FUNDED SUPPLEMENTARY ESTIMATE FOR AIR QUALITY FEASIBILITY STUDY ON THE A331

Noted Executive 1 paper

Cabinet noted this item on Tuesday 17 October 2017. Below is the council's own wording, with the papers it was decided on.

Item39

Resolved

RESOLVED that (i) the additional duties placed on the Council and the deadlines for completion of the key milestones, as set out in Report No. EHH1729, be noted; (ii) an income and expenditure supplementary estimate of £50,000 in 2017/18 be approved; (iii) noting that further work may also be granted funded by DEFRA, future income and expenditure through the budget monitoring process be approved, with the expectation that expenditure would be kept in line with income; and (iv) the approach being taken to this work, as set out on the Report, be approved, noting that the final Plan would require approval by the Cabinet.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

CABINET COUNCILLOR MARTIN TENNANT 17th October, 2017 ENVIRONMENT AND SERVICE DELIVERY PORTFOLIO HOLDER REPORT NO. EHH 1729

KEY DECISION - NO

FUNDED SUPPLEMENTARY ESTIMATE FOR AIR QUALITY FEASIBILITY STUDY ON THE A331

SUMMARY AND RECOMMENDATIONS:

The purpose of this paper is to seek Cabinet approval for an income and expenditure supplementary estimate of £50,000 in 2017/18. The Council has been required, and fully grant funded by DEFRA, to undertake a “Proposal for a Feasibility Study” into measures to improve air quality along the A331.

It is recommended that Cabinet:  note the additional duties placed on the Council, and the deadlines for completion of key milestones  approve an income and expenditure supplementary estimate of £50,000 in 2017/18 and, noting that further work may also be grant funded by DEFRA, approve future income and expenditure through the budget monitoring process, with the expectation that expenditure will be kept in line with income  endorse the approach being taken to this work as described in the report, noting that the final Plan will require Cabinet approval.

1. INTRODUCTION AND BACKGROUND

1.1The UK Plan for tackling roadside nitrogen dioxide (NO2) concentrations, published on 26 July 2017, sets out how the Government will improve air quality to meet EU targets. Rushmoor Borough Council, along with Guildford and Surrey Heath, have been named within the Plan due to modelled exceedances of the annual mean NO2 limit value along the A331 (Blackwater Valley Relief Road). This requires local assessments (Feasibility Studies) to be undertaken to consider the best options to achieve compliance.

1.2The first required deliverable is the submission of a ‘Proposal for a Feasibility Study’, due by November 2017. DEFRA have allocated a grant of £50,000 to each Borough to develop this initial work. All three Boroughs have agreed to work collaboratively and the Government supports this approach. The Final Plan, to be completed by December 2018, will be considered by Members when presented to Cabinet at that time. 2. LEGAL IMPLICATIONS

2.1The requirement to undertake this work is set out in the Environment Act 1995 (Feasibility Study for Nitrogen Dioxide Compliance) Air Quality Direction 2017, which came into force on 28 July 2017.

3. FINANCIAL AND RESOURCE IMPLICATIONS

3.1DEFRA have advised that the work will be fully funded and that support will be provided at key stages. The initial resource grant payment has been made under Section 31 of the Local Government Act 2003, to enable the development of a “Proposal for a Feasibility Study”. On approval, further funding will be allocated to undertake the Feasibility Study itself.

3.2The Government has the right to request reimbursement of the grant funding if a task is not progressing within the agreed project timeline. This risk is mitigated by the fact that DEFRA will be working with us and directing the work as it progresses.

4. EQUALITIES IMPACT IMPLICATIONS

4.1No issues arise.

5. CONCLUSIONS

5.1It is recommended that Cabinet:

 Approve an income and expenditure supplementary estimate of £50,000 in 2017/18 and, noting that further work may also be grant funded by DEFRA, approve future income and expenditure through the budget monitoring process, with the expectation that expenditure will be kept in line with income

CONTACT DETAILS:

Report Authors – Richard Ward / [email protected] / 8137 Colin Alborough / [email protected] / 8169

Head of Service – Qamer Yasin / [email protected] / 8640

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FUNDED SUPPLEMENTARY ESTIMATE FOR AIR QUALITY FEASIBILITY STUDY ON THE A331Supplementary 148 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
BH
Councillor Barbara HurstCommittee Member, present
GL
Councillor Gareth LyonCommittee Member, present
MS
Councillor Maurice SheehanCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies