ALDERSHOT SKI CENTRE - CAPITAL EXPENDITURE AND NEXT STEPS

Approved Executive 1 paper

AI summaryCabinet approved £99,000 for short-term capital works to keep Aldershot Ski Centre open, and agreed a full options appraisal on its medium and long term future after a new leisure operator is appointed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital works and strategic business case agreed
Money£99,000£90,000 estimated cost plus 10% contingency
What happens nextOptions appraisal after operator appointedStrategic business case to follow new operator appointment
Who it affectsAldershot Ski Centre usersPublic users, leisure operator, council as owner

What was decided

Cabinet approved £99,000 from the capital allocation for asset maintenance to fund immediately necessary works to keep the ski slope in use in the short term. Report 4.4

Cabinet noted the medium term financial expenditure needed to keep the slope open, and the longer term need for a full refurbishment and repair programme or substantial replacement of the structure. Report 3.4, 3.5

Cabinet approved a full strategic business case and option appraisal on the medium to long term future of the ski slope, to be carried out after the new Leisure Operator is appointed. Report 3.6

Why

The ski structure was built by the army in 1969 from Bailey Bridge trusses, and a wet mist system has caused corrosion and weakening of joints and steel members. Report 2.1, 2.2

A new structural engineer has reviewed prior surveys and advised that work scheduled for 2025 and 2026 needs to be done quickly to keep the slope safe. Report 3.1, P6

A full year's operating income is needed to complete the strategic business case, so the option appraisal must follow the new operator's appointment. Report 3.6

What happens next

Six monthly inspections of the slope continue, with the next inspection scheduled for January, and any serious deterioration will trigger immediate action. Report 3.1

The new leisure operator procurement is due to conclude in February 2026, after which the strategic business case and option appraisal will be carried out with the operator. Report 2.4, 3.6

The Senior Programme and Buildings Manager will progress client side duties including procurement, contract management and site management for the approved works. Report 4.6, P22

The money

  • £99,000 Approved capital allocation for short-term ski slope works, £90,000 estimated cost plus 10% contingency
  • £800,000 Capital allocation for asset management agreed by Council on 27 February 2025 Report 4.4
  • £780,000 Remaining from the £800,000 allocation after £20,000 to Beaumont Community Centre Report 4.4
  • £100,000 Additional 2025/26 budget approved by Cabinet on 3 June 2025 to support reopening Report 4.5
  • £50,000 Prior years annual income from the ski slope site Report 4.5
  • £50K Estimated medium term cost in 2027 Report 3.4
  • £50K Estimated medium term cost in 2028 Report 3.4
  • £45K Estimated medium term cost in 2029 Report 3.4
  • £90K Estimated medium term cost in 2030 Report 3.4

Options considered

  • Chosen: Approve £99,000 of short-term works and a full strategic business case and option appraisal after the new leisure operator is appointed. Needed to keep the slope safe and open while the long term future is assessed with the new operator Report 3.1, 3.6
  • Rejected: Do not undertake the immediately required works and remove the slope from service. Would remove a popular facility from public use, was included in the Leisure Operator procurement, and would prejudice future options before a full appraisal Report 3.7

Implications

  • Risk: Delay in undertaking the work could lead to slope failure and the need to close at short notice to protect users and the Council. Report 4.1, P17
  • Risk: There is a risk the Council will not continue using the ski slope for long enough to achieve best value from the capital expenditure.
  • Legal: No specific legal implications from releasing funds, but assurance that the site remains safe should be sought through the January site inspection. Report 4.3
  • Financial: £780,000 remains in the capital allocation for asset management after a prior £20,000 allocation to Beaumont Community Centre. Report 4.4
  • Staffing: Capacity is available within the Property Services team to progress client side duties for the works. Report 4.6, P22
  • Equalities: No direct equality implications have been identified from this report. Report 4.7, P24

Who and where

  • Users of Aldershot Ski Centre Report 4.1
  • The new Leisure Operator to be appointed in February 2026 Report 2.4, 3.6
  • Rushmoor Borough Council as owner of the asset Report 2.5, 3.7
  • The Council's Property Services team Report 4.6, P22

Timeline

  • 1969: Ski structure constructed by the army from Bailey Bridge trusses Report 2.1
  • 27 February 2025: Council agreed £800,000 capital allocation for asset management Report 4.4
  • April 2025: Active Nation contract terminated and a temporary arrangement with Places for People put in place Report 2.4, 4.5
  • June 2025: Cabinet considered options after Active Nation ceased trading and identified structural repair needs Report 2.4, 2.5
  • 3 June 2025: Cabinet approved an additional £100,000 budget for 2025/26 to support reopening Report 4.5
  • January 2026: Next six monthly structural inspection of the slope scheduled Report 3.1
  • February 2026: New leisure operator procurement due to conclude, with the ski centre included but with options to remove it Report 2.4
  • 2027: Estimated medium term cost of £50K for further structural works Report 3.4
  • 2028: Estimated medium term cost of £50K for further structural works Report 3.4
  • 2029: Estimated medium term cost of £45K for further structural works Report 3.4
  • 2030: Estimated medium term cost of £90K for further structural works Report 3.4

Plain English for the jargon

  • Bailey Bridge trusses: Portable prefabricated steel trusses originally developed for military bridging, here used to form the ski slope's raking frame.
  • Wet Mist System: A water spray system used by operators to aid the ski experience, which has contributed to corrosion of the structure.
  • CDM: Construction (Design and Management) site management duties referenced for the Senior Programme and Buildings Manager.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item52

Resolved

RESOLVED that (i) an allocation of £99,000, consisting of £90,000 of estimated cost and a 10% contingency, from the capital allocation for asset maintenance, to undertake immediately necessary capital works to secure the use of the ski slope in the short term, as set out in Report No. PG2543, be approved ; (ii) the recommendations for the medium term financial expenditure necessary to keep the slope open, along with the need over the longer term, to maintain the structural integrity for public use of the slope, to provide a full refurbishment and repair programme or for the structure to be substantially replaced, be noted; and (iii) following the appointment of the new Leisure Operator, the undertaking of a full strategic business case and option appraisal, to establish the medium to long term future of the ski slope, be approved.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Background

2.1The ski structure was constructed by the army in 1969. This is a steel framed structure comprising of ex-army Bailey Bridge trusses, pinned together and braced with lacing beams to form a raking structure. Above this sits a series of timber planks upon which the ski surface is supported.

2.2The slope operators use a ‘Wet Mist System’ to aid the ski experience. This has led to dripping through the deck and onto the structure, picking up dirt and depositing it onto joints and steel beams. This has then caused corrosion and weakening of joints and truss members.

2.3Various repairs and renovations have been carried out over the years on the structure. Most recently a series of galvanised frames and foundation bases have been installed to provide additional support to the primary structure. Continuous maintenance is ongoing, including the replacement of the timber decks in small sections so that the slope can continue to be in operation. The slope is now detreating at speed due to its age, compounded corrosion, dilapidated condition and most relevantly the continuous saturation from the elements and water spray/mist system.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ALDERSHOT SKI CENTRE: CAPITAL EXPENDITURE AND NEXT STEPSReport 164 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 6 attended
GA
Councillor Gaynor AustinCommittee Member, present
KD
Councillor Keith DibbleCommittee Member, present
CG
Councillor Christine GuinnessCommittee Member, present
JH
Councillor Julie HallCommittee Member, apologies
SP
Councillor Sophie PorterVice-Chair, present
GW
Councillor Gareth WilliamsChair, present

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies