RESOLVED that ( i ) approval be given to a variation in the Capital Programme, as set out in the Solicitor to the Council’s Exempt Report No. LEG1602, to allow for the conversion works to be tendered and the build contract awarded; and (ii) the Head of Financial Services, in consultation with the Cabinet Member for Corporate Services, be authorised to approve an increase in the Capital Programme, subject to the scheme delivering a rate of return of at least 7%, should the tender process exceed £260,000.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
On the 1st September 2015 cabinet approved a proposal for the conversion of 12 Arthur Street, the former Relate premises, to 3 residential flats. The Solicitor to the Council was given authority to submit a planning application and to go to tender for the conversion works. A small budget of £8000 was given to enable the architect working on the scheme to draw up schematic plans to show the feasibility of the conversion. These plans have been prepared and show a scheme for 2 x 2bed flats and 1 x1 bed flat.
Planning
It has been established that planning permission is required as the Relate offices were used for counselling purposes and thus the conversion will be change of use from D1 (non-residential institution) to C3 (dwelling houses). Initial meetings with the planning management service has indicated that planning permission will be recommended subject to SPA contributions and parking being provided in accordance with standards. It is proposed to provide one parking place on the frontage and it is thought that two places will need to be provided off site rather than on street with residential parking permits.
Conversion Works
The previous Cabinet Report outlined a draft budget for limited conversion works at £90,000. However, further inspection by the architect has shown that a complete overhaul of the electrics, plumbing and heating is required for the conversion works to take place, as well as the reconfigurations of several rooms and reconstruction of several walls that are not up to the required standards for residential. The services are in a poor state of repair, and since this is a residential development all risks should be eliminated as far as possible. The works have not yet been tendered but an indictative figure of £260,000 has been given. The value of the flats as converted in the previous Cabinet Report were given as between £140,000 and £150,000. Having had plans prepared and being able to create 2 two beds flats and 1 one bed flat, the revised values are £215,000 for a 2 bed flat and £175,000 for the one bed flat thus the increased costs of the conversion works (up to £170,000 more subject to tender) is likely to be met by the increased in value from between the previously given £420,000- £450000 to £605,000.
Returns for each option
The Cabinet previously made no decision whether the converted flats should be sold or rented but deferred the decision to the Solicitor to the Council in consultation with the Cabinet Member for Corporate Services so that the decision could be taken when further works had progressed towards the establishment of a housing company to overcome the trading issue and any HRA / Right to Buy issues. Work has now been commissioned from Arlington Close looking at their recommended company structure and officers will be considering the report received. It is proposed that no decision be taken as to whether to sell the conversion or rent the flats until the works have been completed but this report updates the projected returns for both options.
The cost of converting the ground and 1st floor offices into 2x 2 bedroom flats, and refurbishing the 2nd and 3rd floor 1 bedroom duplex would require a budget of £260,000- see Table 3 below
Conversion with rental
Table 2 below shows that 12 Arthur Street can be expected to achieve a total income of £28,000 per annum as per the attached table. This will result in a potential rate of return of 9.4% upon the capital required for the conversion. This is a much higher rate of return than is expected in the current market conditions.
Conversion and Disposal
This involves undertaking the works and disposing of the flats.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.