Resolved
RESOLVED that the action taken, as set out in the Record of Executive Decision dated 22nd February, 2022, be noted and endorsed.
Cabinet noted this item on Tuesday 15 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the action taken, as set out in the Record of Executive Decision dated 22nd February, 2022, be noted and endorsed.
4.1The contracts will be issued in accordance with industry standards and procured within the Council’s procurement arrangements for an urgent decision
5. Financial and Resource Implications
5.1The estimated cost of all the works now proposals have been received from contractors and evaluated by the Council’s Employers agent and/or property team is now expected to be up to £316,500 plus VAT (Previous estimate £200,000). The Executive Head of Finance is proposing that the works be funded from capital receipts received during the financial year to prevent any impact on the Council’s revenue budget and avoid the need for additional capital borrowing. If this approach is changed then this will be reported as part of the next budget monitoring report.
6. Equalities Impact Implications
6.1There are no equalities impact implications as a result of this decision.
7. CONCLUSION
7.1The works set out in the Record of Executive Decision are essential to stabilise the wall and to enable the Union Yard development to proceed. Cabinet are requested to note the further decision made.
CONTACT DETAILS:
Report Author – Karen Edwards, Executive Director [email protected]
2 APPENDIX
RUSHMOOR BOROUGH COUNCIL RECORD OF EXECUTIVE DECISION
Decision taken by individual Cabinet Member / Officer (delete as appropriate) (All sections must be completed (mark “N/A” as applicable))
DECISION MAKER (Name and designation)
Karen Edwards, Executive Director
DECISION AND THE REASON(S) FOR IT
This Decision is an update on the Decision taken on 10th December 2021 and reported to Cabinet (report ED 2102) on the urgent works required to an exposed party wall at 35-39 High Street, Aldershot.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
URGENT REPAIRS: PARTY WALL AT NOS. 35-39 HIGH STREET, ALDERSHOTReport | 269 KB | DownloadRead as text |
Follow Cabinet at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... | Noted | Open |
| 20 Oct 2026 | Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... | Approved | Open |
| 20 Oct 2026 | Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... | Noted | Open |
| 15 Sep 2026 | Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... | Noted | Open |
| 15 Sep 2026 | Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.