RESOLVED that the proposed amendment to the development agreement between Rushmoor Borough Council and KPI Limited and St. Modwen , to allow the long-stop date for Block 3 to be extended to 31st October, 2021 and, in relation to Block 4, for work to be commenced within one year of the practical completion of Block 3, with Block 4 to be completed within two years of commencement of work on it, with a long-stop date of 31st October, 2024, be approved.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
The Council has been approached by the Developer to agree an extension to the long-stop dates for completion of Blocks 3 & 4 in the redevelopment of Farnborough Town Centre. The Council as freeholder of the sites retains step-in rights should completion not be achieved by the target dates. In light of recent progress with Block 3 it is reasonable to agree the proposed amendments to achieve completion of the phased delivery of the scheme.
Recommendations
It is recommended that the Cabinet should approve the proposed amendment to the Development Agreement between the Council and KPI Ltd and St Modwen that would allow the longstop date for Block 3 to be 31 October 2021 and in relation to Block 4 for work to be commenced within one year of the practical completion of Block 3 with Block 4 to be completed within 2 years of commencement of work on it, with a longstop date of 31 October 2024.
1. INTRODUCTION
1.1This report seeks authority to agree an amendment to the Development Agreement relating to Kingsmead, The Mead, Firgrove Court and land at Queensmead, Farnborough, Hampshire to provide extended long stop dates for Block 3 and Block 4 of the scheme.
Background
2.1Key Property Investments (KPI) Limited, is seeking a further amendment to the existing Development Agreement with Rushmoor Borough Council in order to enable additional time to complete the development of Block 3 and provide a further long stop date for completion of Block 4, linked to completion of Block 3, which would conclude the outstanding phases of the Farnborough Town Centre North Queensmead redevelopment. 2.2 Outline planning permission was originally granted for a major redevelopment at the northern end of the town stretching across from Queensmead to Firgrove Court and the Kingsmead car park in July 2003. Full planning permission (04/00080/FUL) was subsequently granted on 24th November 2004 for the following:
Demolition and redevelopment to provide retail (A1/A2/A3) space including new superstore, commercial leisure (D2), office (B1a), hotel (C1) and residential accommodation (C3) together with associated provision for access, servicing, parking and landscaping at Kingsmead, The Mead, Firgrove Court and Land at Queensmead, Farnborough
2.3Rushmoor Borough Council, as the freeholder of the site, entered into a Development Agreement with KPI Ltd and St Modwen at the outset of the development scheme. A key component of that agreement is the ability for the Council to ‘step in’ at a certain point should the development be stalled. Step- in rights would enable the Council to step in to the shoes of another party, in this instance KPI Ltd, in relation to the obligations of the Development Agreement and appoint a new development partner to complete the scheme. The current agreement includes a step-in date of March 2021.
2.4The proposals were broken down into 4 phases of development, referred to as Blocks 1-4. Blocks 1 and 2 have been completed and consist of the Sainsbury’s superstore, Travelodge hotel, Wetherspoons public house and town centre retail units alongside residential apartments above. A planning application for a revised Scheme for Block 3 was submitted in February 2019 and has been approved subject to completion of a Section 106 Planning Obligation.
2.5Progress is now being made on the delivery of Block 3. The developer has commenced work on the site but more comprehensive start up and progression on site is subject to the Council agreeing the revised long stop dates.
2.6Some of the delay in getting to this stage can be attributed to the impacts of the financial recession. Further to this, there was a concerted effort to avoid higher ‘void rates’ within the town centre, which would have been the case had additional units been delivered whilst still seeking tenants for Blocks 1 and 2.
3. DETAILS OF PROPOSED COURSE OF ACTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.