2022-23 HIGH-RISK BUDGETS, FINANCIAL REPORTING PLAN AND BUDGET MONITORING PROCESS

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 5 July 2022. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that (i) the high-risk budgets and pressures, as reviewed and agreed by the Council’s Executive Leadership Team and set out in Section 2 of Report No. FIN2223, be noted ; (ii) the high-level financial reporting timetable for completion and presentation to Cabinet for 2022/23, as set out in Section 3 of the Report, be approved; and (iii) the budget monitoring process, with early service management action to ensure timely completion and to enable robust forecasting for presentation to the Cabinet on 2022/23 revenue and capital budget monitoring reports, as set out in Section 4 of the Report, be approved.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Recommendations

CABINET is recommended to:

i. Note the high-risk budgets and pressures as reviewed and agreed by the Executive Leadership Team (as detailed in Section 2).

ii. Note and approve the high-level financial reporting timetable for completion and presentation to Cabinet for 2022-23 (as detailed in Section 3).

iii. Note and approve the budget monitoring process with early service management action to ensure timely completion and to enable robust forecasting for presentation to Cabinet on 2022-23 revenue and capital budget monitoring reports (as detailed in Section 4).

1 INTRODUCTION

1.1As part of the Finance Improvement Plan this report sets out for Cabinet the intended budget monitoring process for 2022-23 that will be undertaken, with Heads of Service and their management teams leading and owning the forecasts for the budgets they are responsible for.

1.2Heads of Service, cost centre managers and the Finance Team will continue to work collaboratively, with Finance increasingly adopting a finance business partnering approach to support, advise, and provide a ‘check and challenge’ service managers to validate forecast assumptions and to enable managers to deliver the Council’s services within the approved budget.

1.3The high-risk budgets have been identified and discussed by ELT and CMT and a rolling record will be maintained of these throughout the year. The known pressures and estimated risks will be updated as additional information becomes available and will be expanded as necessary to include new pressures and risks as there are identified.

2 HIGH-RISK BUDGET ASSESSMENT AND PRESSURES

2.1The high-risk budgets and known pressures record has been updated from 2021-22 following on from the latest information obtained through the draft outturn and closing processes. The updated and current position for new and existing risks and pressures going into 2022-23 are:

2.1.1 £0.500m to £0.750m risk Interest Payable Risk – there is a risk that Treasury Management Interest Payable costs result in higher debts costs than the MTFS projection due to:

• Up to £0.750m potential risk due to movement in both short-term and long- term interest rates since the MTFS forecast in January 2022. This assumes that the Council takes out an additional £35m of borrowing as per Capital Programme with a mix of short-term and long-term rates.

• The MTFS assumed short-term rates of around 0.75% to 0.80% and PWLB at around 2.10%. However, since then the Bank of England base rate increases mean that current rates are around 1.80% for short-term rates (lending from other Local Authorities) and 3.50% for PWLB. PWLB rates continue to change and as at the final report are moving towards 4% level of long-term borrowing following Bank of England latest base rate increase on 10th June 2022 to 1.25%.

• With the increased interest rates the Council will need to ensure adequate mitigation is in place. The cost of borrowing is above the estimates included in the MTFS and as rates are likely to continue to fluctuate, the timing a scale of any further borrowing must be reviewed. Mitigation is likely to be looking at the availability of alternative funding sources (Capital Receipts), borrowing is delayed/revised, or through the review of longer-term investments and other assets that the Council holds. Treasury Management investment income may improve (although this is unlikely to have a material impact) and will therefore become a pressure within the year to fund.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2022-23 HIGH-RISK BUDGETS, FINANCIAL REPORTING PLAN AND BUDGET MONITORING PROCESSReport 256 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
JC
Councillor Jonathan CantyCommittee Member, present
SC
Councillor Sue CarterCommittee Member, present
DC
Councillor David CliffordChairman, present
AN
Councillor Adrian NewellCommittee Member, present
MS
Councillor Maurice SheehanVice-Chair, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantVice-Chair, present

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies