Resolved
RESOLVED that a variation in the Capital Programme of up to £50,000, to enable the necessary repairs to be carried out to the boundary wall at No. 252 Ash Road, Aldershot, as set out in Report No. LEG1810, be approved .
Cabinet approved this item on Tuesday 16 October 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that a variation in the Capital Programme of up to £50,000, to enable the necessary repairs to be carried out to the boundary wall at No. 252 Ash Road, Aldershot, as set out in Report No. LEG1810, be approved .
2.1The property is on the edge of the Blackwater Way Industrial Estate and borders the Blackwater River on the eastern boundary.
2.2Along the eastern boundary is a tall wall, which is the original wall from when the wider site was a gasworks.
2.3When the Council were considering the purchase, the state of the wall was identified as being poor, and it was anticipated that a repair would take place over 4-5 years, with the sum of £10,000 a year that had been allowed in the calculations undertaken by the Council prior to the purchase, to keep the property in repair and maintenance, and for any other issues that arise. 2.4 Since the purchase, further survey work has been undertaken and there has been more movement in the wall than was expected, and as a result, the works need to be undertaken promptly as a matter of urgency.
2.5It should also be noted that the tenant has recently refurbished the interior showroom to a very high standard, and will be refurbishing the exterior in November. This is showing a strong commitment to a site that is of strategic importance to Renault, due to it covering the wider area of both Aldershot and Guildford.
2.6The Council has also been able to agree a re-gear of the existing lease. The tenant currently has 6 years until expiry, and has agreed to a new 20-year lease to supersede the existing one. As a result, the Council will have a significantly longer lease, securing the rental income and increasing the value. This can only occur once the boundary wall has been repaired.
3. DETAILS OF THE PROPOSAL
General 3.1 A range of options have been considered as to how best effect a repair to the wall that will last, while trying to be as economic as possible.
3.2The proposal is to repair the wall in one go, at a cost of £50,000, which will involve demolishing the top half and rebuilding to the same height (the bottom half being in good repair), and strengthening the whole of the wall to lengthen the life by rendering it. This amount is based on a quotation from one of the Councils framework contractors. The final costs will be subject to a formal tender exercise.
3.3This also includes reworking the drainage adjacent to the wall to reduce flooding (the property is situated in an area which is a flood risk), and a contingency for any unforeseen issues.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
REPAIR OF BOUNDARY WALL AT NO. 252 ASH ROAD, ALDERSHOTReport | 87 KB | DownloadRead as text |
Follow Cabinet at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... | Noted | Open |
| 20 Oct 2026 | Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... | Approved | Open |
| 20 Oct 2026 | Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... | Noted | Open |
| 15 Sep 2026 | Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... | Noted | Open |
| 15 Sep 2026 | Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.