RESOLVED that (i) the provision of business rate relief, up to the state aid maximum of €200,000 (approximately £180,000) over three years once the new facility was developed, in line with the Council’s policy for new businesses and an annual rate to be agreed with Gulfstream, be approved; (ii) the provision of up to £100,000 of financial support to Gulfstream, matched by the Enterprise M3 Local Enterprise Partnership, Hampshire County Council and Gulfstream itself, for training, development and relocation services, with the details to be agreed as part of the budget setting process, be approved; and (iii) the provision of a revised estimate to the budget for 2018/19, allowing the release of £10,000 of the £100,000 set out in (ii) above with immediate effect, be approved.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
(i) provide business rates relief up to the state aid maximum of €200,000 (approximately £180,000) over three years once the new facility is developed in line with the Council’s policy for new businesses and an annual rate to be agreed with Gulfstream;
(ii) provide up to £100,000 of financial support to Gulfstream matched by the Enterprise M3 LEP, Hampshire County Council and Gulfstream itself for training, development and relocation services with the detail to be agreed as part of the budget setting process; and
(iii) provide a revised estimate to the budget for 2018/19 allowing £10,000 of the above £100,000 with immediate effect.
1. INTRODUCTION
1.1The Council was advised by the Department for International Trade (DIT) a competitive UK wide process was underway to identify a site for Gulfstream to accommodate the relocation and expansion of its Maintenance Repair and Overhaul (MRO) facility from Luton Airport.
1.2TAG Farnborough airport expressed an interest to the DIT and engaged the Council, the Enterprise M3 LEP and the County Council in supporting its bid and in providing a package of appropriate support. 2. BACKGROUND
2.1It was announced at EBACE, the business aviation conference in Geneva, at the end of May 2018 that Gulfstream are to locate their new maintenance, repair and overhaul (MRO) facility at TAG Farnborough Airport, and that this new centre will become operational in 2020.
2.2Gulfstream initiated a competitive site selection process in 2015, benchmarking at least 6 alternative airport locations across the UK, and Hampshire County Council, in partnership with Enterprise M3 LEP and Rushmoor Borough Council, developed a public sector support offer to sit alongside the commercial proposition from TAG Farnborough Airport.
2.3Construction of the new 200,000 sq ft facility will commence next year subject to planning permission, on a site within a short distance of the new Farnborough conference and exhibition centre, which opened this year. This major investment will ultimately bring around 400 jobs into Farnborough.
The Company
2.4Gulfstream engineers, manufactures and services prestige business aircraft. Headquartered in Savannah, Georgia, USA, Gulfstream operates facilities on four continents and employs more than 15,000 people worldwide. The Parent company is General Dynamics which employees 95,000 people worldwide.
2.5Since 2003, Gulfstream has conducted major business operations at London Luton Airport and employs circa 300 personnel – the Luton facility primarily serves Gulfstream’s customers in the Europe, Middle East, and Africa (“EMEA”) region.
Project Overview
2.6In 2014, Gulfstream announced two new larger aircraft models (G500 and G600) and it needed to identify a site to develop new larger facilities to perform MRO services more efficiently and cost effectively. Initially 6 airport sites around the UK were shortlisted and assessed. The result being that TAG Farnborough Airport was selected as the preferred location.
2.7Over time it is envisage that the number of staff at the new facility will grow to circa 400, a mix of new and existing roles. Clearly, not everyone will relocate from Luton so the area will benefit from a high number of new well paid and highly skilled jobs. The facility will be 200,000 square feet meaning the Council will benefit from a substantial increase in business rates income. Timescales (indicative)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.