BUDGET MANAGEMENT - MONTH 5

Noted Executive 1 paper

AI summaryCabinet noted the 2025/26 revenue and capital budget forecasts as at the end of August 2025, with the £1.8m savings target met against a £3.4m planned reserve drawdown, while flagging risks from rising interest rates, disposal delays and a Crematorium VAT breach.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFor 2025/26 at end of August 2025
Money£1.8m savings target achievedAgainst £3.4m planned reserve drawdown
What happens nextContinue monitoring and reportingCost controls available if needed
Who it affectsCouncil finances and capital projectsCrematorium, property portfolio, borrowing

What was decided

Cabinet noted the revenue budget forecast set out in Section 3 of Report No. FIN2516.

Cabinet noted the capital budget forecast set out in Section 4 of Report No. FIN2516.

Why

The council has a legal obligation to produce a balanced budget and must achieve its revenue and capital receipt targets through the Financial Recovery Plan. Report 6.1

The financial position over the MTFS period continues to be challenging, though progress is being made. Report 9.3

The latest forecast shows the 2025/26 savings target has been achieved against a planned reserve drawdown of £3.4m. Report 9.1

What happens next

Officers will continue to monitor the financial position closely and report updates regularly to councillors. Report 9.3

If the in-year financial situation determines, cost controls can be implemented to slow expenditure until the situation is resolved. Report 9.2

The Executive Head of Finance will consult at the earliest indication that targeted or broader temporary expenditure control is required. Report 6.2

The money

  • £3.4m Planned reserve drawdown in 2025-26 balanced budget Report 9.1
  • £1.8m Net budget reduction savings target for 2025-26, now achieved Report 9.1
  • £64m Total debt maturing between October 2025 and June 2026 Report 8.1
  • 4.78% Assumed interest rate for longer than one year maturity replacement borrowing Report 8.1
  • £498k Forecast VAT cost for capital arising from Crematorium partial exemption breach Report 8.6
  • £97k Forecast revenue VAT impact from Crematorium partial exemption breach Report 8.6

Options considered

  • Rejected: Do nothing. The council has a legal obligation to produce a balanced budget; there is no Do Nothing option. Report 6.1
  • Rejected: Introduce targeted or broader temporary expenditure control to hold back expenditure and reduce drawdown on reserves. Available if financial situation warrants; the Executive Head of Finance will consult at the earliest indication it is required. Report 6.2

Implications

  • Financial: Interest rate volatility on borrowing remains a risk; £64m of debt maturing between October 2025 and June 2026 may not be replaceable at the assumed 4.78% rate and longer than one year maturity. Report 8.1
  • Financial: Delays to capital receipts disposals are impacting borrowing costs in year and may affect 2026/27 interest and MRP savings if they fall into next year. Report 8.2
  • Financial: Crematorium refurbishment project delays are negatively impacting the 2025/26 income position, with a forecast VAT partial exemption breach of £498k capital and £97k revenue; officers are challenging the position with tax consultants. Report 8.5, 8.6
  • Risk: Property portfolio rental streams support debt costs; properties remain at risk of vacancies which prevent income and may incur rates, maintenance and security costs. Report 8.4
  • Financial: The financial performance of the energy centre at Union Yard is impacted by disposals of residential units block C and D and uptake of the service by commercial tenants. Report 8.3
  • Legal: Under the Council's Finance Procedure Rules, the Executive Head of Finance is responsible for proper administration of financial affairs; Executive Directors and Heads of Service must consult before incurring commitments liable to affect finances materially. Report P12
  • Equalities: No direct equalities impact identified. Report 8.9

Who and where

  • Rushmoor Borough Council finances and reserves Report 9.1, 9.3
  • Crematorium refurbishment project (income, VAT recovery, overall project cost) Report 8.5, 8.6
  • Council property portfolio tenants and rental income streams Report 8.4
  • Union Yard energy centre, residential units blocks C and D and commercial tenants Report 8.3
  • Capital receipts disposal programme and 2026/27 financial year Report 8.2

Timeline

  • 27th February 2025: General Fund Budget 2025/26 and Medium Term Financial Strategy 2025/26 to 2028/29 set by Council. Report P24
  • 8th July 2025: Budget Management Outturn 2024/25 reported. Report P24
  • End of August 2025: Forecasted financial position for 2025/26 reported.
  • October 2025 to June 2026: Period over which £64m of debt is due to mature and require refinancing. Report 8.1
  • End of 2025/26 financial year: Final position on Crematorium VAT partial exemption breach expected to be known. Report 8.6
  • 2025-10-14: Cabinet considered Report No. FIN2516 and noted the revenue and capital budget forecasts.

Plain English for the jargon

  • MRP: Minimum Revenue Provision, the amount councils must set aside from revenue to repay debt.
  • MTFS: Medium Term Financial Strategy, the council's multi-year financial planning document.
  • PWLB: Public Works Loan Board, a UK government body that lends to local authorities.
  • Inter Authority borrowing market: Market where local authorities lend to one another, usually offering maturities less than 2 years.
  • CAMEO reserve: A ringfenced reserve likely to be the first call for the Crematorium revenue VAT impact.
  • Capital receipts: Income from the sale of council assets such as property.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item31

Resolved

RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2516, be noted; and (ii) the capital budget forecast, as set out in Section 4 of the Report, be noted.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

CABINET COUNCILLOR GAYNOR AUSTIN FINANCE & RESOURCES PORTFOLIO HOLDER 14TH OCTOBER 2025 REPORT NO. FIN2516

KEY DECISION? NO

BUDGET MANAGEMENT – MONTH 5

SUMMARY AND RECOMMENDATIONS: This report sets out the forecasted financial position for 2025/26 as at the end of August 2025.

CABINET is recommended to:

i. Review the Revenue budget forecast as set out in Section 3 of the report. ii. Review the Capital budget forecast as set out in Section 4 of the report.

1. INTRODUCTION

1.1The Budget is a major decision for the Council and setting and maintaining a balanced budget is a statutory requirement. This report provides an update on the forecasted outturn position against approved budget for the current financial year 2025/26 based upon service manager information as at the end of August 2025 with additional finance due diligence. Heads of Service, Service Managers and the Finance Team work collaboratively to produce robust forecasts and validate forecast assumptions.

2. BACKGROUND AND EXECUTIVE SUMMARY

2.1The Council has a statutory obligation to set and maintain a balanced budget. In February 2025 the Council identified a significant challenge to its future financial sustainability (as set out at the February 2025 Budget Council).

2.2The forecast outturn for 2025/26 is on track with the full £1.8million savings requirement achieved.

2.3Whilst the council has utilised more of its cashflow to avoid external borrowing, the overall reduction in level of borrowing required in the MTFS can only be achieved through capital receipts.

3. CURRENT YEAR FINANCIAL PERFORMANCE

Revenue Account 3.1. The original net General Fund Revenue budget for 2025/26 was approved by Council at their meeting in February 2025. The latest approved budget also includes budget carry forwards of £101k as noted in the July Outturn report. The month 5 forecast outturn is presented in the table below.

2025-26 2025-26 2025-26 2025-26 Original Approved Forecasted Forecast Budget Budget Outturn Variance £'000 £'000 £'000 £'000 Economy, Skills & Regeneration (4,868) (5,058) (5,382) (324) Finances & Resources 3,873 4,407 4,066 (342) Healthy Communities & Active Lives 3,730 3,792 3,854 61 Housing & Planning 2,613 2,669 2,893 224 Leader/Communications 25 13 16 3 Policy, Performance & Sustainability 578 1,226 1,129 (97) Pride in Place & Neighbourhood 7,929 8,052 8,161 109 Services Subtotal 13,879 15,102 14,736 (366) Less: Reversal of Accounting Entries (2,957) (2,883) (2,883) - Net Service Revenue Expenditure 10,922 12,219 11,852 (366) Corporate Income & Expenditure Minimum Revenue Provision (MRP) 2,133 2,133 2,133 - Interest Receivable (1,402) (1,401) (1,747) (346) Interest Payable 6,490 6,489 6,734 245 Vacancy Savings (400) (400) - 400 Recurrent Savings (1,784) 94 - (94) Pooled Funds 1,000 - - - NI Compensation Grant (152) (152) (137) 15 Union Yard Holding costs provision 221 - - - Capital Contributions - (60) (60) - Irrecoverable VAT - - 97 97 Contract Inflation 362 150 - (150) RCCO - 35 35 - Capital Receipts Flexibility - (311) (311) - Movement in Earmarked Reserves 587 (872) (922) (50) Movement in General Reserves (3,421) (3,368) (3,368) - Net General Fund Revenue Budget 14,556 14,556 14,306 (250) Funded by: Council Tax (8,039) (8,039) (8,039) - Business Rates (5,071) (5,071) (5,071) - Collection Fund (31) (31) (31) - New Homes Bonus (512) (512) (512) - Local Restrictions Support Grant (615) (615) (615) - Other Grant Income - (39) (39) - Funding Guarantee (118) (118) (118) - Revenue Support Grant (170) (131) (131) - Total Funding (14,556) (14,556) (14,556) (0) Core (Surplus)/Deficit - - (250) (250) 3.2. Details of the Month 5 forecast variance by nature is provided below. This table brings the vacancy margin into a service savings total to give a complete service position.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BUDGET MANAGEMENT: MONTH 5Report 415 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
SW
Sun WongCouncil Staff, expected
LC
Louise ClarkeCouncil Staff, expected
GA
Councillor Gaynor AustinCommittee Member, present
KD
Councillor Keith DibbleCommittee Member, present
CG
Councillor Christine GuinnessCommittee Member, present
JH
Councillor Julie HallCommittee Member, apologies
SP
Councillor Sophie PorterVice-Chair, present
GW
Councillor Gareth WilliamsChairman, present

On this subject at Rushmoor

Search all
  1. BUDGET MANAGEMENT - MONTH 5This decision
  2. Budget management - month 4Noted
  3. Budget management - month 10Noted
  4. Budget management - month 8Noted
  5. Budget management - month 3Noted
  6. Budget management - outturn 2024/25Noted

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open