ADDITIONAL ITEM - COUNCIL OFFICES - REPLACEMENT HEATING BOILER

Approved Executive 1 paper

Cabinet approved this item on Tuesday 11 December 2018. Below is the council's own wording, with the papers it was decided on.

Item66

Resolved

RESOLVED that approval be given to a variation to the 2018/19 Capital Programme of up to £35,000 to enable the replacement of the faulty boiler to be completed , as set out in Report No. ITFMP1802 .
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Background

2.1The Council Offices is served by two gas boilers, which supply heating to the building. The boilers are several years old and have been regularly maintained through a service framework contract.

2.2On the 30th November, and subsequent inspection and investigation by engineers on the 2nd December, the engineers found that one of the boilers had developed a fault resulting in the mixing of gas and water adjacent to the heat exchange seam. This is a potentially dangerous condition and as such this boiler was immediately condemned and isolated.

2.3The second working boiler was also inspected at this time and has been approved for continued use. In the opinion of the inspecting engineer, there is no need to replace this boiler at this stage, given the maintenance contract. 2.4 The Council Offices is now reliant upon a single heating boiler, however the remaining boiler is not designed to operate at this level and the extra workload could lead to expedited deterioration and failure. Notably, the use of this boiler in this way would leave the offices with no spare heating capacity or contingency in the event of its failure.

2.5The engineer’s advice is that the faulty boiler is beyond repair. The expert advice of the engineers is that the faulty boiler should be replaced with a modern unit and operated in conjunction with the second existing boiler.

2.6The existing flue and ventilation arrangements are not suitable for, or compatible with, modern day standards and will similarly need to be upgraded to accommodate any modern unit. This will inevitably involve scaffolding and roof work and will significantly increase the costs of this work.

2.7The existing maintenance supplier has provide a quotation for replacing the boiler and upgrading the flue system, estimated at £34,782.00.

2.8The Council’s officers are seeking further expert advice on the type of boiler that will integrate with the existing infrastructure, e.g. radiator systems, prior to undertaking the procurement exercise.

2.9Under health and safety legislation, the Council is obliged to ensure the welfare of its staff, customers and fee paying tenants who use its premises. This includes the provision of adequate heating to minimum standards. Notably, the Council also accommodates various tenants and out of hours services (e.g. police, CCTV etc.) who must similarly comply with health and safety obligations and which may require heating provision on a continuous basis.

3. DETAILS OF THE PROPOSAL

Alternative options

3.1Officers have explored the option of a reconditioned boiler, which given the need to comply with building regulations, health and safety, in any event, would not provide the benefits of a more efficient and economical unit.

3.2The installation and use of temporary mobile boiler units has also been explored. However, the rental costs of these are prohibitively expensive and would likely require external installation in the grounds.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ADDITIONAL ITEM: COUNCIL OFFICES: REPLACEMENT HEATING BOILERReport 142 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
BH
Councillor Barbara HurstCommittee Member, present
GL
Councillor Gareth LyonCommittee Member, present
MS
Councillor Maurice SheehanCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open