Resolved
RESOLVED that the Prudential Indicators for 2023/24 be reviewed by the Council’s treasury management advisors ( Arlingclose ) for completeness with any update to be included in the report to the Council on 23rd February 2023.
Audit and Governance Committee decided this item on Monday 30 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Prudential Indicators for 2023/24 be reviewed by the Council’s treasury management advisors ( Arlingclose ) for completeness with any update to be included in the report to the Council on 23rd February 2023.
The Council is required to approve a Capital Strategy for 2023/24 before 1 April 2023.
The Capital Strategy 2023/24 (Appendix 1) is in accordance with CIPFA’s “Prudential Code” and the “Treasury Management Code of Practice” 2017, and the Ministry of Housing, Communities and Local Government (MHCLG) guidance on Local Government Investment.
Members are requested to recommend to Council:
(i) Approval of the Capital Strategy for 2023/24 to 2025/26 and Prudential Indicators for 2023/24 (subject to (ii) below); (ii) The Prudential Indicators for 2023/24 will be reviewed by the Councils Treasury Management advisors Arlingclose for completeness with any update included in the report to Council on 23 February 2023.
1 INTRODUCTION
1.1This report sets out the proposed Capital Strategy for the year 2023/24 to 2025/26, including the Prudential indicators for capital finance for 2023/24.
1.2This capital strategy report gives a high-level overview of how capital expenditure, capital financing and treasury management activity contribute to the provision of local public services along with an overview of how associated risk is managed and the implications for future financial sustainability.
1.3Decisions made this year on capital and treasury management will have financial consequences for the Authority for many years into the future. They are therefore subject to both a national regulatory framework and to local policy framework, summarised in this report. 1.4 The Council follows best practice by adhering to the Chartered Institute of Public Finance and Accountancy’s Treasury Management in the Public Services: Code of Practice 2017 (the CIPFA Code), incorporating any subsequent revised guidance. Subsequently the Council approves both a Capital Strategy and the related Treasury Management Strategy before the start of each financial year.
2 PURPOSE
2.1The purpose of the Capital Strategy is to give an overview of how capital expenditure; capital financing and treasury management activity contribute to the provision of local public services along with an overview of how associated risk is managed and the implications for future financial sustainability.
2.2The purpose of investment management operations is to ensure that all investment decisions that are made primarily to generate a profit have a suitable level of security and liquidity. Ensuring risks and rewards are monitored regularly.
2.3The second main function of the Capital Strategy is to set the Prudential indicators for affordable, prudent and sustainable capital investment.
2.4Appendix 1 sets out the Capital Strategy for 2023/24 to 2025/26 and fulfil key legislative requirements as follows:
• The Capital Strategy sets out a high-level overview of how capital expenditure, capital financing and treasury management activity contribute to the provision of local public services along with an overview of how associated risk is managed and the implications for future financial sustainability. It has been written in accordance with CIPFA’s Code of Practice on Treasury Management, the CIFPA Prudential Code and MHCLG guidance on local government investments.
These policies and parameters provide an approved framework within which officers undertake the day-to-day capital, treasury and non- treasury investment activities.
3 SCOPE
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Capital Strategy 2023/24Report | 181 KB | DownloadRead as text |
Follow Audit and Governance Committee at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. | Noted | Open |
| 29 Sep 2026 | Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. | Noted | Open |
| 29 Sep 2026 | Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... | Approved | Open |
| 29 Sep 2026 | Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... | Noted | Open |
| 30 Jul 2026 | Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.