Resolved
RESOLVED that (i) a variation of £210,000 to the Capital Programme for the financial year 2018/19, for the construction of the new Council depot, be approved; (ii) additional General Fund full financial year revenue costs in relation to the supplementary budget at ( i ) above, amounting to £1,260 interest on borrowing in 2018/19 and a minimum revenue provision of £5,250 commencing in the year 2019/20, be approved; (iii) an additional capital budget for further contingency requirements for the construction of the new Council depot of £100,000 for the financial year 2018/19 be approved, with any spend being agreed in consultation with the Head of Financial Services ; and (iv) additional General Fund full financial year revenue costs in relation to the additional contingency budget at (iii) above, amounting to £600 interest on borrowing in 2018/19 and a minimum revenue provision of £2,500 commencing in the year 2019/20, be approved.