Rushmoor Borough Council
Cabinet, Tuesday 20 September 2016 at 7.00pm

UNION STREET EAST REGENERATION

Approved Executive 1 paper

Cabinet approved this item on Tuesday 20 September 2016. Below is the council's own wording, with the papers it was decided on.

Item46

Resolved

RESOLVED that (i) the redevelopment of the Union Street East and former Marks and Spencer Key Site, as identified in Appendix 1 of the Solicitor to the Council’s Report No. LEG1612, be approved; (ii) the details of the project be taken to the Aldershot Regeneration Group; (iii) the capital cost for the acquisition of the four Union Street properties stated in the Report, as set out in the confidential Appendix 2 of the Report, be approved; (iv) the full year revenue costs associated with the property acquisitions, as set out in the confidential Appendix 2 of the Report, be approved; (v) the urgency decision to acquire Nos. 60 – 62 Union Street, Aldershot be noted; (vi) the Head of Financial Services be authorised to : - accept any grant funding towards the costs of the redevelopment and to enter into any prudential borrowing arrangement, subject to appropriate safeguards, to increase the viability of the scheme; - submit expressions of interest and to enter into any loan or grant agreements with the Local Enterprise Partnership or the Homes and Communities Agency necessary in respect of the redevelopment of the key site; (vii) the Solicitor to the Council be authorised to: - negotiate and acquire by agreement Nos. 60 - 62 Union Street, Nos. 54 – 56 Union Street / Nos. 53 – 55 High Street, No. 52 Union Street, No. 50 Union Street and No. 36 Union Street within the key site area, at the price set out in the confidential Appendix 2 of the Report and subject to confirmation from the Council’s valuer or the Council’s external Compulsory Purchase Order adviser that the price represents the appropriate open market value; - enter into ... view the full minutes text for item 46.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Background

2.1The eastern end of Union Street contains a number of large buildings which have proved difficult to adapt and have gradually fallen into low value use or vacancy over the last few years. The sloping site and the need to have frontages onto both Union Street and the High Street means that the existing building are not best suited to modern retail requirements.

2.2The Aldershot Town Centre Prospectus SPD, adopted January 2016, forms a material planning consideration for development management decisions within Aldershot. It provides the planning framework to allow the council to seek development partners and intervene where necessary to acquire these properties, either by agreement or using its compulsory purchase powers, in order to assemble a development site(s) and seek development partner(s) to build out a mixed use scheme to regenerate this area of the town. The SPD envisages a development of mixed retail / leisure and other town centre uses with residential above.

2.3The SPD envisages either this Key Site coming forward in two parts; 48-62 Union Street/51-57 High Street as a refurbishment scheme, as a public sector led development partner procurement, and the former M&S for redevelopment with a private sector development partner; or that the site could come forward as a whole. In respect of 48-62 Union Street/51-57 High Street, the SPD seeks to retain, where possible, the historic frontage. The SPD also seeks to secure a pedestrian link through the former Marks and Spencer Store from the High Street to the Wellington Centre and the creation of a town square. 3. DEVELOPMENT OPTIONS

3.1In October 2014, prior to the closure of M&S, Montagu Evans were commissioned to undertake some high level site feasibility work on the Union Street East site comprising 51 High Street, 50-52 Union Street, 53-55 High street/54-56 Union Street, 57 High Street/58 Union Street, and 60-62 Union Street. This work advised that if the Council chose not to act, then the private sector alone would be unlikely to deliver the necessary transformation. Further, the advice was that it would be very challenging to gain access to upper floors to provide residential without further compromising ground floor retail space, which is already poorly configured. The report explained that it was likely that the complexity of ownership patterns, weak retail demand and concerns over viability have been private sector inhibitors in bringing the site forward.

This feasibility work for the Union Street East site considered some indicative schemes, namely Low, Mid and High Level interventions (as outlined below). The land assembly costs in support of this work were estimated at this point in time.  The Low Level intervention looked at refurbishment of the retail space with residential above;  The Mid-Level intervention consisted of refurbishment of 50-52 and 60-62 Union Street and 51 High Street; redevelopment of 54-58 Union Street and 53-57 High Street and retention of the High Street façade providing 2,210sqm of new residential development (now 34 units).  The High Level intervention consisted of complete demolition and redevelopment of the existing site, delivering approx. 44 units.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UNION STREET EAST REGENERATIONReport 425 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
SC
Councillor Sue CarterCommittee Member, present
BH
Councillor Barbara HurstCommittee Member, present
GL
Councillor Gareth LyonCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

On this subject at Rushmoor

Search all
  1. UNION STREET EAST REGENERATIONThis decision
  2. Determination of an application to transfer a premises licence in respect of pizza gogo, no. 5 union street, aldershotDecided
  3. Determination of an application for the review of a premises licence in respect of pizza gogo, no. 5 union street, aldershotDecided
  4. Determination of an application a premises licence in respect of no. 47 union street, aldershotAgreed
  5. Determination of an application a premises licence in respect of no. 88 union street, farnboroughAgreed
  6. Aldershot regeneration update - union street, aldershotNoted

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies