder together with the Corporate Director.
Recommendations
5.1Cabinet are recommended to agree the recommendations for the allocation of grant funding, totalling £43,530.37, as outlined in Table 1 of Appendix 1 the recommendations for the allocation of funding, subject to further details, as outlined in Table 2 of Appendix 1 that applications requiring further details be determined by the Environment and Service Delivery Portfolio Holder together with the Corporate Director, subject to the applications continuing to meet the Scheme’s criteria and the total budget not being exceeded that a composite project be developed for Grosvenor Road/ Upper Union Street and Station Road, in conjunction with the applicants.
__________________________________________________________________ David Quirk Corporate Director
Background papers: Aldershot town centre shop front improvement scheme - Report No. DCE1502 APPENDIX 1 - ALDERSHOT TOWN CENTRE SHOP FRONT IMPROVEMENT SCHEME
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.