RESOLVED that: (a) the revised costs of the current stage of planning and design work (RIBA Stage 3) of £386,855, as set out in Report No. REG2402, be noted; (b) an initial sum of £50,000 towards potential redesign work be approved; (c) the undertaking of a costing exercise by Willmott Dixon on the RIBA 3 designs, to provide market tested costs for consideration before the decision to move to the next stage of design and development (RIBA Stage 4), be approved; (d) the undertaking of a pre-planning consultation exercise in March, on the designs at the conclusion of the RIBA 3 design process, be approved; (e) the adjustment in the overall project timeline, to take into account the market costing exercise and provide a period for any necessary design revisions as a result of the report and the pre-planning public consultation exercise, as set out in the Report, be noted; (f) the undertaking of work as part of the Council’s Financial Resilience Plan to address the affordability of the current and future capital programme and the links to the decision to move fully to the next stage of design and development (RIBA Stage 4) be noted; (g) the revised funding strategy for the project, given the position set out in the 2024/25 budget report and supporting Financial Resilience Plan, be noted; (h) the approach to the demolition of the Pinehurst Car Park and the temporary relocation of the Council’s car boot sale to the High Street multi-storey in Aldershot be noted; and (i) the use of any slippage on the Civic Quarter capital budget in 2023/24 to progress elements of the Civic Quarter regeneration programme, ... view the full minutes text for item 50.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
CABINET 6th February COUNCILLOR MARTIN TENNANT 2024 MAJOR PROJECTS AND PROPERTY PORTFOLIO HOLDER
REPORT NO. REG2402 KEY DECISION? YES
FARNBOROUGH REGENERATION AND LEISURE AND CULTURAL HUB – NEXT STEPS
SUMMARY AND RECOMMENDATIONS:
In January 2023 the Government announced that the Council’s bid for £20m Levelling Up funding to support the delivery of a Leisure and Cultural Hub in Farnborough had been successful. In March 2023 Cabinet considered a report (REG2303) which identified the next steps in the project, authorised allocation of funding to enable work to commence and confirmed that Council should enter into a Memorandum of Understanding with Government to enable the drawdown of funding. That report also provided budget to enable the project to procure a Leisure Operator to commence.
In October 2023 Cabinet approved the final project scope, schedule of accommodation and the forecast budget required to complete the pre-construction phases of the project and to submit the planning application. That report also set out the proposed funding strategy for the project.
This report provides an update to the Cabinet on the project and operator procurement. It then considers options for the next stages of the project taking into account the work undertaken since October, impacts of inflation and implications for the current funding strategy given the position relating to the Council’s future capital programme as set out in the 2024/25 budget report.
It is Recommended that Cabinet:
1) Notes the revised costs of the current stage of planning and design work (RIBA stage 3) of £386,855 and agrees an initial £50,000 towards potential redesign work and Recommends that the Council agrees to an increase in the Capital budget for 23/24 of £255,000 funded by a further draw down from the Levelling Up grant. 2) Agrees that a costing exercise be undertaken by Willmott Dixon on the RIBA 3 designs to provide market tested costs for consideration before the decision to move the next stage of design and development (RIBA Stage 4) 3) Agrees pre-planning public consultation be undertaken in March on the designs at the conclusion of the RIBA 3 design process. 4) Notes the adjustment in the overall project timeline to take into account the market cost exercise and to provide a period for any necessary design revisions as a result of the report and the pre-planning public consultation. 5) Notes the work being undertaken as part of the Council’s Financial Resilience Plan to address the affordability of the current and future capital programme and the links to the decision to move fully to the next stage of design and development (RIBA stage 4). 6) Notes the revised funding strategy for the project given the position set out in 2024/25 budget report and supporting Financial Resilience Plan 7) Recommends that Council agrees to the inclusion of the £1.725m One Public Estate Brownfield Land Release Fund grant in the 23/24 and 24/25 capital programme, as appropriate, to enable the demolition of the Pinehurst car park and site preparation and utilities work across plots established by the Civic Quarter masterplan. 8) Notes the approach to the demolition of the Pinehurst Car Park and the temporary relocation of the Council’s Car Boot sale to the High Street multi- storey car park in Aldershot. 9) Agree that any slippage on the Civic Quarter capital budget in 2023/24 be used to progress elements of the Civic Quarter regeneration programme where this could lead to improved land values in line with the Financial Resilience Plan
1 INTRODUCTION AND BACKGROUND
1.1Since 2019, the site of the former Farnborough Recreation Centre, Plot B on the Civic Quarter Masterplan (See Figure 1 below) has been identified for the development of a new leisure centre.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.